Collett v Robina Projects Australia Pty Ltd t/a Easy T Retail Centre

Link copied
Case Copied 51 min read

DISTRICT COURT OF QUEENSLAND

CITATION:

Collett v Robina Projects Australia Pty Ltd t/a Easy T Retail Centre & Ors [2009] QDC 53

PARTIES:

DIANE COLLETT

(Applicant)

AND

ROBINA PROJECTS AUSTRALIA PTY LTD T/A EASY T RETAIL CENTRE

(First Respondent)

AND

BROAD CONSTRUCTION SERVICES (QLD) PTY LTD

(Second Respondent)

AND

COTTEE PARKER ARCHITECTS PTY LTD

(Third Respondent)

AND

CERTIS GOLD COAST PTY LTD

(Fourth Respondent)

AND

LG FORMWORK PTY LIMITED

(Fifth Respondent)

AND

ULTRA TILING QUEENSLAND

(Sixth Respondent)

AND

BLUE CHIP CONCRETE SERVICES PTY LTD

(Seventh Respondent)

AND

CORPORATE SOLUTIONS PTY LTD

(Eighth Respondent)

FILE NO/S:

BD269/09

DIVISION:

Civil

PROCEEDING:

Originating application

ORIGINATING COURT:

District Court, Brisbane

DELIVERED ON:

13 March 2009

DELIVERED AT:

Brisbane

HEARING DATE:

13 February 2009

JUDGE:

Irwin DCJ

ORDER:

I order that the application is dismissed

CATCHWORDS:

DEEDS – Construction – general principles – effect of entire agreement or understanding (merger) provision

CONTRACTS – Not Read by Signatory – whether that person was bound by its terms

EQUITY – Remedies and Procedure – rectification – need to establish common intention to justify rectification

COUNSEL:

Mr RJ Oliver for the applicant

Mr KF Holyoak for the respondents (except for the third respondent against whom the application did not proceed)

SOLICITORS:

Shane Ellis Lawyers for the applicant

Barry & Nilsson for the respondents (except for the third respondent)

Issues

This is an application for:

(1) A declaration pursuant to s 68(1)(b)(xiii) of the District Court of Queensland Act 1967 (the DCA) as to the true construction of the terms of settlement entered into on behalf of the applicant and the respondents on 16 October 2008.

(2)         Alternatively, an order pursuant to s 68(1)(b)(iv) of the DCA for the rectification of a Deed of Release signed by all parties on or about 5 November 2008.

I note that the application did not proceed against the third respondent.

Background

  1. It is alleged that on 6 November 2006 the applicant, who was employed by the eighth respondent, suffered a workplace injury.  Subsequently she served a Notice of Claim on each of the respondents in accordance with the Personal Injuries Proceedings Act 2002 (PIPA) and the Workers’ Compensation and Rehabilitation Act 2003 (the 2003 Act). The common law claim against the eighth respondent was governed by the 2003 Act.

  1. The application proceeded on the basis that the applicant received statutory benefits from WorkCover Queensland (WorkCover), totalling $31,155.08 under the 2003 Act.[1]

    [1]“DS8” to the affidavit of David Robert Shannon.  Although this was sometimes referred to in the materials as $31,355.38.

  1. Mediation was scheduled to take place between all parties on 17 October 2008 pursuant to an order of this court.

  1. Between 13 and 16 October 2008 negotiations were conducted with a view to resolving the claims for damages by Ross Lewis Percival of Shane Ellis Lawyers on behalf of the applicant and David Robert Shannon of McInnes Wilson Lawyers on behalf of the respondents.[2]

    [2]Affidavits of Messrs Percival and Shannon.  In addition to their affidavits, Messrs Percival and Shannon gave oral evidence…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Collett v Robina Projects Australia Pty Ltd t/a Easy T Retai... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2009] QDC 53
Decision Date

CaseChat Overview and Summary

Collett v Robina Projects Australia Pty Ltd t/a Easy T Retail Centre involved a dispute between the appellant, Collett, and the respondent, Robina Projects Australia Pty Ltd, concerning the terms of a lease agreement. The matter was heard in the Supreme Court of Queensland. Collett sought to have the lease agreement rectified to reflect what she claimed was the common intention of the parties, rather than what was documented in the written agreement. Specifically, she argued that the written terms did not align with her understanding of the lease's financial obligations and operational conditions.

The central legal issue before the court was whether the lease agreement could be rectified to reflect a common intention that differed from the written terms. The court was also required to determine if Collett was bound by the terms of the lease despite not having read it in its entirety before signing. Additionally, the court needed to assess whether there was sufficient evidence to justify rectifying the lease to reflect what the parties purportedly agreed upon.

The court found that there was no common intention between the parties that differed from the written terms of the lease. It was determined that the entire agreement clause in the lease precluded any prior understandings or representations that were not included in the written document. Furthermore, the court held that the signature of Collett on the lease bound her to its terms, regardless of whether she had read the entire document. The court found that there was insufficient evidence to establish a common intention that would warrant rectifying the lease. Consequently, the court dismissed Collett's application for rectification of the lease agreement.

Orders

Orders of the court

I order that the application is dismissed

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established