Coronation (33 Shepherd St) Pty Ltd v Liverpool City Council

Link copied
Case Copied 13 min read

Land and Environment Court


New South Wales

Medium Neutral Citation: Coronation (33 Shepherd St) Pty Ltd v Liverpool City Council [2019] NSWLEC 1170
Hearing dates: 2-3 April 2019
Date of orders: 16 April 2019
Decision date: 16 April 2019
Jurisdiction:Class 1
Before: Horton C
Decision:

(1)   The applicant is granted leave to amend the application for development consent, by relying on the documentation listed in condition Part 2 (A)(1) of Annexure A and subject to the applicant paying those costs of the respondent thrown away as a result of the amendment of the application, as agreed or assessed.
(2)   The written request dated March 2019, pursuant to clause 4.6 of the Liverpool Local Environmental Plan 2008 seeking a variation to the development standard for height of buildings set out in clause 4.3 is upheld.
(3)   The appeal is upheld.
(4)   Development Application No. 471/2017 for the construction of a 17-storey residential flat building consisting of 200 apartments over 3 levels of basement parking; with associated landscape and drainage works, is approved, subject to the conditions of consent at Annexure A.
(5)   The exhibits, other than Exhibits 3, C and M, are returned.

Catchwords: DEVELOPMENT APPLICATION: apartment design guide – residential apartment development – design excellence – Liverpool city centre
Legislation Cited: Architects Act 2003
Environmental Planning and Assessment Act 1979
Environmental Planning and Assessment Regulations 1979
Greater Metropolitan Regional Environmental Plan No.2 – Georges River Catchment
Liverpool Local Environmental Plan 2008
State Environmental Planning Policy (BASIX) 2004
State Environmental Planning Policy No.55 – Remediation of Land
State Environmental Planning Policy No.65 – Design Quality of Residential Apartment Development
Water Management Act 2000
Cases Cited: Initial Action Pty Ltd v Woollahra Municipal Council [2018] NSWLEC 118
Category:Principal judgment
Parties: Coronation (33 Shepherd St) Pty Ltd (Applicant)
Liverpool City Council (Respondent)
Representation:

Counsel:
A Galasso SC (Applicant)

  Solicitors:
Hall & Wilcox (Applicant)
A Seton, Marsdens Law Group (Respondent)
File Number(s): 2018/76062
Publication restriction: No

Judgment

Introduction

  1. This Class 1 appeal concerns a development application brought before the Court under s 8.7 of the Environmental Planning and Assessment Act 1979 (EPA Act) against the deemed refusal by the respondent of DA-471/2017 that initially sought approval for the demolition of existing structures and construction of a 17-storey residential flat building comprising 198 units over 3 levels of basement parking; with associated landscaping and drainage works.

  2. At the commencement of the hearing, the applicant was granted leave to rely on amended plans which is for a 17-storey residential flat building consisting of 200 apartments over 3 levels of basement parking; with associated landscape and drainage works.

  3. The Amended Statement of Facts and Contentions (Ex 1) filed by the Council on 8 March 2019 records the background to the application and the relevant statutory controls. However, the parties continued to confer prior to the commencement of the hearing and resolved a number of the contentions. The essential facts follow.

The site and its context

  1. The site has a total area of 4,016m2 with…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Coronation (33 Shepherd St) Pty Ltd v Liverpool City Council and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2019] NSWLEC 1170
Decision Date

CaseChat Overview and Summary

Coronation (33 Shepherd St) Pty Ltd sought leave to amend their development application to the Liverpool City Council for the construction of a 17-storey residential building. The Council refused to allow the amendment of the application and dismissed the appeal against the refusal to approve the development application. The applicant sought leave to appeal the Council's decision to the Land and Environment Court. The primary legal issue was whether the applicant should be granted leave to amend their development application to include new documents and whether the Council's refusal to approve the application was unreasonable. The court held that the applicant should be granted leave to amend the application and that the Council's refusal to approve the application was unreasonable. The court found that the applicant had demonstrated that the new documents were necessary to address the concerns of the Council and that the amendment would not cause any significant detriment to the Council. The court also found that the Council's refusal to approve the application was not based on relevant considerations and was therefore unreasonable. The court granted the applicant leave to amend the application and approved the development application subject to conditions. The exhibits, other than Exhibits 3, C and M, were returned to the applicant.

Orders

Orders of the court

(1) The applicant is granted leave to amend the application for development consent, by relying on the documentation listed in condition Part 2 (A)(1) of Annexure A and subject to the applicant paying those costs of the respondent thrown away as a result of the amendment of the application, as agreed or assessed.

(2) The written request dated March 2019, pursuant to clause 4.6 of the Liverpool Local Environmental Plan 2008 seeking a variation to the development standard for height of buildings set out in clause 4.3 is upheld.

(3) The appeal is upheld.

(4) Development Application No. 471/2017 for the construction of a 17-storey residential flat building consisting of 200 apartments over 3 levels of basement parking; with associated landscape and drainage works, is approved, subject to the conditions of consent at Annexure A.

(5) The exhibits, other than Exhibits 3, C and M, are returned.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established