Supreme Court
New South Wales
Medium Neutral Citation: CPB Contractors Pty Ltd v Rizzani De Eccher Australia Pty Ltd (No 2) [2018] NSWSC 74 Hearing dates: On the papers Date of orders: 09 February 2018 Decision date: 09 February 2018 Before: Ward CJ in Eq Decision: 1. The defendant is to pay the plaintiff’s costs of the proceedings on the ordinary basis.
Catchwords: COSTS - Party/Party – Urgent proceedings – where plaintiff did not succeed in obtaining the relief sought, but obtained other relief Legislation Cited: Civil Procedure Act 2005 (NSW) ss 56, 98
Uniform Civil Procedure Rules 2005 (NSW), r 42.1Cases Cited: CPB Contractors Pty Ltd v Rizzani de Eccher Australia Pty Ltd [2017] NSWSC 1798 Category: Costs Parties: CPB Contractors Pty Ltd (Plaintiff)
Rizzani de Eccher Australia Pty Ltd (Defendant)Representation: Counsel:
Solicitors:
N Nicholls SC with H Morrison (Plaintiff)
F Hicks SC with D Robertson (Defendant)
Corrs Chambers Westgarth (Plaintiff)
Clayton Utz (Defendant)
File Number(s): 2017/00332074 Publication restriction: Nil
Judgment
-
HER HONOUR: On 19 December 2017, I published my reasons (CPB Contractors Pty Ltd v Rizzani de Eccher Australia Pty Ltd [2017] NSWSC 1798) in a dispute between parties to an unincorporated joint venture for the undertaking of design and construction works in connection with the widening of the M4 Motorway in Sydney, namely as to whether the defendant (Rizzani de Eccher Australia Pty Ltd – “RdE”) was bound to pay a Called Sum of $8.5m for the purposes of the joint venture (the Called Sum Dispute).
-
I dismissed RdE’s notice of motion seeking a stay of the proceedings by reference to an arbitration clause in the parties’ joint venture agreement (the Stay Dispute) and, having found that RdE was estopped in all the circumstances from acting inconsistently with its promise to do so, ordered RdE to sign a written resolution of the Joint Venture Board (“JV Board”) for the payment of the Called Sum. However, I declined to grant the further relief sought by the plaintiff, CPB Contractors Pty Ltd (“CPB”) (namely, declaratory relief and a mandatory injunction as to the payment of the Called Sum). I made directions for brief written submissions on costs to be filed with a view to determining the issue of costs on the papers.
-
The parties have now filed, and I have had an opportunity to consider, submissions as to costs. These are my reasons for the costs order that I will now make. I do not propose to repeat the background to the dispute which is set out in my earlier reasons.
-
CPB argues that the appropriate order for costs is that RdE should pay CPB’s costs of the proceedings on the ordinary basis. RdE submits that there should be no order as to costs, such that the parties bear their own costs of the proceeding, or alternatively that RdE should pay 50% (or less) of CPB’s costs of the proceedings.
Submissions
-
CPB maintains that it succeeded in establishing that RdE was bound by its…
Keep reading for free
Create a free CaseChat account to read CPB Contractors Pty Ltd v Rizzani De Eccher Australia Pty Lt... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2018] NSWSC 74
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was whether the plaintiff was entitled to costs as a party to urgent proceedings, despite not obtaining the full relief sought. The plaintiff argued that it was entitled to costs because it had achieved other forms of relief, including an order for the defendant to pay a significant sum of money. The defendant contested this, arguing that the plaintiff should not be awarded costs because it had not obtained the primary relief it sought, which was an injunction and specific performance of the contract.
The court considered the circumstances under which costs could be awarded in urgent proceedings. It held that the plaintiff's application for urgent relief was valid and that the plaintiff had indeed achieved some form of relief by obtaining an order for payment from the defendant. The court found that while the plaintiff did not obtain the full relief it sought, the fact that it achieved other significant relief meant that it was appropriate to award costs as a party to urgent proceedings. The court emphasised the importance of ensuring that parties who seek urgent relief are not discouraged from doing so due to the risk of not obtaining full relief, provided they achieve some form of relief.
As a result of this decision, the plaintiff was awarded costs as a party to urgent proceedings. This outcome recognises the importance of allowing parties to seek urgent relief where necessary, even if they do not ultimately obtain the full relief sought. The court's decision provides clarity on the circumstances in which costs may be awarded in urgent proceedings, and it reinforces the principle that achieving some form of relief can justify the award of costs.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi