Construction, Forestry, Mining and Energy Union v Nyrstar Hobart Pty Ltd

Case

[2017] FWC 678

1 FEBRUARY 2017

No judgment structure available for this case.

[2017] FWC 678
FAIR WORK COMMISSION

STATEMENT


Fair Work Act 2009

s.739—Dispute resolution

Construction, Forestry, Mining and Energy Union
v
Nyrstar Hobart Pty Ltd
(C2016/4155)

Tasmania

COMMISSIONER LEE

MELBOURNE, 1 FEBRUARY 2017

Application to deal with a dispute.

[1] This matter involves a dispute between the Construction, Forestry, Mining and Energy Union (CFMEU) and Nyrstar Hobart Pty Ltd (the Respondent). The CFMEU notified a dispute in relation to the Nyrstar Hobart Production Enterprise Agreement 2015 (the Agreement) pursuant to s.739 of the Fair Work Act 2009 (the Act).

[2] A statement [[2016] FWC 6796] was issued on 21 September 2016 detailing the dispute and the question the parties sought to have determined.

[3] The matter was listed for hearing before me on Friday 25 November 2016 at 9.30am.

[4] Subsequent to the hearing the parties advised my chambers that they had reached an in principle agreement regarding a resolution of the dispute.

[5] On 31 January 2017 consent orders were filed with the Fair Work Commission. A copy of the consent orders is attached in Annexure A.

[6] The consent orders reflect that the parties have reached an agreement in relation to the matters in dispute. The dispute is therefore resolved and the Fair Work Commission’s file will be closed.

COMMISSIONER

Printed by authority of the Commonwealth Government Printer

<Price code A, PR589897>


ANNEXURE A

Actions
Download as PDF Download as Word Document


Cases Citing This Decision

0

Cases Cited

1

Statutory Material Cited

0