FEDERAL COURT OF AUSTRALIA
Clifford Constructions Pty Limited (in liquidation) v Lucca Rd Pty Ltd [2025] FCA 897
File number(s): NSD 1053 of 2020 Judgment of: OWENS J Date of judgment: 5 August 2025 Catchwords: CORPORATIONS – application pursuant to s 477(2B) of the Corporations Act for approval of settlement agreements – retrospective approval sought – approval granted Legislation: Corporations Act 2001 (Cth), ss 477(2B), 588FDA
Federal Court of Australia Act 1976 (Cth), ss 37AF, 37AG(1)(a)
Cases cited: Binqld Finances Pty Ltd (in liq) v Binetter (settlement approval) [2025] FCA 811
In the matter of One.Tel Limited [2014] NSWSC 457
Lewis (liquidator), in the matter of Concrete Supply Pty Ltd (in liq) [2020] FCA 841
Lindholm (liquidator), in the matter of Aviation 3030 Pty Ltd (in liq) [2021] FCA 1244
Naidenov, in the matter of AJW Interiors and Constructions Pty Ltd (in liq) [2024] FCA 25
Division: General Division Registry: New South Wales National Practice Area: Commercial and Corporations Sub-area: Corporations and Corporate Insolvency Number of paragraphs: 21 Date of hearing: 4-5 August 2025 Counsel for the Plaintiffs: Mr A Spencer Solicitor for the Plaintiffs: Addisons ORDERS
NSD 1053 of 2020 BETWEEN: CLIFFORD CONSTRUCTIONS PTY LIMITED (IN LIQUIDATION) ACN 054 514 859
First Plaintiff
STEWART WILLIAM FREE IN HIS CAPACITY AS LIQUIDATOR OF CLIFFORD CONSTRUCTIONS PTY LTD (IN LIQUIDATION) ACN 054 514 859
Second Plaintiff
AND: LUCCA RD PTY LTD ACN 612 771 678
First Defendant
STUART DAVID ABBOTT
Second Defendant
AND BETWEEN: LUCCA RD PTY LTD ACN 612 771 678
Cross-Claimant
AND: CLIFFORD CONSTRUCTIONS PTY LIMITED (IN LIQUIDATION) ACN 054 514 859
Cross-Defendant
ORDER MADE BY:
OWENS J
DATE OF ORDER:
5 AUGUST 2025
THE COURT ORDERS THAT:
1.Pursuant to s 37AF of the Federal Court of Australia Act 1976 (Cth), on the ground specified in s 37AG(1)(a) of that Act, Confidential Exhibit B be kept confidential and not be published, made available or disclosed to any person other than the Court or the parties to this proceedings and their legal representatives until 5 August 2026.
2.Pursuant to s 477(2B) of the Corporations Act 2001 (Cth), the Court approves nunc pro tunc the plaintiffs’ entry into of the Heads of Agreement dated 29 May 2025 and the Deed of Settlement and Release dated 1 July 2025, copies of which were Annexure A to the affidavit of Stewart William Free sworn 4 July 2025, and Exhibit A, respectively.
3.The plaintiffs’ costs of this application be costs in the liquidation of the first plaintiff.
Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.
REASONS FOR JUDGMENT
Delivered ex tempore, revised from transcriptOWENS J:
Before it was placed into liquidation, the first plaintiff, Clifford Constructions Pty Ltd (in liquidation), was engaged in the business of constructing large retail buildings for commercial clients. The second plaintiff was appointed liquidator of that company on 4 June 2020, having earlier, on 3 April 2020, been appointed voluntary administrator.
The shares in Clifford Constructions were at…
Keep reading for free
Create a free CaseChat account to read Clifford Constructions Pty Limited (in liquidation) v Lucca... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2025] FCA 897
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the Court was whether the settlement agreements were in the best interests of the creditors of Clifford Constructions Pty Limited. The Court had to consider whether the liquidators had acted appropriately and whether the settlements were fair, considering the interests of the creditors and the potential benefits of pursuing litigation. The Court also needed to decide whether to grant retrospective approval of the settlement agreements, despite them being entered into before the application for approval was lodged.
The Court found that the liquidators had acted in the best interests of the creditors of Clifford Constructions Pty Limited. The Court was satisfied that the settlement agreements were fair and reasonable, and that the liquidators had properly considered the interests of the creditors. The Court noted that the settlements provided immediate and certain benefits to the creditors, which outweighed the potential risks and costs associated with pursuing litigation. Consequently, the Court granted retrospective approval of the settlement agreements. The Court also ordered that certain confidential information be kept confidential until 5 August 2026, and that the costs of the application be costs in the liquidation of Clifford Constructions Pty Limited.
Orders
Orders of the court
1. Pursuant to s 37AF of the Federal Court of Australia Act 1976 (Cth), on the ground specified in s 37AG(1)(a) of that Act, Confidential Exhibit B be kept confidential and not be published, made available or disclosed to any person other than the Court or the parties to this proceedings and their legal representatives until 5 August 2026.
2. Pursuant to s 477(2B) of the Corporations Act 2001 (Cth), the Court approves nunc pro tunc the plaintiffs’ entry into of the Heads of Agreement dated 29 May 2025 and the Deed of Settlement and Release dated 1 July 2025, copies of which were Annexure A to the affidavit of Stewart William Free sworn 4 July 2025, and Exhibit A, respectively.
3. The plaintiffs’ costs of this application be costs in the liquidation of the first plaintiff.
Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.