Correnti v Queensland Building and Construction Commission

Link copied
Case Copied 24 min read
CITATION: Correnti v Queensland Building and Construction Commission [2014] QCAT 501
PARTIES: John Correnti t/as Correnti Homes Pty Ltd
(Applicant)
v
Queensland Building and Construction Commission
(Respondent)
APPLICATION NUMBER: GAR282-13
MATTER TYPE: General administrative review matters
HEARING DATE: 9 September 2014
HEARD AT: Brisbane
DECISION OF: Member Browne
DELIVERED ON: 8 October 2014
DELIVERED AT: Brisbane
ORDERS MADE: 1.    The decision made by the Queensland Building and Construction Commission on 24 July 2013 to direct John Correnti t/as Correnti Homes Pty Ltd to rectify the defective footing and slab system of the property at 1 Hakea Court, Plainland, Queensland is confirmed.
CATCHWORDS:

GENERAL ADMINISTRATIVE REVIEW – RECTIFICATION OF BUILDING WORK – where complaint lodged by home owner – where decision made to direct builder to rectify building work – whether work performed by builder is defective – whether discretion to issue a direction to rectify should be made

Queensland Building and Construction Commission Act 1991 (Qld), s 72, s 87
Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 18, s 24

Taok v Queensland Building Services Authority [2013] QCAT 508, cited

APPEARANCES and REPRESENTATION (if any):

APPLICANT: Mr Correnti, self-represented
RESPONDENT: Mr Seefeld of counsel instructed by Holding Redlich Lawyers

REASONS FOR DECISION

  1. Mr Correnti has been a builder since 1981 and has built approximately 1,100 homes. He was engaged by owners of land at Lot 117 Hakea Court, Plainland, Queensland to build a low-set brick veneer house in about 2006 for the contract price of $169,340.00. The house at Lot 117 Hakea Court, Plainland (the property) was completed in about May 2007.

  2. Mr Correnti was the builder responsible for building the property in accordance with the design prepared by FMG Koukourou Engineers.

  3. The property was constructed on what is commonly referred to amongst professionals and trades in the building industry as a ‘waffle raft footing system’.

  4. On 25 October 2012 and 26 October 2012, the Queensland Building and Construction Commission (QBCC) received complaints from the owners of the property about issues with the building work allegedly completed by Mr Correnti. The complaints identified issues, amongst others, relating to cracks in the ceiling and ‘new plasterwork cracks are reopening’.[1]

    [1]Complaint form received 25 October 2012, material filed by the QBCC under s 21 of the Queensland Civil and Administrative Tribunal 2009 (Qld), p 79.

  5. The QBCC, after receiving the complaint and requesting further information, inspected the property on 17 December 2012 and prepared an inspection report dated 20 December 2012.[2] The report prepared by Arnold Fisher, building inspector for the QBCC, identified issues in relation to alleged ‘cracking and movement’ in the walls and floor in certain parts of the property.

    [2]BSA Resolution Services subsidence report dated 17 December 2012, s 21 material, attachment marked ‘SOR-12’, p 224.

  6. The QBCC obtained independent evidence from an engineer, Booth Engineers & Associates Pty Ltd, to report on the alleged movement and damage to the property.

  7. After receiving information and making further enquiries, the QBCC determined on 24…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Correnti v Queensland Building and Construction Commission and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2014] QCAT 501
Decision Date

CaseChat Overview and Summary

Correnti Homes Pty Ltd, trading as Correnti Homes, contested a decision made by the Queensland Building and Construction Commission (QBCC) to require the rectification of a building's footing and slab system. The dispute originated from a complaint lodged by the property owner regarding damage to their home, which the QBCC attributed to subsidence or movement caused by non-compliance with the relevant Australian Standard AS2870-1996. The central legal issue was whether the builder, Correnti Homes, had performed defective work warranting the QBCC's directive for rectification. Additionally, the court had to determine if the QBCC had correctly exercised its discretion in issuing the rectification direction.

The Tribunal examined the evidence presented by Booth Engineers and Geotest Engineering, which included soil tests taken from beneath the slab to ascertain the cause of the property's damage. Despite the builder's contention about the adequacy of the soil samples, the Tribunal found the samples to be reliable, as they were taken from the specified locations under the slab. The builder's argument that the soil samples could have been contaminated by other materials present around the property was dismissed. Based on the expert evidence, the Tribunal concluded that the footing and slab system did not comply with the relevant Australian Standard, leading to the observed damage.

The Tribunal upheld the QBCC's decision to direct Correnti Homes to rectify the defective footing and slab system. The evidence supported the QBCC's findings that the damage resulted from the non-compliance with the Australian Standard. Consequently, the Tribunal confirmed the QBCC's decision, ensuring that the builder would address the identified defects to rectify the property's issues.

The final order confirmed the decision made by the Queensland Building and Construction Commission on 24 July 2013, mandating John Correnti, trading as Correnti Homes Pty Ltd, to rectify the defective footing and slab system of the property at 1 Hakea Court, Plainland, Queensland. This ruling affirmed the QBCC's authority to direct such rectifications when necessary to ensure compliance with building standards and protect property owners.

Orders

Orders of the court

1. The decision made by the Queensland Building and Construction Commission on 24 July 2013 to direct John Correnti t/as Correnti Homes Pty Ltd to rectify the defective footing and slab system of the property at 1 Hakea Court, Plainland, Queensland is confirmed.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

The Tribunal is satisfied based on the evidence of Mr Rebibou that there is evidence of damage to the property and the likely cause of the damage is subsidence or movement resulting from the footing and slab system not complying with the relevant Australian Standard AS2870-1996.Is there evidence of ‘fill’ from soil test samples taken? After the complaint was made to the QBCC by the owners various inspections were undertaken by Booth Engineers through external consultants Geotest Engineering; and by Queensland Soil Testing. The investigations included excavations around the property to enable soil samples to be taken from under the slab. This was necessary to determine the cause of the damage to the property, in particular whether there was presence of uncontrolled fill under the slab (in the absence of piers). Mr Correnti in giving his evidence does not accept that the soil samples taken were adequate in that there was uncertainty about where the excavation pits were located and whether the soil samples were in fact samples taken from under the block. Mr Correnti was given an opportunity at the hearing to cross examine the expert witnesses Mr Hardy and Mr Rebibou in relation to the location of soil test samples taken at the property. Mr Hardy stated at the hearing that the test pit samples referenced in his report dated 4 April 2014 were taken by a technician and the location of the pits were referenced in the report dated 4 April 2014. The pits referenced are depicted as being excavations from the under the slab of the property. The report states:The depth of fill material detected in all three pits is indicated on the attached drawing number ‘SK1’ with the footing cross-sections being provided on drawing “SK2”. A summary of the findings has been provided below….[17][17]Exhibit marked ‘5’, p 1. The soil test samples taken by Geotest Engineering Services Pty Ltd that Mr Rebibou relied upon in preparing his report were also taken from under the slab. Mr Rebibou produced at the hearing a copy of his instructions to Geotest Engineering Services Pty Ltd in relation to soil test samples. The instructions sent by Booth Engineering to Geotest Engineering identify 3 excavation sites at the property on the right hand side, far back right hand side and far back left hand side. There is a map depicted on the instructions to show the areas where excavation and samples should be taken. The instructions state:We require a soil test report for the following work for the BSA investigation:All soil tests require three (3) boreholes, moisture contents at 500mm intervals over 1500mm, D.C.P’s if fill or soft material encountered and Estimate of footing depths/part footing excavations.[18] [18]Exhibit marked ‘14’. I am satisfied that the testing conducted by Geotech relied upon by Mr Rebibou and the test samples taken by Queensland Soil Testing relied upon by Mr Hardy are test samples as referenced in their respective reports taken from under the slab of the property. I am satisfied that the test samples of soil taken by Geotech and Queensland Soil Testing were not corrupted by other material that was also present around the perimeter of the property, as contended by Mr Correnti.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.