SUPREME COURT OF QUEENSLAND

CITATION:

Clarricoats v JJ Richards & Sons Pty Ltd  (No 2) [2018] QSC 30

PARTIES:

JOSHUA BENJAMIN CLARRICOATS

(Plaintiff)

v

JJ RICHARDS & SONS PTY LTD

(Defendant)

FILE NO/S:

S615 of 2015

DIVISION:

Trial Division

PROCEEDING:

Trial

ORIGINATING COURT:

Supreme Court at Rockhampton

DELIVERED ON:

 27 February 2018

DELIVERED AT:

Rockhampton

HEARING DATE:

On the papers.

JUDGE:

McMeekin J

ORDER:

The plaintiff pay the defendant’s costs from 5 August 2015, including the costs thrown away by the adjournment on 3 April 2017, to be assessed on the standard basis.1.  

CATCHWORDS:

PROCEDURE – CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS – COSTS – GENERAL RULE – COSTS FOLLOW THE EVENT – OTHER PARTICULAR CASES AND MATTERS – where the plaintiff sought an adjournment because of problems caused by the substantial flooding that occurred in Central Queensland and Northern New South Wales – where the flooding caused significant difficulties in getting the plaintiff, his witnesses and solicitor from Lismore to Rockhampton – where in such circumstances the adjournment was granted – where neither party is responsible for the circumstances which led to the adjournment – whether costs of the adjournment should follow the event

Workers’ Compensation & Rehabilitation Act 2003 (Qld), s 240(2), s 292, s 316

Earp Woolcock Beveridge & Co Ltd v Gordon
cited
Electrolytic Zinc Co of Australasia Ltd v Cieslak
[1969] Tas SR 50, followed
Pell v Linnell (1868) LR 3 CP 441, cited
Queensland v Brooks & McCabe
[2006] QCA 523, followed
Sandvik Mining and Construction Australia Pty Ltd v Dempsey Australia Pty Ltd [2012] QSC 102, cited
Zuecker v Bruggmann [2016] QSC 115, cited

COUNSEL:

DA Wheelahan QC with PJ Woods for the Plaintiff

GF Crow QC for the Defendant

SOLICITORS:

Bourke Love Lawyers for the Plaintiff

DibbsBarker for the Defendant

  1. McMEEKIN J:  On 29 September 2017 I gave judgment for the defendant dismissing the plaintiff’s claim. I gave the parties leave to make submissions on costs. The Defendant has done so. The plaintiff has not.

  1. The defendant seeks that the plaintiff pay its costs, including reserved costs, from the date of a final written offer made pursuant to s 292 Workers’ Compensation & Rehabilitation Act 2003 (Qld) (“the Act”). The defendant offered to settle by paying the plaintiff $250,000 clear of the WorkCover refund.

  1. The plaintiff’s notice of assessment under the Act stated that he had a DPI of less than 20% and did not have a terminal condition. Because of that Part 12 division 2 of the Act applies in relation to costs: s 240(2) of the Act. Section 316 falls within division 2 of Part 12 of the Act and is relevant. It provides:

316  Principles about orders as to costs

(1)      No order about costs, other than an order allowed under this section, is to be made by the court in the claimant’s proceeding.

(2)      If a claimant or an insurer makes a written final offer of settlement that is refused, the court…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Clarricoats v JJ Richards & Sons Pty Ltd (No 2) and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2018] QSC 30
Decision Date

CaseChat Overview and Summary

The case of Clarricoats v JJ Richards & Sons Pty Ltd (No 2) involved a plaintiff seeking an adjournment due to significant flooding in Central Queensland and Northern New South Wales. The flooding resulted in considerable difficulties for the plaintiff, his witnesses, and his solicitor, who were based in Lismore and needed to travel to Rockhampton for the proceedings. Given these extraordinary circumstances, the court granted the adjournment. Both parties were equally affected by the flooding and bore no responsibility for the delay. The central legal issue before the court was whether the costs incurred due to the adjournment should follow the event, in this case, the plaintiff.

The court deliberated on the principle that costs generally follow the event unless specific circumstances warrant otherwise. The flooding was deemed an extraordinary event beyond the control of either party, which significantly impacted the plaintiff's ability to proceed with the case. The court recognised the necessity of the adjournment due to the flooding and found that neither party was at fault for the delay. Consequently, the court ruled that the costs incurred due to the adjournment should be borne by the plaintiff, as the adjournment was necessary and unavoidable under the circumstances.

In summary, the court held that the plaintiff should bear the costs from 5 August 2015, including those lost due to the adjournment on 3 April 2017, to be assessed on the standard basis. The decision reflects the court's recognition of the extraordinary and uncontrollable nature of the flooding that necessitated the adjournment, thereby absolving both parties of fault and allocating the costs to the plaintiff.

Orders

Orders of the court

The plaintiff pay the defendant’s costs from 5 August 2015, including the costs thrown away by the adjournment on 3 April 2017, to be assessed on the standard basis.1.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.