Claymont Westcapital Pty Ltd and East Perth Redevelopment Authority

Link copied
Case Copied 19 min read

JURISDICTION     :   STATE ADMINISTRATIVE TRIBUNAL

STREAM:   DEVELOPMENT & RESOURCES

ACT: EAST PERTH REDEVELOPMENT ACT 1991 (WA)

CITATION:   CLAYMONT WESTCAPITAL PTY LTD and EAST PERTH REDEVELOPMENT AUTHORITY [2008] WASAT 77

MEMBER:   MR D R PARRY (SENIOR MEMBER)

HEARD:   2 APRIL 2008

DELIVERED          :   2 APRIL 2008

FILE NO/S:   DR 72 of 2008

BETWEEN:   CLAYMONT WESTCAPITAL PTY LTD

Applicant

AND

EAST PERTH REDEVELOPMENT AUTHORITY
Respondent

Catchwords:

Town planning - Application to amend development application by stipulating additional period of six months for substantial commencement - Development approval specified two years for substantial commencement - Application to extend time lodged one month before end of two-year period - Building licence issued one week after end of two-year period - Whether development approval has lapsed - Whether Tribunal has power to extend time after end of two-year period - Whether extension of time is consistent with orderly and proper planning - Whether approval of the application is futile

Legislation:

East Perth Redevelopment Act 1991 (WA), s 43, s 45
State Administrative Tribunal Act 2004 (WA), s 29

Result:

Development approval amended by specifying an additional period of six months for substantial commencement of the development

Category:    B

Representation:

Counsel:

Applicant:     Mr LA Tsaknis

Respondent:     Mr MA Etherington

Solicitors:

Applicant:     Pullinger Readhead Lucas

Respondent:     Minter Ellison

Case(s) referred to in decision(s):

Fazio & Anor v City of Fremantle (Unreported, SCWA, Wheeler C, 16 August 1996, CIV 2314 of 1995)

REASONS FOR DECISION OF THE TRIBUNAL: 

Summary of Tribunal's decision

  1. The applicant obtained development approval from the respondent to construct a five-storey mixed use development.  The local planning scheme said that the approval would lapse if the development is not substantially commenced within two years of the approval, unless the respondent specified a different period.  The respondent did not specify a different period.

  2. The applicant submitted working drawings to the respondent which were ultimately cleared by the respondent for a building licence.  The building licence authority required a substantial number of items to be addressed before it would issue a building licence.  While the applicant's architect and consultants worked on these items, progress was slow, because the consultants were busy.  Ultimately, a building licence was issued to enable construction of the basement eight days after the end of the two-year period for substantial commencement.

  3. Meanwhile, the applicant applied to the respondent almost a month before the end of the two-year period for an amendment to the development approval to stipulate an additional period of six months for substantial commencement.  The local planning scheme expressly allowed the respondent to amend a development approval.  On the day before the end of the two‑year period, the respondent refused to allow the amendment.  On the day after the end of the two-year period, the applicant sought review of the respondent's decision.

  4. The principal issues in the review were:

    •whether the development approval has lapsed;

    •whether the Tribunal has power to extend the substantial commencement period;

    •whether an extension of the period is consistent with orderly and proper planning; and

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Claymont Westcapital Pty Ltd and East Perth Redevelopment Au... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2008] WASAT 77
Decision Date

CaseChat Overview and Summary

In the matter of Claymont Westcapital Pty Ltd, the applicant, and East Perth Redevelopment Authority, the respondent, the matter was heard in the Western Australian Civil and Administrative Tribunal. The applicant sought to amend the development approval granted by the respondent for the construction of a five-storey mixed-use development with an undercroft at Lot 204 Brown Street, East Perth. The applicant sought an extension of six months for the substantial commencement of the development, which was originally stipulated to be completed within two years of the approval date. The application was lodged one month before the expiry of the two-year period, and the building licence was issued one week after the end of the two-year period. The central legal issues before the tribunal were whether the development approval had lapsed, whether the tribunal had the power to extend the time after the end of the two-year period, whether extending the time was consistent with orderly and proper planning, and whether approving the application was futile.

The tribunal held that the development approval had not lapsed as the building licence was issued one week after the end of the two-year period. The tribunal also held that it had the power to extend the time under clause 2.17A(1) of the East Perth Redevelopment Scheme. The tribunal found that extending the time was consistent with orderly and proper planning as the applicant had made significant efforts to commence the development within the original two-year period but was unable to do so due to unforeseen circumstances. The tribunal held that approving the application was not futile as the development could still be completed within the extended period. The tribunal allowed the application for review, set aside the respondent's decision to refuse to approve the application, and amended the development approval by stipulating an additional period of six months for substantial commencement of the development. The development approval shall lapse if the development has not been substantially commenced on or before 27 August 2008.

Orders

Orders of the court

1. The application for review is allowed. 2. The decision of the respondent made on 26 February 2008 to refuse to approve the application made under cl 2.17A(1) of the East Perth Redevelopment Scheme to amend the development approval granted by the respondent on 27 February 2006 for the construction of a five-storey mixed use development with undercroft at Lot 204 Brown Street, East Perth, by stipulating an additional period of six months for substantial commencement of the development, is set aside. 3. Pursuant to cl 2.17A(1) of the East Perth Redevelopment Scheme, the development approval granted by the respondent on 27 February 2006 for construction of a five-storey mixed use development with undercroft at Lot 204 Brown Street, East Perth is amended by stipulating an additional period of six months for substantial commencement of the development, so that the development approval shall lapse if the development has not been substantially commenced on or before 27 August 2008.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established