Cordon Investments Pty Ltd v Lesdor Properties Pty Ltd

Link copied
Case Copied 8 min read
CITATION: Cordon Investments Pty Ltd v Lesdor Properties Pty Ltd [2006] NSWSC 481
HEARING DATE(S): 20/04/06, 27/04/06, 05/05/06
JURISDICTION: Equity Division
JUDGMENT OF: Barrett J
EX TEMPORE JUDGMENT DATE: 05/05/2006
DECISION: Interlocutory order refused
CATCHWORDS: CONTRACTS - contractual promise to sign strata plans as expeditiously as possible after "completion of the Building Works" - such works to be carried out in accordance with certain plans, specifications and approvals - whether serious question to be tried as to whether "completion" has occurred - application for interlocutory order for specific performance - may be regarded as application for interlocutory mandatory injunction - a particularly rara avis
PARTIES: Cordon Investments Pty Limited - Plaintiff
Lesdor Properties Pty Limited - Defendant
FILE NUMBER(S): SC 2332/06
COUNSEL: Mr V. Ruta - Plaintiff
Mr J.S. Whyte - Defendant
SOLICITORS: McBridge Harle & Martin - Plaintiff
Solari Legal - Defendant

IN THE SUPREME COURT
OF NEW SOUTH WALES
EQUITY DIVISION

BARRETT J

FRIDAY 5 MAY 2006

2332/06 CORDON INVESTMENTS PTY LIMITED v LESDOR PROPERTIES PTY LIMITED

JUDGMENT

1 The plaintiff, Cordon Investments Pty Limited (“Cordon”), seeks by its notice of motion filed on 12 April 2006, an order compelling the defendant, Lesdor Properties Pty Limited (“Lesdor”), to execute particular strata plans in respect of a property which is the subject of a joint venture agreement between them.

2 The joint venture is effectively one under which Lesdor contributed land and Cordon undertook to carry out building works. A highly relevant provision of the parties' written contract is clause 15:

          “Cordon shall at its own expense use its best endeavours to have the Strata Plan approved by the Council and registered at LPINSW as expeditiously as possible following the completion of the Building Works and Lesdor shall do all such things as shall be reasonably required of it to give effect to this.”

3 I should also refer to clause 13.3 which follows two provisions by which Lesdor purports to appoint Cordon as Lesdor's attorney and to confer certain powers on Cordon. Clause 13.3 is as follows:

          “Notwithstanding the preceding provisions of this clause, Lesdor shall execute any plan of subdivision, the Strata Plan any accompanying instruments and such Contract, Contracts, Transfer or Transfers for the conveyance of the title of the residual lots to such persons or corporation as Cordon shall nominate and shall deliver such plans, instruments and such Contract, Contracts, Transfer or Transfers to Cordon forthwith upon request.”

4 Clause 13.3 is, in my view, a provision of a machinery or procedural kind. It appears in the power of attorney and authority conferring context. The obligation it purports to impose is not qualified as to time.

5 Clause 15, on the other hand, introduces a relevant timing element and is a substantive provision rather than a procedural one. Clause 15 says that Cordon is to use its best endeavours to have the strata plan approved and registered “as expeditiously as possible following completion of the building works”. Lesdor's obligation under the same clause is to…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Cordon Investments Pty Ltd v Lesdor Properties Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2006] NSWSC 481
Decision Date

CaseChat Overview and Summary

The case of Cordon Investments Pty Ltd v Lesdor Properties Pty Ltd was heard in the Supreme Court of New South Wales. The dispute arose from a contractual agreement between the parties concerning the completion of building works and the subsequent signing of strata plans. Cordon Investments, the applicant, sought an interlocutory order for specific performance from Lesdor Properties, the respondent, arguing that Lesdor had not fulfilled its obligation to sign the strata plans promptly after the building works were completed. Lesdor Properties contended that the building works were not yet complete and thus, it was not obligated to sign the plans.

The primary legal issue before the court was the interpretation of the contractual phrase "completion of the Building Works" and whether this term had been satisfied. The court had to determine whether there was a serious question to be tried regarding the completion of the building works and if Lesdor Properties was indeed obligated to sign the strata plans. Additionally, the court considered whether the application for specific performance could be regarded as an application for an interlocutory mandatory injunction, a rare occurrence in such cases.

In its judgment, the court noted that for an interlocutory order for specific performance to be granted, there must be a serious question to be tried on the merits of the case. The court examined the evidence presented by both parties and found that there was indeed a serious question as to whether the building works had been completed. Given that the issue of completion was not clear-cut, the court was hesitant to grant specific performance at the interlocutory stage. The court regarded the application as an interlocutory mandatory injunction, which is an uncommon remedy, and found that it was not appropriate to compel Lesdor Properties to sign the strata plans without further evidence and determination of the completion status.

The final orders of the court were to deny the application for specific performance and to dismiss the application for an interlocutory mandatory injunction. The court emphasised that the determination of whether the building works had been completed required a full trial and could not be resolved on an interlocutory basis. The case was to proceed to a final hearing to determine the completion status and the obligations of the parties under the contract.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established