CMF Projects P/L v Riggall

Link copied
Case Copied 8 min read

DISTRICT COURT OF QUEENSLAND

CITATION:

CMF Projects P/L v Riggall & Anor  [2014] QDC 101

PARTIES:

CMF PROJECTS PTY LTD (ACN 114 539 212)

Respondent/plaintiff

v

BRIAN NOEL MANSON RIGGALL

applicant/first defendant

and

JANE REIMAN RIGGALL

applicant/second defendant

FILE NO/S:

BD4085 of 2013

DIVISION:

Civil Applications

PROCEEDING:

Application for costs

ORIGINATING COURT:

Brisbane

DELIVERED ON:

8 May 2014

DELIVERED AT:

Brisbane

HEARING DATE:

Written submissions to 6 May 2014

JUDGE:

Andrews SC DCJ

ORDER:

Order that the plaintiff pay on the indemnity basis the defendants’ costs of the applications filed on 1 and 15 April 2014

CATCHWORDS:

COSTS – whether indemnity costs appropriate – where one cause of action was reasonably included in pleading but a second cause of action was unreasonably maintained – where both struck out as unenforceable

UCPR 171

Mio Art Pty Ltd v Macequest Pty Ltd & Ors [2013] QSC 211

Mio Art Pty Ltd v Macequest Pty Ltd (No 2) [2013] QSC 271

Colgate Palmolive Co & Anor v Cussons Pty Ltd (1993) 46 FCR 225 at 233; 118 ALR 248

Di Carlo v Dubois & Ors [2002] QCA 225

Gideona v Suncorp Metway Insurance Ltd [2005] QSC 309

COUNSEL:

G I Thomson for the applicant/defendants

G Coveney for the respondent plaintiff

SOLICITORS:

H W L Ebbsworth for the applicant/defendants

Arrow Law for the respondent/plaintiff

  1. The issue is whether indemnity costs are appropriate. On 24 April 2014 in this proceeding I made orders and published reasons.[1]  On the amended application of the defendants (“home owners”) I ordered that the plaintiff’s (“builder’s”) amended statement of claim be struck out.  Because the builder may not maintain its estoppel argument paragraphs 4(d), 10 and 11 of the builder’s reply were ordered to be struck out together with paragraphs 1, 3(b) and 4 of the answer to the amended counter-claim.  The parties had not made submissions as to costs.  By my reasons I observed:

The general rule is that where the court strikes out all or part of a pleading there will be an order that the costs of the application be paid by the unsuccessful party on the indemnity basis.  I am reluctant to impose that order without first giving the unsuccessful builder liberty to make submissions to the contrary.  However, in an effort to spare the parties from wasted expense it seems sensible to order that the plaintiff pay the defendants’ costs of the application calculated on the indemnity basis and to give the plaintiff liberty for 7 days to apply to set aside that order for costs.

  1. The builder has since opposed the indemnity basis for the costs.  The home owners submit that indemnity costs are appropriate.

  1. The builder’s counsel’s submission helpfully drew my attention to Mio Art Pty Ltd v Macequest Pty Ltd (No 2) [2013] QSC 271. With the benefit of that decision I accept that there is no general rule that where the court strikes out all or part of a…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read CMF Projects P/L v Riggall and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2014] QDC 101
Decision Date

CaseChat Overview and Summary

The case involved a dispute between CMF Projects P/L and Riggall, with the latter being the defendants. The plaintiff sought to enforce a written contract, but the defendants argued that the contract was unenforceable due to certain clauses. The matter was heard in the Federal Circuit Court of Australia. The defendants applied to strike out the claims on the grounds that they were unenforceable, and the plaintiff subsequently applied for leave to amend the statement of claim.

The central legal issue was whether indemnity costs were appropriate, given that one cause of action was reasonably included in the pleadings, but a second cause of action was unreasonably maintained. The court considered whether it was appropriate to order the plaintiff to pay the defendants' costs on an indemnity basis, despite the fact that both causes of action were ultimately struck out as unenforceable.

The court held that it was appropriate to order the plaintiff to pay the defendants' costs on an indemnity basis. The court found that while the first cause of action was reasonably included in the pleadings, the second cause of action was unreasonably maintained. The court considered it appropriate to order indemnity costs due to the unreasonable maintenance of the second cause of action. The court emphasised the importance of ensuring that claims are well-founded and reasonable before proceeding with litigation, to avoid unnecessary costs for the opposing party. The court concluded that the plaintiff should pay the defendants' costs of the applications filed on 1 and 15 April 2014 on an indemnity basis.

Orders

Orders of the court

Order that the plaintiff pay on the indemnity basis the defendants’ costs of the applications filed on 1 and 15 April 2014

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.