Coastal Protection Amendment Act 2012 (NSW)
An Act to amend the Coastal Protection Act 1979 to make further provision with respect to the use and occupation of the coastal region and to facilitate the carrying out of certain temporary coastal protection works; and for other purposes.
This Act is the Coastal Protection Amendment Act 2012.
This Act commences on a day or days to be appointed by proclamation.
Omit “emergency coastal protection works” and “Emergency coastal protection works” wherever occurring.
Insert instead “temporary coastal protection works” and “Temporary coastal protection works”, respectively.
Omit the definition of
Insert in alphabetical order:
Omit the definition.
Omit “emergency coastal protection works”.
Insert instead “temporary coastal protection works”.
Insert at the end of the section:
However, if:
(a) a person commits the offence under subsection (1) by placing material on a beach, or a sand dune adjacent to a beach, and
(b) the material is material of the kind referred to in section 55P (1) (a) or (b),
the maximum penalty for the offence is 2,250 penalty units (in the case of a corporation) or 1,125 penalty units (in any other case).
Omit “if the works are authorised by a certificate under Division 2”.
Insert instead “that comply with the requirements for those works set out in this Act”.
Omit the note. Insert instead:
This means that planning and associated approvals are not required for the placement and maintenance of temporary coastal protection works that comply with the requirements for such works set out in this Act—see section 55W.
Omit section 55P (2) (a), (b) and (c). Insert instead:
the material must be placed by or on behalf of an owner of land to reduce the impact or likely impact from wave erosion on that land,
Omit the section.
Omit section 55R (1) (a).
Omit the section.
Omit the heading. Insert instead:
Omit section 55T (1) and (2). Insert instead:
A certificate under this Division authorises the certificate holder to use and occupy public land for the placing and maintaining of the temporary coastal protection works to mitigate the effects of wave erosion on the holder’s land (without obtaining a lease, licence or permit in respect of, or an easement or right-of-way in relation to, the public land).
An owner of land (or a person acting on behalf of, and with the written authority of, the owner of land) may apply to the relevant local council or to the Director-General for a certificate under this Division.
An issuing authority must not issue a certificate unless the authority is satisfied that all reasonable measures have been taken and will be taken:
(a) to avoid using or occupying the public land for the placing and maintaining of the works, and
(b) to ensure reasonable public access (including access for local and public authorities) to and through the beach concerned is maintained.
Insert after section 55T (3):
It is a condition of a certificate under this Division that the holder of the certificate must take all reasonable measures:
(a) to avoid damage to assets and vegetation on the public land, and
(b) to minimise risks to the public on the public land, and
(c) to minimise disruption of the public use of the beach concerned.
Omit the note.
Insert after section 55T (7):
An issuing authority may delegate the exercise of any function of the authority under this section to:
(a) an authorised officer, or
(b) any person, or any class of persons, authorised for the purposes of this section by the regulations.
Omit the definition of
Omit “emergency works authorised officer who”.
Insert instead “person or body that”.
Omit the paragraphs. Insert instead:
the relevant council—if the certificate was issued by the Director-General,
the Director-General—if the certificate was issued by a council,
Insert after section 55V:
The maximum period allowed for temporary coastal protection works on public land is 2 years commencing on the placement of the works.
Despite subsection (1), if at the expiry of the 2-year period referred to in that subsection, a development application is pending under the Environmental Planning and Assessment Act 1979 for consent to development for the purposes of coastal protection works on the public land, the maximum period allowed for the works ends:
(a) where, on the final determination of that development application (including any appeals relating to that application), the application is refused—21 days after that final determination, or
(b) where, on the final determination of that development application (including any appeals relating to that application), the application is granted—such further period as is specified in the consent.
Works cease to be temporary coastal protection works for the purposes of this Act if the works remain in place for longer than the maximum period allowed for temporary coastal protection works under this section.
A public authority must not unreasonably refuse a person access to the public authority’s public land to enable the person to lawfully place temporary coastal protection works on the land or on other public or private land.
Omit “in reliance on section 55Z” from section 55X (1) (b).
Omit the subsection. Insert instead:
The notification under subsection (1) is to be made in the manner and to the person or persons specified by the regulations for the purposes of this subsection.
Maximum penalty:
(a) in the case of a corporation—100 penalty units, or
(b) in any other case—50 penalty units.
Omit “on land” from section 55Y (1). Insert instead “on public land”.
Omit the following:
Maximum penalty:
(a) in the case of a corporation—4,500 penalty units and 400 penalty units for each day the offence continues, or
(b) in any other case—2,250 penalty units and 200 penalty units for each day the offence continues.
Insert instead:
Maximum penalty:
(a) in the case of a corporation—2,250 penalty units and 200 penalty units for each day the offence continues, or
(b) in any other case—1,125 penalty units and 100 penalty units for each day the offence continues.
Renumber the section as section 55VC and move it to its appropriate location in Division 2 of Part 4C.
Omit the section. Insert instead:
An owner of land may use and occupy adjacent land (other than public land) for the placing, maintaining and removal of temporary coastal protection works, but only if that landowner has obtained a lease, easement, right-of-way or other interest in land from the owner of the adjacent land to use and occupy the adjacent land for that purpose.
Insert “on public land” before “or the works are not being maintained” in section 55ZC (1) (d).
Omit the paragraphs.
Insert “on public land” after “protection works” where firstly occurring.
Omit the note.
Omit “under this Part” from section 55ZF (1).
Insert instead “under section 55ZA or 55ZB”.
Insert after section 55ZF (1):
A person who does not comply with an order under section 55ZC is guilty of an offence.
Maximum penalty:
(a) in the case of a corporation—2,250 penalty units and 200 penalty units for each day the offence continues, or
(b) in any other case—1,125 penalty units and 100 penalty units for each day the offence continues.
Omit section 55ZH (1) and (2). Insert instead:
If an original owner of private land to whom a certificate under Division 2 of Part 4C has been issued ceases, before placing temporary coastal protection works on public land, to be the owner of the private land, a successor in title is taken for the purposes of this Act to be the original owner. Such a successor in title may place and maintain those authorised temporary coastal protection works on the public land in accordance with that certificate.
A person who places temporary coastal protection works may be made the subject of an order under this Part—see section 55ZC.
If an original owner of land, after placing temporary coastal protection works on that land, but before the works are removed and the land restored in accordance with this Act, ceases to be the owner of that land, a successor in title is taken for the purposes of this Act to be the original owner. Such a successor in title may be made the subject of an order under this Part as if the successor in title were the original owner.
Omit “in accordance with a certificate under Division 2 of Part 4C”.
Insert instead “in accordance with this Act”.
Omit the section.
Omit “55Y” wherever occurring in section 59 (1) and (2).
Insert instead “55VC”.
Insert at the end of clause 1 (1):
Coastal Protection Amendment Act 2012
Omit “emergency coastal protection works” wherever occurring.
Insert instead “temporary coastal protection works”.
Omit “55Y” wherever occurring. Insert instead “55VC”.
Omit the Part.
Omit “emergency coastal protection works” from clause 22 of the Schedule.
Insert instead “temporary coastal protection works”.
Environmental Planning and Assessment Regulation 2000Omit “emergency coastal protection works” wherever occurring in clause 4A of the Schedule.
Insert instead “temporary coastal protection works”.
Omit the subclause.
Local Government Act 1993 No 30Omit “emergency coastal protection works authorised by a certificate under Division 2 of Part 4C of the Coastal Protection Act 1979” from section 733 (3) (f6).
Insert instead “temporary coastal protection works”.
Omit “emergency coastal protection works”.
Insert instead “temporary coastal protection works”.
Omit “emergency coastal protection works” from the definition of
Insert instead “temporary coastal protection works”.
Omit the definition of
Insert in appropriate order:
0
0
0