| CITATION: | Contrast Constructions Pty Ltd v Bartlett [2013] QCAT 322 |
| PARTIES: | Contrast Constructions Pty Ltd (Applicant) |
| v | |
| Brett Bartlett (Respondent) |
| APPLICATION NUMBER: | BD469-08 |
| MATTER TYPE: | Building matters |
| HEARING DATE: | 4, 5, 6, 7, 8 February 2013 and 1 July 2013 |
| HEARD AT: | Brisbane |
| DECISION OF: | Joanne Browne, Member |
| DELIVERED ON: | 5 July 2013 |
| DELIVERED AT: | Brisbane |
| ORDERS MADE: | 1. The Applicant to pay the Respondent the amount of $219,162.84 plus $130,547.35 in interest by 4.00pm on 5 September 2013. 2. Any submissions on costs to be filed in the Tribunal and served on the other party by 4.00pm on 12 September 2013. 3. Any submissions on costs in reply to be filed in the Tribunal and served on the other party by 4.00pm on 26 September 2013. 4. Any application for costs will be determined on the papers without an oral hearing by the member who conducted the hearing in these proceedings. |
| CATCHWORDS: | BUILDING DISPUTE – where contract to build house – where architect to administer and assess claims under the contract – where contract provided for adjustment of time costs for an extension of time – whether home owner was in breach – where builder abandoned the site – assessment of claim for incomplete and defective works. Queensland Civil and Administrative Tribunal Act 2009, s 47 Shevill v Builders Licensing Board (1982) 149 CLR 620 |
APPEARANCES and REPRESENTATION (if any):
| APPLICANT: | Contrast Constructions Pty Ltd represented by Mr Michael Labone of counsel instructed by Mills Oakley Lawyers |
| RESPONDENT: | Mr Brett Bartlett represented by Mr Peter Hacket of counsel instructed by MSB Lawyers |
REASONS FOR DECISION
Mr Bartlett contracted with a building company, Contrast Constructions Pty Ltd, on 23 June 2006 to build a house on the riverfront at 32 Hiron Street, St Lucia at a cost of $2,302,000.[1]
[1] Adjusted contract sum (agreed) is $2,520,097.96.
The contract was administered by an architect who also acted as an assessor. The role of the architect was to provide instructions to the builder, to act independently in assessing claims for delay costs, costs for completion of work and any claims for liquidated damages arising from a change to the date of practical completion.
The architect for the purposes of administering and assessing the contract was initially Bligh Voller Nield Pty Ltd (BVN). The parties agree dm2architecture (DM2) became the architect from 14 October 2008. [2]
[2]Agreed “Issues for determination” filed on 8 February 2013.
The house could be described as unique in that it had various items to be used in its construction that are of a high quality and design. For example, there were approximately 20 windows to be installed using a PVC product instead of wood. The PVC product is rare for Australian standards but not uncommon in the European and Asian markets and was, according to the builder, a difficult product to source.
The Tribunal heard evidence at the…
Continue reading Contrast Constructions Pty Ltd v Bartlett
Sign in free to access the full text
- AGLC
- Contrast Constructions Pty Ltd v Bartlett [2013] QCAT 322
- Case
- [2013] QCAT 322
- Decision Date
CaseChat Overview and Summary
The court in Contrast Constructions Pty Ltd v Bartlett addressed several issues in the context of a building dispute between a builder and a homeowner. The primary legal issues included whether the builder was entitled to an adjustment of time costs for an extension of time, whether the homeowner was in breach of contract, and the reasonable value of incomplete and defective work. The court found in favour of the builder in terms of entitlement to adjustment of time costs for certain periods but not for others. It determined that the homeowner was not in breach of contract and, therefore, the builder was not entitled to liquidated damages. The court also assessed the reasonable value of the incomplete and defective work, taking into account the expert evidence and the context of the high-quality fixtures and fittings involved in the construction. The final order required the builder to pay the homeowner a specified amount, plus interest, by a certain date.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.