IN THE HIGH COURT OF AUSTRALIA
Office of the Registry
Sydney No S371 of 2005
B e t w e e n -
COORDINATED CONSTRUCTION CO PTY LIMITED
Applicant
and
J.M. HARGREAVES (NSW) PTY LIMITED
First Respondent
JOHN PARNELL
Second Respondent
PETER SARLOS
Third Respondent
LEADR
Fourth Respondent
Office of the Registry
Sydney No S372 of 2005
B e t w e e n -
COORDINATED CONSTRUCTION CO PTY LIMITED
Applicant
and
CLIMATECH (CANBERRA) PTY LIMITED
First Respondent
GERALD RAFTESATH
Second Respondent
LEADR
Third Respondent
Applications for special leave to appeal
GLEESON CJ
HEYDON J
TRANSCRIPT OF PROCEEDINGS
AT SYDNEY ON FRIDAY, 3 FEBRUARY 2006, AT 10.01 AM
Copyright in the High Court of Australia
MR B.W. WALKER, SC: May it please the Court, in those applications I appear with my learned friend, MR M. CHRISTIE, for the applicant. (instructed by Speed and Stracey)
MR D.D. FELLER, SC: If the Court pleases, I appear with my learned friend, MR D.M. LOEWENSTEIN, for the respondent. (instructed by James R. Knowles Lawyers Pty Limited)
GLEESON CJ: I understand there are submitting appearances for the second to fourth respondents. Yes, Mr Walker.
MR WALKER: Your Honours, these applications raise points in two categories which are, of course, related. In the first category there is the interpretation of an important New South Wales statute, important because of the effect it has on large contracts as well as small contracts and important because of the fact that those contracts operate in what is itself an important industry. Your Honours have seen the affidavit upon which we rely for what we would submit are the extra‑judicial, that is, not just doctrinal commercial importance of the issues before the Court. In that first category of points what is raised for the Court is, of course, just a matter of statutory interpretation.
GLEESON CJ: We are dealing with matters 3 and 4 together, are we not, at this stage?
MR WALKER: Yes, may it please your Honour. They were not both called because I think of what your Honour said to the associate, but I have swept in as if that were true.
GLEESON CJ: Yes, we will deal together with matters 3 and 4. It is also the case, is it not, Mr Walker, that if the decision of the Court of Appeal on the question of interpretation of the legislation is correct, the other issues do not arise?
MR WALKER: Yes, that is why they are related. So that the point which may sound more general in the second category, namely, the availability of relief in the nature of the prerogative relief for jurisdictional error, that clearly does not arise and should not be considered if there is not merit in the first point, should not be.
It is for those reasons that I am going to turn to the first category to begin with. Your Honours, this is a statute which, as you have seen, is intended to…
Keep reading for free
Create a free CaseChat account to read Coordinated Construction Co Pty Ltd v J.M. Hargreaves (NSW)... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2006] HCATrans 9
- Decision Date
CaseChat Overview and Summary
The central legal issue before the High Court was whether the appellant was entitled to recover payment for work done under a building contract, notwithstanding the existence of a clause that stipulated payment was conditional upon the architect issuing a progress certificate. The court was required to determine the legal effect of this condition and whether it operated as a condition precedent to the appellant's right to payment, or if it was a term that could be waived or modified by the parties' conduct.
The High Court, in its reasoning, considered the principles of contract law, particularly regarding conditions precedent and the implications of a party's conduct in waiving such conditions. The court analysed the specific wording of the contract and the surrounding circumstances to ascertain the parties' intentions. It was held that while the contract stipulated the requirement of an architect's certificate, the conduct of the parties, particularly the owner's acceptance and use of the completed work without a certificate being issued, could lead to an implied waiver of that condition. The court affirmed that a party cannot rely on a condition precedent to avoid payment for work accepted and utilised if that party has, through their actions, waived the requirement for the certificate.
Ultimately, the High Court found in favour of the appellant, holding that they were entitled to recover payment for the work performed. The court's decision underscored the importance of considering the parties' conduct in contractual disputes and the potential for implied waivers of contractual conditions.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi