DISTRICT COURT OF QUEENSLAND
CITATION: | Conquest v Bundaberg Regional Council; Conquest v Bundaberg Regional Council [2014] QDC 166 |
PARTIES: | Matter 48/12 ROBERT JOHN CONQUEST v BUNDABERG REGIONAL COUNCIL Matter 49/12 ANN CONQUEST v BUNDABERG REGIONAL COUNCIL |
FILE NO/S: | 48/12 and 49/12 |
DIVISION: | Appellate |
PROCEEDING: | Appeal |
ORIGINATING COURT: | Maroochydore Magistrates Court |
DELIVERED ON: | 8th August 2014 |
DELIVERED AT: | Brisbane |
HEARING DATE: | 28th April and 6th May and written submissions |
JUDGE: | Robertson DCJ |
ORDER: | Appeal dismissed |
CATCHWORDS: | APPEALS: appeal against conviction, sentence, and reparation order; where appellants had caused works to be undertaken on their land at Inness Park via Bundaberg which involved excavating and filling in excess of 50m3 and construction of revetment and retaining walls and access road without any approvals; where respondent issued a Show Cause Notice and appellants responded; where Council issued an Enforcement Notice which was not complied with; whether Enforcement Notice was valid; whether prosecution had proved that the works were not “building work” as defined by the IPA DEVELOPMENT OFFENCES: where only issued ventilated on appeal was whether the works were not building work; whether the learned Magistrate applied the correct “test”; whether subjective intention of appellants in relation to the purpose for the works was relevant to the only live issue on appeal where his Honour had made adverse findings of credit against the appellants. WORDS AND PHRASES : “building work” and “operational works”; whether principles developed in cases decided in merits appeals and other forms of civil proceedings are relevant to the proper approach to the prosecution of a criminal offence |
COUNSEL: | Mr M Black for the appellants Mr M Williamson for the respondent |
SOLICITORS: | Payne Butler Lang for the appellants Connor O’Meara for the respondent |
Both appellants were convicted in the Maroochydore Magistrates Court on 5 October 2012 of one count each of contravening s 4.3.15(1) of the Integrated Planning Act 1997 (“IPA”) in that he/she failed to comply with an enforcement notice dated 14 May 2008 issued by the Bundaberg Regional Council pursuant to s 4.3.11 of the IPA in relation to land situated at Logan Road, Innes Park in the State of Queensland, more particularly described as Lot 2 on RP893359, County Cook, Parish Barolin.
Both appellants were convicted after a trial before Acting Magistrate P Buetel. The trial proceeded over a number of days. From 10 to 11 October 2011 the appellants were represented by Mr Barr of Counsel. On 4 November 2011 and from 22 to 23 December 2012 the appellants represented themselves, or at least the female appellant appeared to take the lead in representing both appellants. I was informed that the parties were the owners of the land as joint tenants but had divorced in 2006. His Honour, not surprisingly, adjourned to consider his judgment which he delivered on 5 October 2012. The judgment covers 75 pages of transcript.
He convicted each of the defendants, fined them each $20,000, ordered them to pay the respondent’s costs fixed…
Keep reading for free
Create a free CaseChat account to read Conquest v Bundaberg Regional Council; Conquest v Bundaberg... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2014] QDC 166
- Decision Date
CaseChat Overview and Summary
In addressing these issues, the court considered the principles that govern the interpretation of "building work" and whether the subjective intentions of the appellants regarding the purpose of the works were relevant. The court examined whether the learned Magistrate correctly applied the appropriate legal test and if the adverse findings of credit against the appellants were justified. The court found that the appellants' intention was not a relevant factor in determining whether the works constituted "building work". Furthermore, the court held that the principles developed in civil cases were not applicable to the prosecution of criminal offences. Consequently, the appeal was dismissed, and the original conviction, sentence, and reparation order were upheld.
Orders
Orders of the court
Appeal dismissed
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi