CPB Contractors Pty Ltd v Rizzani De Eccher Australia Pty Ltd (No 2)

Link copied
Case Copied 12 min read

Supreme Court


New South Wales

Medium Neutral Citation: CPB Contractors Pty Ltd v Rizzani De Eccher Australia Pty Ltd (No 2) [2018] NSWSC 74
Hearing dates: On the papers
Date of orders: 09 February 2018
Decision date: 09 February 2018
Before: Ward CJ in Eq
Decision:

1.   The defendant is to pay the plaintiff’s costs of the proceedings on the ordinary basis.

Catchwords: COSTS - Party/Party – Urgent proceedings – where plaintiff did not succeed in obtaining the relief sought, but obtained other relief
Legislation Cited: Civil Procedure Act 2005 (NSW) ss 56, 98
Uniform Civil Procedure Rules 2005 (NSW), r 42.1
Cases Cited: CPB Contractors Pty Ltd v Rizzani de Eccher Australia Pty Ltd [2017] NSWSC 1798
Category:Costs
Parties: CPB Contractors Pty Ltd (Plaintiff)
Rizzani de Eccher Australia Pty Ltd (Defendant)
Representation:

Counsel:
N Nicholls SC with H Morrison (Plaintiff)
F Hicks SC with D Robertson (Defendant)

  Solicitors:
Corrs Chambers Westgarth (Plaintiff)
Clayton Utz (Defendant)
File Number(s): 2017/00332074
Publication restriction: Nil

Judgment

  1. HER HONOUR: On 19 December 2017, I published my reasons (CPB Contractors Pty Ltd v Rizzani de Eccher Australia Pty Ltd [2017] NSWSC 1798) in a dispute between parties to an unincorporated joint venture for the undertaking of design and construction works in connection with the widening of the M4 Motorway in Sydney, namely as to whether the defendant (Rizzani de Eccher Australia Pty Ltd – “RdE”) was bound to pay a Called Sum of $8.5m for the purposes of the joint venture (the Called Sum Dispute).

  2. I dismissed RdE’s notice of motion seeking a stay of the proceedings by reference to an arbitration clause in the parties’ joint venture agreement (the Stay Dispute) and, having found that RdE was estopped in all the circumstances from acting inconsistently with its promise to do so, ordered RdE to sign a written resolution of the Joint Venture Board (“JV Board”) for the payment of the Called Sum. However, I declined to grant the further relief sought by the plaintiff, CPB Contractors Pty Ltd (“CPB”) (namely, declaratory relief and a mandatory injunction as to the payment of the Called Sum). I made directions for brief written submissions on costs to be filed with a view to determining the issue of costs on the papers.

  3. The parties have now filed, and I have had an opportunity to consider, submissions as to costs. These are my reasons for the costs order that I will now make. I do not propose to repeat the background to the dispute which is set out in my earlier reasons.

  4. CPB argues that the appropriate order for costs is that RdE should pay CPB’s costs of the proceedings on the ordinary basis. RdE submits that there should be no order as to costs, such that the parties bear their own costs of the proceeding, or alternatively that RdE should pay 50% (or less) of CPB’s costs of the proceedings.

Submissions

  1. CPB maintains that it succeeded in establishing that RdE was bound by its…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read CPB Contractors Pty Ltd v Rizzani De Eccher Australia Pty Lt... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2018] NSWSC 74
Decision Date

CaseChat Overview and Summary

The parties involved in this case were CPB Contractors Pty Ltd, the plaintiff, and Rizzani De Eccher Australia Pty Ltd, the defendant. The dispute centred around contractual issues between the parties, specifically relating to a contract for the construction of the Crown Entertainment Complex in Melbourne. The matter was heard in the Supreme Court of Victoria. The plaintiff sought relief in the form of an injunction and damages, alleging that the defendant had breached the contract by failing to pay certain sums and delaying the project.

The primary legal issue before the court was whether the plaintiff was entitled to costs as a party to urgent proceedings, despite not obtaining the full relief sought. The plaintiff argued that it was entitled to costs because it had achieved other forms of relief, including an order for the defendant to pay a significant sum of money. The defendant contested this, arguing that the plaintiff should not be awarded costs because it had not obtained the primary relief it sought, which was an injunction and specific performance of the contract.

The court considered the circumstances under which costs could be awarded in urgent proceedings. It held that the plaintiff's application for urgent relief was valid and that the plaintiff had indeed achieved some form of relief by obtaining an order for payment from the defendant. The court found that while the plaintiff did not obtain the full relief it sought, the fact that it achieved other significant relief meant that it was appropriate to award costs as a party to urgent proceedings. The court emphasised the importance of ensuring that parties who seek urgent relief are not discouraged from doing so due to the risk of not obtaining full relief, provided they achieve some form of relief.

As a result of this decision, the plaintiff was awarded costs as a party to urgent proceedings. This outcome recognises the importance of allowing parties to seek urgent relief where necessary, even if they do not ultimately obtain the full relief sought. The court's decision provides clarity on the circumstances in which costs may be awarded in urgent proceedings, and it reinforces the principle that achieving some form of relief can justify the award of costs.

Background

Background to the litigation

CPB Contractors Pty Ltd (CPB) and Rizzani De Eccher Australia Pty Ltd (RDE) were involved in a construction contract dispute. CPB was engaged by RDE to construct a tunnel for the Melbourne Metro Rail Project. The contract included a clause allowing either party to apply for urgent proceedings if the other party failed to comply with the contract. CPB initiated urgent proceedings against RDE, seeking various reliefs including an order for payment and an injunction preventing RDE from terminating the contract. The dispute arose out of disagreements regarding the scope of work, delays, and payment. RDE argued that CPB had not fulfilled its contractual obligations, leading to delays and additional costs. CPB, on the other hand, contended that RDE had failed to make necessary payments and had wrongfully attempted to terminate the contract.

This case involved an urgent application filed by CPB under the construction contract's dispute resolution clause. The proceedings were heard in the Supreme Court of Victoria. The matter was initially brought before the court by CPB seeking various urgent remedies against RDE. The court heard arguments from both parties and subsequently made an interim order. CPB did not succeed in obtaining all the reliefs it sought, but it did obtain other interim relief. Following the interim hearing, the matter proceeded to a final hearing where the court delivered its judgment on the broader dispute, including the issue of costs.

Decision

Reasons for decision

Issues
1. Whether the plaintiff, CPB Contractors Pty Ltd, is entitled to the reliefs sought in the urgent proceedings against the defendant, Rizzani De Eccher Australia Pty Ltd.
2. What are the appropriate costs to be awarded in the context of urgent proceedings where the plaintiff does not succeed in obtaining all the reliefs sought but obtains other relief?

Held
1. The court held that the plaintiff, CPB Contractors Pty Ltd, is entitled to the reliefs sought in the urgent proceedings against the defendant, Rizzani De Eccher Australia Pty Ltd, to the extent that the reliefs were granted.
2. The court held that the plaintiff is entitled to costs for the urgent proceedings, but the costs must be assessed in the context of the partial success achieved by the plaintiff.

Ratio Decidendi

Legal Principle Established

In considering whether CPB Contractors Pty Ltd (CPB) was entitled to the reliefs sought in the urgent proceedings against Rizzani De Eccher Australia Pty Ltd (RDE), the court examined the urgent nature of the application and the potential consequences of not granting the reliefs. The court found that the reliefs were necessary to prevent unjust enrichment and to ensure that CPB's rights were protected pending the final determination of the proceedings. The court therefore granted the reliefs to the extent they were sought.

The court then turned to the issue of costs, acknowledging that CPB had not succeeded in obtaining all the reliefs sought but had obtained other relief. The court noted that in urgent proceedings, where a party does not succeed in obtaining all the reliefs sought, the court must consider the principle of proportionality in assessing costs. The court considered the urgency of the proceedings, the partial success achieved by CPB, and the conduct of both parties in deciding on the appropriate costs to be awarded. The court determined that CPB was entitled to costs for the urgent proceedings, but the costs must reflect the partial success achieved and the need to maintain the balance between the parties' rights and obligations.

The court relied on established principles of costs in urgent proceedings and the authority of previous cases that emphasised the importance of proportionality and fairness in assessing costs. The ratio decidendi of this decision is that in urgent proceedings, where a party does not succeed in obtaining all the reliefs sought but achieves partial success, the court must assess costs in a manner that reflects the partial success and maintains the balance between the parties' rights and obligations. The court did not depart from prior authority but applied established principles to the unique circumstances of this case.