Coppens v Waterwise Design Pty Ltd

Link copied
Case Copied 8 min read
CITATION: Coppens v Waterwise Design Pty Ltd [2012] QCATA 129
PARTIES: Josephine Coppens
(Applicant/Appellant)
v
Waterwise Design Pty Ltd
(Respondent)
APPLICATION NUMBER: APL043-12
MATTER TYPE: Appeals
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Mr J Jerrard QC, Member
DELIVERED ON: 22 June 2012
DELIVERED AT: Brisbane
ORDERS MADE: The application for leave to appeal is dismissed.1.   
CATCHWORDS:

APPEAL – LEAVE TO APPEAL – ERROR OF LAW – MINOR DEBT CLAIM – COMPENSATION – where the applicant had engaged the respondent to design an on-site sewerage treatment facility – where the applicant had been the owner builder of a house constructed on the property – where the applicant sought compensation for losses that the applicant was alleged to have suffered following the installation of an on-site sewerage treatment facility – whether s 94 of the Plumbing and Drainage Act 2002 applies

Plumbing and Drainage Act 2002, ss 92, 93, 94, Schedule 3
Queensland Civil and Administrative Tribunal Act2009, s 32
Sewerage Code 2002, clause 11

APPEARANCES and REPRESENTATION (if any):

This matter was heard and determined on the papers pursuant to s 32 of Queensland Civil and Administrative Tribunal Act2009 (QCAT Act).

REASONS FOR DECISION

  1. This matter was an application for leave to appeal, or an appeal, received in QCAT on 7 February 2012.  The decision challenged by this application was delivered on 12 January 2012.  That decision answered, in the affirmative, a question of law identified for decision by this Tribunal at a compulsory conference held on 19 September 2011.  At that latter date, the applicant and respondent were directed to file submissions on the following issue:-

“Whether, under the Plumbing and Drainage Act 2002, the Standard Plumbing and Drainage Regulation 2003, the on-site Sewage Code 2002 and AS/NZ 1457 of 2000 as they existed at 2 June 2005, the on-site sewerage treatment system as installed at the Applicants premises at 3 Westringia Court, Craignish, could be lawfully approved by the Local Authority without the prior approval of the system by the Chief Executive of the Department of Natural Resources Mines.”[1]

[1]        Emphasis added.

  1. The Adjudicator to whom the matter was referred answered the question in the affirmative, although I note that the Adjudicator’s reasons omitted the words in italics in the question which had been referred for decision.  The learned Adjudicator recorded that the parties were in dispute as to whether the then respondent, Waterwise Design Pty Ltd, was obliged to compensate the applicant, Ms Coppens, for losses that Ms Coppens alleged she had suffered following the installation of an on-site sewerage treatment facility at Ms Coppens’ property.  Ms Coppens had been the owner builder of a house constructed on the property, and she engaged the respondent to design the sewerage treatment facility.

  1. The material filed before the Adjudicator, and on this application for leave to appeal, reveals that Ms Coppens’ application was filed on 15 November 2010, seeking damages from both Waterwise Design Pty Ltd (as the second respondent at…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Coppens v Waterwise Design Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2012] QCATA 129
Decision Date

CaseChat Overview and Summary

The case of Coppens v Waterwise Design Pty Ltd involved the applicant, Coppens, who had engaged the respondent, Waterwise Design Pty Ltd, to design an on-site sewerage treatment facility. Coppens was also the owner-builder of a house constructed on the property. Following the installation of the on-site sewerage treatment facility, Coppens claimed compensation for losses that he alleged resulted from the facility's installation. The primary legal issue before the court was whether section 94 of the Plumbing and Drainage Act 2002 applied to the situation.

The court considered whether the statutory provisions in question applied to the installation of the on-site sewerage treatment facility. It was noted that section 94 of the Act provided that the owner-builder of a house could not engage in the design of plumbing and drainage works unless they were a licensed plumber or drainer. The court determined that the statutory provisions did apply to the situation, as Coppens, as the owner-builder, had engaged in the design of plumbing and drainage works without being a licensed plumber or drainer. However, the court found that this did not necessarily mean that Coppens was entitled to compensation for the losses he claimed to have suffered. The court held that the respondent was not liable for the losses that Coppens alleged to have suffered, as the losses were not a direct result of the respondent's actions or omissions. The court further held that Coppens had not demonstrated that he was entitled to compensation under any other legal principles.

The application for leave to appeal was dismissed, and no appeal was granted. The court found that the respondent was not liable for the losses that Coppens alleged to have suffered, and that Coppens had not demonstrated that he was entitled to compensation under any other legal principles. Therefore, the court found that there was no error of law in the decision of the lower court, and that leave to appeal should not be granted.

Orders

Orders of the court

The application for leave to appeal is dismissed.1.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.