| [2019] FWCFB 102 |
| FAIR WORK COMMISSION |
DECISION |
Fair Work Act 2009
s.604 - Appeal of decisions
Construction, Forestry, Maritime, Mining and Energy Union
v
Wagstaff Piling Pty Ltd
(C2018/6537)
VICE PRESIDENT HATCHER |
|
Introduction and background
[1] The Construction, Forestry, Maritime, Mining and Energy Union (CFMMEU) has lodged an appeal, for which permission to appeal is required, against a decision of Deputy President Masson issued on 16 November 2018 1 (Decision). The Decision concerned an application by Wagstaff Piling Pty Ltd (Wagstaff) made pursuant to s 739 of the Fair Work Act 2009 (FW Act) for the Commission to deal with a dispute pursuant to the dispute settlement procedure in clause 10 of the Wagstaff Piling Pty Ltd and the CFMEU (Victorian Construction and General Division) Piling Agreement 2016 – 2018 (Agreement).2 The dispute in question concerned a site allowance to be paid to employees of Wagstaff engaged on the West Gate Tunnel Project (Project) in Melbourne. The Victorian Building Industry Disputes Panel (Panel) had earlier determined, pursuant to Appendix C of the Agreement, that the amount of the site allowance should be $8.90 per hour. Wagstaff’s application sought that the Commission conduct a full review (in the nature of a hearing de novo) of the Panel’s determination. Before the Deputy President, the CFMMEU contended that clause 10 of the Agreement did not confer upon the Commission jurisdiction to deal with the dispute. In the alternative, it contended that if the Commission could deal with the dispute, it could only deal with it as an appeal stricto sensu from the Panel’s determination. The Deputy President rejected both contentions: he found that the Commission had the power under clause 10 of the Agreement to deal with the dispute and review the Panel’s determination, and it was required to do so by conducting a hearing de novo concerning the quantum of the site allowance. In its appeal, the CFMMEU contends that the Deputy President erred in respect of each of these conclusions.
[2] Under s 739(4) of FW Act, the Commission may arbitrate a dispute where empowered to do so by the disputes settlement procedure in an enterprise agreement. Section 739(3) provides that the Commission must not exercise any powers limited by the dispute settlement procedure. In the proceedings before the Deputy President, Wagstaff contended that clause 10 of the Agreement provided the requisite source of power. Clause 10 provides:
“10 Disputes Settlement Procedure
10.1 A major objective of this Agreement is to eliminate lost time and/or production arising out of disputes or grievances. Disputes over any work related or industrial matter or any matters arising out of the operation of the Agreement or incidental to the operation of the Agreement should be dealt with as close to its source as possible. Disputes over matters arising from this Agreement (or any other dispute related to the employment relationship or the NES, including subsections 65(5) or 76(4) of the Fair Work Act)…
Keep reading for free
Create a free CaseChat account to read Construction, Forestry, Maritime, Mining and Energy Union v... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2019] FWCFB 102
- Decision Date