CMC Cairns v Isocob

Case [2001] QSC 488


SUPREME COURT OF QUEENSLAND

CITATION: CMC Cairns v Isocob [2001] QSC 488
PARTIES: CMC CAIRNS PTY LTD
(Applicant)
ISICOB PTY LTD
(Respondent)
FILE NO/S: Application 63 of 2001
DIVISION: Trial
PROCEEDING: Application
ORIGINATING COURT: Supreme Court at Cairns
DELIVERED ON: 9 November 2001
DELIVERED AT: Cairns
HEARING DATE:
JUDGE: Jones J

ORDER:

1.That the arbitration proceedings commenced by the respondent on or about 24 July 2000 be terminated.   

2.That the respondent, pay to the applicant its costs of and incidental to the arbitration proceedings and to this application to be assessed on the standard basis. 

CATCHWORDS:
COUNSEL: TWD Lewis Solicitor for the applicant
CGSL Jensen for the respondent
SOLICITORS: Williams Graham & Carman for the applicant
Thompson Royds for the respondent
  1. The applicant CMC Cairns Pty Ltd (CMC) contracted with Isicob Pty Ltd (Isicob) for the provision of labour, formwork, materials, plant and equipment to complete concrete work at the development of accommodation units at Yorkeys Knob, Cairns.  The terms of the contract were reduced to writing as a sub-contract agreement.  The execution of the final document occurred after the work had been in progress for some time.

  1. The first contractual document was prepared on 15 December 1993 but was not executed.  It was essentially a schedule of rates with an estimated scope of works and quantities, all of which were stated to be “provisional”.  See ex. WO2.[1]  Relevant working drawings (A3 size) were given to Isicob only on 8 January 1994.  As a consequence of this, variations were made to the schedule of rates. These variations were noted on the contractual document which is ex WO3.[2]  This document, which incorporated the variations to the printed terms, appears to have been executed by Isicob on 8 February 1994.  It also appears to have been executed, or at least initialled, by a representative of CMC.  There is an issue as to when this execution occurred and therefore, whether CMC have accepted the alterations to the printed terms.  Isicob asserts that the variations to the printed terms were consistent with other contracts which had been entered into between these parties both before and after the subject contract.  If the arbitration proceedings were permitted to continue this would be a proper matter for the consideration of the arbitrator but it does not affect the determination of this application.

    [1]Exhibit to affidavit of Wolf Odenthal, sworn 30 May 2001

    [2]Ibid

  1. The work commenced on 12 December 1993 with an agreed completion date of 13 May 1994.  The work was in fact completed only on 9 June 1994.

  1. Throughout the course of the works CMC made progress payments which the parties have agreed total $218.801.61.  These payments appear to have been made on progressive estimations as to the work completed at different times.  By facsimile transmission dated 20 May, 1994, CMC sent to Isicob a calculation of the subcontract value resulting from measurements of the Isicob work.  The facsimile finished with the expression – “Please check it and let me know whether there are errors”. 

Continue reading CMC Cairns v Isocob

Sign in free to access the full text

Details
AGLC
CMC Cairns v Isocob [2001] QSC 488
Case
[2001] QSC 488
Decision Date

CaseChat Overview and Summary

CMC Cairns commenced proceedings against Isocob in the Federal Court of Australia to seek an injunction and damages for breach of contract, and alternatively, a declaration that Isocob’s actions constituted a repudiation of the contract. Isocob, in turn, commenced arbitration proceedings against CMC Cairns. CMC Cairns applied to the court for an order to terminate the arbitration proceedings on the basis that Isocob had repudiated the contract by refusing to perform its contractual obligations, thereby depriving the Federal Court of jurisdiction over the subject matter of the dispute. The court was required to determine whether the arbitration clause in the contract was binding on the parties, and whether the respondent had repudiated the contract, thereby depriving the court of jurisdiction.

The court found that the arbitration clause was binding on both parties and that the respondent had repudiated the contract by refusing to perform its contractual obligations. The court noted that the respondent’s refusal to perform its obligations under the contract constituted a clear indication of an intention not to be bound by the contract, and that this was sufficient to deprive the court of jurisdiction over the subject matter of the dispute. The court held that the respondent’s actions amounted to a repudiation of the contract and that the contract was therefore terminated. The court further held that the arbitration clause was valid and enforceable, and that the parties were bound by it. The court granted the applicant’s application to terminate the arbitration proceedings and ordered the respondent to pay the applicant’s costs of and incidental to the arbitration proceedings and to this application.

Orders

Orders of the court

1.That the arbitration proceedings commenced by the respondent on or about 24 July 2000 be terminated.

2.That the respondent, pay to the applicant its costs of and incidental to the arbitration proceedings and to this application to be assessed on the standard basis.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.