| CITATION: | Clelland v Ommensen [2014] QCAT 366 |
| PARTIES: | Alaisdair Clelland (Applicant) |
| v | |
| Stuart Ommensen (Respondent) |
| APPLICATION NUMBER: | BDL301-13 |
| MATTER TYPE: | Building matters |
| HEARING DATE: | 25 July 2014 |
| HEARD AT: | Brisbane |
| DECISION OF: | Member Gardiner |
| DELIVERED ON: | 31 July 2014 |
| DELIVERED AT: | Brisbane |
| ORDERS MADE: | 1. Mr Clelland is to pay Mr Ommensen $32,302.11 within 14 days. 2. Mr Clelland is to provide to Mr Ommensen any outstanding warranty documentation within 14 days. |
| CATCHWORDS: | BUILDING MATTER – Dispute between builder and home owner about the final payment of a contract to renovate a house – WHERE applicant did not attend hearing at short notice – WHERE final invoice not paid by homeowner because of allegations of defects – WHERE 53 variations but only 5 in dispute – WHERE experts have different views of workmanship of builder – WHERE one expert must be preferred – WHETHER there are major defects with the renovation of the home – WHETHER liquidated damages and loss of rent should be allowed Queensland Building and Construction Commission Act 1991 (Qld) |
APPEARANCES and REPRESENTATION (if any):
| APPLICANT: | No appearance |
| RESPONDENT: | Mr Ommensen, in person |
REASONS FOR DECISION
Alaisdair Clelland is a builder who entered into a contract with Stuart Ommensen to renovate Mr Ommensen’s Queenslander style home at Paddington by building in under the house and making other alterations.
The original contract amount was $338,977.00. Without counting the variations in dispute, the final contract price as agreed by the parties with all other consensual variations allowed is $335,605.05[1].
[1]Mr Ommensen’s amended spreadsheet filed 25 July 2014.
Added to this are further consensual plumbing, electrical and provisional sum variations which add $1,037.00, $6,221.36 and $3,304.00 respectively. This totals $346,167.41.
In December 2013 Mr Clelland filed an application for a domestic building dispute seeking monies owing under, and as a result of the contract, from Mr Ommensen of $17,024.92.
While Mr Clelland seeks payment under the contract, Mr Ommensen in his response and counter-claim filed on 6 February 2014 seeks the following amounts:
Reimbursement of funds overpaid $ 5,903
Structural defects costed and assessed at $ 41,355
Water damage assessed at $ 11,539
Loss of rental $ 50,062
Total $108,859
The matter was set down before the Tribunal as a hearing at 9.30am on 25 July 2014. At 9:00am on the morning of the hearing an email was received by the registry from Mr Clelland advising the Tribunal that he did not intend to appear at the hearing. The registry, on instructions from the Tribunal, both emailed and spoke to Mr Clelland, encouraging him to attend the hearing and pointing out that the Tribunal would be limited to considering his application and any submissions received already if he did not attend.
Mr Clelland accepted this in a telephone call with the case officer of the registry saying that he did not mean any disrespect to the Tribunal, but that he had had personal issues and that he understood the decision…
Continue reading Clelland v Ommensen
Sign in free to access the full text
- AGLC
- Clelland v Ommensen [2014] QCAT 366
- Case
- [2014] QCAT 366
- Decision Date
CaseChat Overview and Summary
The Tribunal examined the evidence presented by both parties, including expert reports and submissions, to determine the outcomes of the various disputes. The Tribunal allowed most of the variations agreed upon by both parties, finding that exceptional circumstances applied and that it would not be unfair to Mr Ommensen to allow Mr Clelland to recover amounts for these variations. The Tribunal also found that certain rectification costs were reasonable and should be allowed, while other costs were to be left where they fell due to insufficient evidence. Regarding defects, the Tribunal allowed certain rectification costs for structural defects but disallowed costs for water damage and insurance as they were not adequately substantiated by Mr Ommensen. The Tribunal further found that the liquidated damages claimed by Mr Ommensen were excessive and allowed a lesser amount for the time delays caused by necessary rectifications. Finally, the Tribunal disallowed Mr Ommensen’s claim for loss of rent as he had not mitigated his losses and had chosen not to rent the affected bedroom.
The final orders of the Tribunal were that Mr Clelland was to pay Mr Ommensen $32,302.11 within 14 days and provide any outstanding warranty documentation within the same timeframe. This decision balanced the claims and counterclaims between the parties, taking into account the evidence presented and the applicable statutory provisions.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.