Cook's Constructions P/L v Stork ICM Australia P/L

Link copied
Case Copied 13 min read

SUPREME COURT OF QUEENSLAND

CITATION:

Cook’s Constructions P/L v Stork ICM Australia P/L [2006] QSC 160

PARTIES:

COOK’S CONSTRUCTIONS PTY LTD
ACN 004 782 558
(plaintiff/respondent)
v
STORK ICM AUSTRALIA PTY LTD
ACN 004 448 042
(defendant/applicant)

FILE NO/S:

S10993 of 2001

DIVISION:

Trial Division

PROCEEDING:

Application

ORIGINATING COURT:

Supreme Court

DELIVERED ON:

23 June 2006

DELIVERED AT:

Brisbane

HEARING DATE:

21 June

JUDGE:

Muir J

ORDER:

That the application be dismissed and that the costs of and incidental to the application be the parties’ costs in the cause.

CATCHWORDS:

PROCEDURE – JUDGMENTS AND ORDERS – IN GENERAL – OTHER MATTERS – where applicant applies for summary judgment – where applicant alleges failure to comply with Subcontract – where respondent claims damages for breach of contract – whether matter should proceed to trial

Uniform Civil Procedure Rules 1999 (Qld), r 292

COUNSEL:

S R Grahame for the respondent
K E Downes for the applicant

SOLICITORS:

ClarkeKann for the respondent
McCullough Robertson for the applicant

Introduction

  1. The applicant defendant as contractor and the respondent plaintiff as subcontractor entered into a subcontract (“the Subcontract”) to perform certain works in relation to the construction of an ammonium nitrate plant at Moura. On 5 March 2001 the respondent commenced proceedings against the applicant in the Supreme Court of Victoria claiming $1,661,654 damages for breach of contract. The proceedings were transmitted to Queensland and an Amended Statement of Claim was filed on 2 August 2005. In it a number of discrete claims were made. The applicant seeks summary judgment in respect of the following three claims:

·     The pedestal variation:  paragraphs 109 to 123 and 130 of the 2005 Statement of Claim.

·     The suspended slabs direction: paragraphs 147 to 162 of the 2005 Statement of Claim.

·     The prill store variation: paragraphs 163 to 178 of the 2005 Statement of Claim.

  1. The applicant’s case is centred upon clause 51.1 of the General Conditions of Subcontract. It provides:

“Stork shall not be liable upon any claim by the Subcontractor in respect of or arising out of a breach of the Subcontract unless within 14 days after the first day upon which the Subcontractor could reasonably have been aware of the breach, the Subcontractor has given to Stork’s Representative the prescribed notice.
Stork shall not be liable upon any other claim by the Subcontractor for any extra cost or expense in respect of or arising out of any direction or approval by Stork’s Representative unless within 42 days after the first day upon which the Subcontractor could reasonably have been aware of the entitlement to make the claim, the Subcontractor has given to Stork’s Representative the prescribed notice.
The prescribed notice is a notice in writing which includes particulars of all the following:

(a)the breach, act, omission, direction, approval or circumstances on which the claim is or will be based;

(b)the provision of the Subcontractor or other basis for the claim or proposed claim; and

(c)         the quantum or likely quantum of the claim.
This Clause…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Cook's Constructions P/L v Stork ICM Australia P/L and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2006] QSC 160
Decision Date

CaseChat Overview and Summary

In the matter of Cook's Constructions P/L v Stork ICM Australia P/L, the Federal Court was presented with an application for summary judgment by Cook's Constructions P/L against Stork ICM Australia P/L. The dispute arose from an alleged breach of a subcontract, with Stork ICM Australia P/L claiming damages for the alleged failure of Cook's Constructions P/L to comply with the terms of the agreement. The primary legal issue before the Court was whether the matter should proceed to a trial or if summary judgment could be granted in favor of Cook's Constructions P/L.

The court considered the relevant provisions of the contract and the nature of the alleged breach. It was noted that there were disputed facts concerning the extent of the non-compliance and the resulting damages. The Court emphasised the importance of allowing the parties to present their evidence and arguments to resolve these factual disputes, and concluded that the matter could not be decided based on the current evidence without a trial. The Court held that the application for summary judgment should be dismissed, as the evidence presented did not conclusively establish that there was no genuine issue to be tried.

Consequently, the Court dismissed the application for summary judgment and ordered that the costs of and incidental to the application be the parties' costs in the cause. This decision underscores the importance of allowing the parties to present their respective cases in full, particularly in matters involving contractual disputes with significant factual complexities.

Orders

Orders of the court

That the application be dismissed and that the costs of and incidental to the application be the parties’ costs in the cause.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.