Construction Technologies Australia Pty Ltd v Doueihi and 4 Ors (No. 3)

Link copied
Case Copied 25 min read

Supreme Court


New South Wales

Medium Neutral Citation: Construction Technologies Australia Pty Ltd v Doueihi & 4 Ors (No. 3) [2015] NSWSC 1850
Hearing dates:16 November 2015
Decision date: 04 December 2015
Jurisdiction:Equity
Before: White J
Decision:

Notices of motion dismissed.

Catchwords: LANDLORD AND TENANT – development approval – landlords and tenant were required to do all things necessary to obtain council development approval – both parties alleged the other was in breach of undertaking or court order – whether the tenant was required to lodge an appeal from a deemed refusal of its application for development approval – whether the landlords should be restrained from doing anything that may have the effect of delaying, frustrating or otherwise hindering the development approval process – where landlords had consented to the tenant’s application for development approval but had also lodged objections to the application – both applications dismissed
Legislation Cited: Environmental Planning and Assessment Act 1979 (NSW)
Cases Cited: Construction Technologies Australia Pty Ltd v Doueihi [2014] NSWSC 1717; (2015) 17 BPR 33,457
Construction Technologies Australia Pty Ltd v Edward Doueihi & Ors (9 March 2015, no medium neutral citation)
Lizzio v Council of the Municipality of Ryde (1983) 155 CLR 211
Category:Procedural and other rulings
Parties: Construction Technologies Australia Pty Ltd (Plaintiff)
Edward Doueihi (1st Defendant)
Katrina Scott (2nd Defendant)
Maria Vatselias (3rd Defendant)
Nicole Hogan (4th Defendant)
Marble Plus Pty Ltd (5th Defendant)
Representation:

Counsel:
K Rees SC with R A Jedrzejczyk (Plaintiff)
W G Muddle SC (Defendants)

  Solicitors:
Fong D’Emilio Lawyers (Plaintiff)
Norton Rose Fulbright (Defendants)
File Number(s):2012/367996

Judgment

  1. HIS HONOUR:   On 18 December 2014 I made orders to give effect to my reasons for judgment of 4 December 2014 (Construction Technologies Australia Pty Ltd v Doueihi [2014] NSWSC 1717; (2015) 17 BPR 33,457). As part of the orders made on 18 December 2014 I noted an undertaking from the plaintiff (CTA) to the Court promptly to do all things necessary on its part to obtain all necessary regulatory approvals for its occupation and use of the CTA premises and its manufacturing facility at those premises. I ordered the first to fourth defendants to do all that was necessary on their part for the obtaining of such approvals by CTA, including providing their consent to CTA’s application for necessary approvals, failing which a registrar of the Court could provide such consent.

  2. In my reasons of 4 December 2014 I explained at paras [97]-[104] the circumstances in which the issue of council approval to CTA’s operations arose. The defendants had submitted that CTA was not entitled to any equitable relief because it did not have necessary approvals for its manufacturing activities. I held that that complaint would be appropriately dealt with by its being a condition of a grant of any equitable relief that development consent (if required) and any other approval that might be required for the manufacturing use be obtained (at [97] and [104]). Because the owners’ consent…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Construction Technologies Australia Pty Ltd v Doueihi and 4... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2015] NSWSC 1850
Decision Date

CaseChat Overview and Summary

The matter before the court involved Construction Technologies Australia Pty Ltd, the tenant, and four landlords, Doueihi and others, regarding a dispute over the development approval process for a property. The tenants alleged that the landlords had breached a lease provision requiring them to do all things necessary to obtain council development approval. Conversely, the landlords claimed the tenants had failed to lodge an appeal against a deemed refusal of their development application. The dispute culminated in both parties seeking remedies, including declarations, injunctions, and damages.

The central legal issues the court needed to address were whether the tenants were obligated to appeal the deemed refusal of their development application and whether the landlords should be restrained from actions that could impede the approval process. The court examined the lease provisions, the nature of the landlords' consent and objections, and the obligations of both parties under the lease and relevant planning laws.

The court found that the tenants were not required to lodge an appeal against the deemed refusal as the landlords' consent to the development application was unequivocal, and their subsequent objections did not negate this consent. The court held that the landlords' actions did not constitute a breach of their obligations under the lease. Consequently, both applications were dismissed, with the court determining that no party was in breach of the lease or court orders.

No further orders were made, as the court concluded that the landlords' consent, despite their objections, effectively met the tenants' obligations under the lease. The landlords' actions, therefore, did not hinder the development approval process, and no further injunctions or declarations were warranted.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.