QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION:
Crafter v Jared Nichol Builder Pty Ltd [2023] QCAT 88
PARTIES:
FIONA CRAFTER (applicant)
v
JARED NICHOL BUILDER PTY LTD (respondent)
APPLICATION NO/S:
BDL013-22
MATTER TYPE:
Building matters
DELIVERED ON:
10 March 2023
HEARING DATE:
On the papers
HEARD AT:
Brisbane
DECISION OF:
Adjudicator Stroud
ORDERS:
The application is dismissed.
CATCHWORDS:
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – DEFECTIVE WORKS – where power failure to property caused damage to electrical items _ whether the works carried out by the builder were defective – whether the works carried out by the builder were the cause of the power failure to the property.
Queensland Building and Construction Commission Act 1991 (Qld) s 75, s 77(1), Schedule 2
Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 9, s 10, s 28
APPEARANCES & REPRESENTATION:
This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld)
Applicant:
Self-represented
Respondent:
Self-represented
REASONS FOR DECISION
What is this application about?
Fiona Crafter contracted with Jared Nichol Builder Pty Ltd (builder) to build a wheelchair accessible bathroom (works) at her property. The works included some electrical wiring to the bathroom. Fourteen months after the works were completed Ms Crafter notified the builder that there had been an electrical failure at her residence resulting in damage to several electrical items. Ms Crafter claims the electrical failure was a result of defective work carried out by the builder and seeks an order that the builder compensate her for the cost of replacing the damaged items.
Does the Tribunal have Jurisdiction?
This is a domestic building dispute. The Tribunal has original jurisdiction to hear and decide ‘building disputes’.[1] The definition of building dispute includes a ‘domestic building dispute’. [2]
[1]Sections 9 and 10 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld) (QCAT Act) and s 77(1) of the Queensland Building and Construction Commission Act 1991 (Qld) (QBCC Act).
[2]QBCC Act, Schedule 2 (definition of ‘building dispute’).
A domestic building dispute includes a claim or dispute arising between a building owner and a building contractor related to the performance of ‘reviewable domestic work’ or a claim or dispute in negligence related to the performance of ‘reviewable domestic work’.[3]
[3]QBCC Act, Schedule 2 (definition of ‘domestic building dispute’).
‘Reviewable domestic work’ means ‘Tribunal work’.[4] Tribunal work includes the renovation, alteration, extension improvement or repair of a building as well as the provision of electrical work for a building.[5]
[4]Section 75(2) of the QCAT Act.
[5]Section 75(1)(b) and (c) of the QCAT Act.
I am satisfied that the Tribunal has jurisdiction to hear this dispute.
The relevant facts
On 9 June 2020 the parties entered into a QBCC Level 2 Renovation, Extension and Repair Contract for the works for a contract price of $50.071.20. The works reached practical completion on 24 August 2020.
The works included some electrical work which…
Continue reading Crafter v Jared Nichol Builder Pty Ltd
Sign in free to access the full text
- AGLC
- Crafter v Jared Nichol Builder Pty Ltd [2023] QCAT 88
- Case
- [2023] QCAT 88
- Decision Date
CaseChat Overview and Summary
The central legal issues revolved around whether the Tribunal had jurisdiction over the matter and whether Ms Crafter could prove on the balance of probabilities that the builder's works were defective and caused the electrical failure. Ms Crafter needed to provide sufficient evidence to support her claims, while the builder needed to demonstrate that the works were compliant and that any alleged defects were not the cause of the power failure.
The Tribunal concluded that it had jurisdiction to hear the dispute, as it fell within the definition of a domestic building dispute. However, the Tribunal found that Ms Crafter had not provided sufficient evidence to prove that the builder's works were defective or that these defects caused the electrical failure. The builder presented evidence from the Electrical Safety Office confirming the compliance of the electrical works. Additionally, the builder's electrician provided a detailed explanation addressing the alleged defects, which was corroborated by the Electrical Safety Office's findings. Ms Crafter's evidence relied heavily on hearsay from another electrician, who did not provide a statement in the proceeding. The Tribunal found that the builder had sufficiently rebutted Ms Crafter's claims, and therefore, her application failed to meet the required standard of proof.
The Tribunal dismissed the application and ruled that the builder was not liable for the damages claimed by Ms Crafter. The Tribunal's decision was based on the lack of sufficient evidence to establish the builder's works as defective and the cause of the power failure.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.