Construction, Forestry, Maritime, Mining and Energy Union v Wagstaff Piling Pty Ltd

Link copied
Case Copied 40 min read
[2019] FWCFB 102
FAIR WORK COMMISSION

DECISION


Fair Work Act 2009

s.604 - Appeal of decisions

Construction, Forestry, Maritime, Mining and Energy Union
v
Wagstaff Piling Pty Ltd
(C2018/6537)

VICE PRESIDENT HATCHER
DEPUTY PRESIDENT ANDERSON
DEPUTY PRESIDENT SAUNDERS



SYDNEY, 17 JANUARY 2019

Introduction and background

[1] The Construction, Forestry, Maritime, Mining and Energy Union (CFMMEU) has lodged an appeal, for which permission to appeal is required, against a decision of Deputy President Masson issued on 16 November 2018 1 (Decision). The Decision concerned an application by Wagstaff Piling Pty Ltd (Wagstaff) made pursuant to s 739 of the Fair Work Act 2009 (FW Act) for the Commission to deal with a dispute pursuant to the dispute settlement procedure in clause 10 of the Wagstaff Piling Pty Ltd and the CFMEU (Victorian Construction and General Division) Piling Agreement 2016 – 2018 (Agreement).2 The dispute in question concerned a site allowance to be paid to employees of Wagstaff engaged on the West Gate Tunnel Project (Project) in Melbourne. The Victorian Building Industry Disputes Panel (Panel) had earlier determined, pursuant to Appendix C of the Agreement, that the amount of the site allowance should be $8.90 per hour. Wagstaff’s application sought that the Commission conduct a full review (in the nature of a hearing de novo) of the Panel’s determination. Before the Deputy President, the CFMMEU contended that clause 10 of the Agreement did not confer upon the Commission jurisdiction to deal with the dispute. In the alternative, it contended that if the Commission could deal with the dispute, it could only deal with it as an appeal stricto sensu from the Panel’s determination. The Deputy President rejected both contentions: he found that the Commission had the power under clause 10 of the Agreement to deal with the dispute and review the Panel’s determination, and it was required to do so by conducting a hearing de novo concerning the quantum of the site allowance. In its appeal, the CFMMEU contends that the Deputy President erred in respect of each of these conclusions.

[2] Under s 739(4) of FW Act, the Commission may arbitrate a dispute where empowered to do so by the disputes settlement procedure in an enterprise agreement. Section 739(3) provides that the Commission must not exercise any powers limited by the dispute settlement procedure. In the proceedings before the Deputy President, Wagstaff contended that clause 10 of the Agreement provided the requisite source of power. Clause 10 provides:

“10 Disputes Settlement Procedure

10.1 A major objective of this Agreement is to eliminate lost time and/or production arising out of disputes or grievances. Disputes over any work related or industrial matter or any matters arising out of the operation of the Agreement or incidental to the operation of the Agreement should be dealt with as close to its source as possible. Disputes over matters arising from this Agreement (or any other dispute related to the employment relationship or the NES, including subsections 65(5) or 76(4) of the Fair Work Act)…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Construction, Forestry, Maritime, Mining and Energy Union v... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2019] FWCFB 102
Decision Date

CaseChat Overview and Summary

The Construction, Forestry, Maritime, Mining and Energy Union (CFMMEU) appealed a decision of the Fair Work Commission concerning a site allowance to be paid to employees of Wagstaff Piling Pty Ltd engaged on the West Gate Tunnel Project in Melbourne. The CFMMEU argued that the Commission lacked the jurisdiction to conduct a review of a decision made by the Victorian Building Industry Disputes Panel, and that even if it did, the review was to be an appeal stricto sensu, not a hearing de novo. The Commission upheld Wagstaff's application for review, and the CFMMEU sought permission to appeal the decision of the Deputy President. The Fair Work Commission allowed the appeal in part and concluded that the Deputy President erred in finding that the Commission had the power to conduct a merits review of the Panel's determination. The Commission was of the view that the specific provisions of the Agreement dealing with site allowances excluded the operation of the general disputes settlement procedure, and thus the Commission could only review the Panel's determination as to whether it had jurisdiction under Appendix C to determine a site allowance for the Project. In terms of the nature of the review, the Commission found that the ordinary meaning of the word "review" was to inspect, look over or re-examine something, and that the Commission was empowered to discharge its review function by facilitating agreement between the parties through conciliation or by making a decision by arbitration.