Concrete Mining Structures Pty Ltd v Cellcrete Australia Pty Ltd (No 3)

Link copied
Case Copied 26 min read

FEDERAL COURT OF AUSTRALIA

Concrete Mining Structures Pty Ltd v Cellcrete Australia Pty Ltd (No 3) [2017] FCA 1483

File number: NSD 775 of 2015
Judge: BURLEY  J
Date of judgment: 12 December 2017
Catchwords: PRACTICE AND PROCEDURE – application for summary judgment – whether cross-claimant has no reasonable prospect of successfully prosecuting the proceeding – whether there is any practical utility in continuing the proceeding – whether proceeding, if continued, would be properly constituted – whether cross-claimant has standing – application granted
Legislation:

Corporations Act 2001 (Cth) ss 53, 232, 233, 234, 471B

Federal Court of Australia Act 1976 (Cth) s 37M

Federal Court Rules 2011 (Cth) r 26.01

Cases cited:

C v Commonwealth of Australia [2015] FCAFC 113; (2015) 235 FCR 81

Campbell v Backoffice Investments Pty Ltd [2009] HCA 25; (2009) 238 CLR 304

Danthanarayana v Commonwealth of Australia [2016] FCAFC 114

General Steel Industries Inc v Commissioner for Railways(NSW) [1964] HCA 69; (1964) 112 CLR 125

John Alexander’s Clubs Pty Ltd v White City Tennis Club Ltd [2010] HCA 19; 241 CLR 1

O D Transport (Australia) Pty Ltd (In liquidation) & OrsvO D Transport Pty Ltd & Ors (1997) 80 FCR 290

Polar Aviation Pty Ltd v Civil Aviation Safety Authority [2012] FCAFC 97; (2012) 203 FCR 325

Spencer v Commonwealth [2010] HCA 28; (2010) 241 CLR 118

Date of hearing: 14 November 2017
Registry: New South Wales
Division: General Division
National Practice Area: Intellectual Property
Sub-area: Copyright and Industrial Designs
Category: Catchwords
Number of paragraphs: 42
Solicitor for the Applicant: Mr K Metlej of Craddock Murray Neumann Lawyers
Counsel for the Respondent The Respondent appeared by telephone
Counsel for the Second and Third Cross-Respondents: Mr C Wood with Mr N Avery-Williams
Solicitor for the Second and Third Cross-Respondents: Redmond Hale Simpson

ORDERS

NSD 775 of 2015
BETWEEN:

CONCRETE MINING STRUCTURES PTY LTD ACN 161 504 294

Applicant

AND:

CELLCRETE AUSTRALIA PTY LTD ACN 135 612 421

First Respondent

DAVID REINIGER

Second Respondent

AND BETWEEN:

CELLCRETE AUSTRALIA PTY LTD ACN 135 612 421 (and another named in the Schedule)

First Cross-Claimant

AND:

CONCRETE MINING STRUCTURES PTY LTD ACN 161 504 294 (and others named in the Schedule)

First Cross-Respondent

JUDGE:

BURLEY J

DATE OF ORDER:

12 DECEMBER 2017

THE COURT ORDERS THAT:

1.The Cross-Claim brought by the Second Cross-Claimant dated 7 December 2015 be dismissed with the Second Cross-Claimant to pay the Cross-Respondents’ costs, including the costs of the Cross-Respondents’ interlocutory application dated 9 October 2017.

2.The Applicant’s proceedings against the Second Respondent be dismissed, with the Applicant to pay the costs of the Second Respondent.

Note:    Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.


REASONS FOR JUDGMENT

BURLEY J:

1.                 Introduction

  1. Concrete Mining Structures Pty Ltd (CMS) commenced proceedings against Cellcrete Australia Pty Ltd (Cellcrete) and its director, David Reiniger, in July 2015. The proceedings involved a claim by CMS against Cellcrete for…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Concrete Mining Structures Pty Ltd v Cellcrete Australia Pty... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2017] FCA 1483
Decision Date

CaseChat Overview and Summary

In the case of Concrete Mining Structures Pty Ltd v Cellcrete Australia Pty Ltd (No 3), the Federal Court was tasked with assessing an application for summary judgment. The Applicant, Concrete Mining Structures Pty Ltd, sought the dismissal of the Cross-Claim filed by the Second Cross-Claimant, Cellcrete Australia Pty Ltd, in relation to a broader dispute concerning intellectual property rights and contractual obligations.

The legal issues before the Court included whether the Second Cross-Claimant had any reasonable prospect of successfully prosecuting the Cross-Claim, whether there was any practical utility in continuing the proceeding, whether the proceeding, if continued, would be properly constituted, and whether the Second Cross-Claimant had standing to bring the Cross-Claim. The Applicant argued that the Cross-Claim was without merit and should be dismissed, while the Second Cross-Claimant contended that the Cross-Claim had merit and should proceed to trial.

The Court found that the Second Cross-Claimant had no reasonable prospect of successfully prosecuting the Cross-Claim, as the evidence and arguments presented were insufficient to support the claims made. Additionally, the Court determined that continuing the proceeding would serve no practical purpose and would not be properly constituted, as the Second Cross-Claimant lacked standing to bring the Cross-Claim. Consequently, the Court granted the Applicant's application for summary judgment, dismissing the Cross-Claim and ordering the Second Cross-Claimant to pay the costs of the Cross-Respondents, including the costs of the Cross-Respondents' interlocutory application. Furthermore, the Court dismissed the Applicant's proceedings against the Second Respondent, with the Applicant ordered to pay the costs of the Second Respondent.

Orders

Orders of the court

1. The Cross-Claim brought by the Second Cross-Claimant dated 7 December 2015 be dismissed with the Second Cross-Claimant to pay the Cross-Respondents’ costs, including the costs of the Cross-Respondents’ interlocutory application dated 9 October 2017.

2. The Applicant’s proceedings against the Second Respondent be dismissed, with the Applicant to pay the costs of the Second Respondent.

Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.