SUPREME COURT OF QUEENSLAND
CITATION:
Comprite P/L v Returned & Services League of Australia (Queensland Branch) [2008] QSC 234
PARTIES:
COMPRITE PTY LTD ACN 010 486 736
(plaintiff)
v
RETURNED AND SERVICES LEAGUE OF AUSTRALIA (QUEENSLAND BRANCH)(defendant)
FILE NO/S:
1047 of 2006
DIVISION:
Trial Division
PROCEEDING:
Application
ORIGINATING COURT:
Supreme Court at Brisbane
DELIVERED ON:
26 September 2008
DELIVERED AT:
Brisbane
HEARING DATE:
16 September 2008
JUDGE:
de Jersey CJ
ORDERS:
1. That the defendant’s counter claim be struck out.
2. That the defendant pay the plaintiff’s costs of and incidental to the application to be assessed on the standard basis.
CATCHWORDS:
ABUSE OF PROCESS – striking out pleading – prejudicial and embarrassing – leave to re-plead
Australian Commercial Research and Development Ltd v Commonwealth (1995) 2 Qd R 336, cited
David Securities Pty Ltd v Commonwealth Bank of Australia (1992) 175 CLR 353, referred to
COUNSEL:
W Sofronoff QC SG, with T Bradley , for the plaintiff
J A Griffin QC, with R Clutterbuck, for the defendant.
SOLICITORS:
Russell and Company for the plaintiff
Mylne Lawyers for the respondent
de Jersey CJ: The plaintiff seeks orders that the defendant’s counter-claim be struck out, and for additional or alternative relief.
The plaintiff’s claim is for approximately $2.6 million, reimbursable expenses incurred by the plaintiff between 1987 and 2005 in conducting art unions for the defendant. The defendant has counter-claimed for damages in an amount exceeding $7.5 million.
The plaintiff contends that the counter-claim does not disclose a reasonable cause of action, may prejudice and delay a fair trial, incorporates unnecessary material, and is otherwise an abuse of process.
The problems attending the counter-claim may be summarized as follows.
Pleading of breach
In para 25(b) of the counterclaim, the defendant alleges:
“(In) breach of the agreement, however, some of those charges were…in excess of …the amounts…the plaintiff was entitled to charge under the agreement; and/or…not properly payable by the defendant to the plaintiff under the agreement.”
The pleading does not specify which terms were breached, and the limit of the entitlement, so that the manner of arriving at the alleged excess can be seen. On 17 January 2007, the plaintiff sought particulars of the terms relied upon, and received no reply. The request was renewed on 28 July 2008 after the proceedings were put into their present consolidated state. The response was as follows:
“The defendant says that because of the construction of the agreement, that is, the agreement of 1 April 1999, that the figures referred to in column 12 of the Schedule accompanying the defence and counter-claim were the only sums which the plaintiff was entitled to charge the defendant.”
That response was inadequate. The defendant should have identified the contractual provisions or mechanism which led to that result.
The schedule referred to in that response lists, as instances of “excess” claiming, various amounts in respect of a large number of art unions, but without any indication how the amount of the excess has been calculated or…
Keep reading for free
Create a free CaseChat account to read Comprite P/L v. Returned & Services League of Australia (Que... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2008] QSC 234
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
1. That the defendant’s counter claim be struck out.
2. That the defendant pay the plaintiff’s costs of and incidental to the application to be assessed on the standard basis.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi