City of Salisbury v Ahrens Group Pty Ltd

Link copied
Case Copied 22 min read

SUPREME COURT OF SOUTH AUSTRALIA

(Land and Valuation Division: Civil)

CITY OF SALISBURY v AHRENS GROUP PTY LTD

[2010] SASC 254

Judgment of The Honourable Justice Bleby

18 August 2010

ENVIRONMENT AND PLANNING - ENVIRONMENTAL PLANNING - PLANNING OFFENCES - GENERALLY

CRIMINAL LAW - SENTENCE - SENTENCING ORDERS - DISCRETION TO RECORD CONVICTION - RELEVANT CONSIDERATIONS

Respondent pleaded guilty to undertaking development without approval contrary to s 44 of the Development Act 1993 - respondent contracted to provide various building services in relation to the construction of a warehouse and office building - sentencing judge imposed a fine without recording a conviction - application of s 16 Criminal Law (Sentencing) Act 1988 - whether conditions precedent to the exercise of a discretion not to record conviction met - whether extenuating circumstances existed in the present case - whether discretion not to record conviction properly exercised.

Held: sentencing judge erred in holding extenuating circumstances existed - respondent undertook no steps to avoid commission of the offence - no good reason to not record a conviction - appeal allowed - conviction recorded.

Development Act 1993 (SA) s 32, s 44, s 59; Building Work Contractors Act 1995 (SA) s 21, s 25; Criminal Law (Sentencing) Act 1988 (SA) s 16; Development Regulations 1993 (SA) reg 74, referred to.
Leonello v Police [2005] SASC 29; Hemming v Lukin (1996) 67 SASR 248; House v The King (1936) 55 CLR 499, applied.
R v Wilton (1981) 28 SASR 362, distinguished.
Everett v The Queen (1994) 181 CLR 295; Police v Zefi [2003] SASC 218; R v Briese (1996-1997) 92 A Crim R 75, considered.

WORDS AND PHRASES CONSIDERED/DEFINED

"extenuating circumstances"

CITY OF SALISBURY v AHRENS GROUP PTY LTD
[2010] SASC 254

Miscellaneous Appeal

BLEBY J

Introduction

  1. The respondent pleaded guilty in the Environment Resources and Development Court (“the Environment Court”) to a breach of s 44(1) of the Development Act 1993 (SA). Without recording a conviction the Court imposed a fine of $9,000. The sole question on this appeal is whether the Environment Court erred in failing to record a conviction.

  2. Section 44(1) of the Development Act makes it an offence for a person to undertake development contrary to Part 4 Division 1 of the Development Act. The maximum penalty is a fine of $120,000. Particulars of the charge were that between 17 March 2008 and 13 November 2008 the respondent undertook development, namely building work, by constructing or causing the construction of a warehouse and office buildings on certain land at Pooraka. The development was not an approved development. It was therefore undertaken contrary to s 32 of the Development Act, which section is in Part 4 Division 1 of the Act.

    The facts

  3. The respondent was one of three defendants charged with breaches of s 44(1) of the Development Act in respect of the same development.  The first defendant, Giuseppe Rocca, was the developer’s agent and was described in the contract mentioned below as…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read City of Salisbury v Ahrens Group Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2010] SASC 254
Decision Date

CaseChat Overview and Summary

The case of City of Salisbury v Ahrens Group Pty Ltd involves the City of Salisbury, the appellant, and Ahrens Group Pty Ltd, the respondent. The dispute revolves around the respondent's conviction for undertaking development without approval, in contravention of Section 44 of the Development Act 1993. The respondent, a construction company, had been contracted to provide various building services for a warehouse and office building project. Despite not being responsible for obtaining the necessary development approval, the respondent commenced the building work without ensuring compliance with the Development Act. The case was heard in the South Australian Court of Appeal, where the primary issue was whether the sentencing judge correctly exercised the discretion not to record a conviction under Section 16 of the Criminal Law (Sentencing) Act 1988.

The Court of Appeal examined whether the conditions precedent to the exercise of the discretion not to record a conviction were met and whether extenuating circumstances existed in the present case. The sentencing judge had imposed a fine but chose not to record a conviction, citing the respondent's unlikely future reoffending and the existence of extenuating circumstances. The extenuating circumstances included the fact that the responsibility to obtain approval belonged to others and the respondent commenced the building work at the request of others involved in the project. The appellant argued that these circumstances did not constitute extenuating circumstances as they did not relate to any action or failure on the part of the respondent to ensure compliance with the Development Act.

The Court of Appeal held that the sentencing judge erred in finding that extenuating circumstances existed. The identified circumstances did not constitute extenuating circumstances as they did not relate to any action or failure on the part of the respondent to ensure compliance with the requirements of the Development Act. The Court found that the respondent undertook no steps to avoid the commission of the offence and there was no good reason to not record a conviction. Consequently, the appeal was allowed, and the conviction was recorded. The Court of Appeal varied the order of the Environment Resources and Development Court to record the respondent's conviction, confirming the order in all other respects.

Orders

Orders of the court

Background

Background to the litigation

Section 44(1) of the Development Act makes it an offence for a person to undertake development contrary to Part 4 Division 1 of the Development Act. The maximum penalty is a fine of $120,000. Particulars of the charge were that between 17 March 2008 and 13 November 2008 the respondent undertook development, namely building work, by constructing or causing the construction of a warehouse and office buildings on certain land at Pooraka. The development was not an approved development. It was therefore undertaken contrary to s 32 of the Development Act, which section is in Part 4 Division 1 of the Act.The facts The respondent was one of three defendants charged with breaches of s 44(1) of the Development Act in respect of the same development. The first defendant, Giuseppe Rocca, was the developer’s agent and was described in the contract mentioned below as the superintendent of works. He entered into a contract with the respondent (the second defendant) which required the respondent to undertake certain contract services in respect of the construction of the warehouse. Those services included the supply, fabrication, erection, supervision and cladding of the warehouse and office building, including the provision of concrete footings and the preparation of structural drawings and engineering calculations relating to the contract services. It was a substantial structure, the warehouse occupying approximately 3000m2 and the office structure comprising two storeys with a total floor area of 390m2. The structure was to accommodate a five tonne gantry travelling crane. The contract price, including GST, was over $1,000,000. The first defendant also retained the services of an architect to design the whole of the building works and to obtain development approval for the works. Upon their completion, the respondent provided the engineering drawings to the first defendant’s architect for completion of the plans for the whole building and for submission for development approval. The footing design and associated engineering requirements, electrical, plumbing and sewerage detail and fire compliance did not form part of the respondent’s scope of work. The respondent was not instructed to obtain Building Rules consent or Development Approval. The agreement for the contract services between the first defendant and the respondent was entered into in late November 2007. On 17 March 2008 Development Plan consent was granted by the appellant for the development. The first defendant then instructed the respondent to commence the contract services. Commencement of the erection of the steel work for the walls of the buildings was undertaken on or about 25 July 2008. By 30 September 2008 the wall and roof cladding of the building had been completed. When instructed to commence the contract services, the earthworks for the footings of the building had already been undertaken. However, the respondent commenced the contract services without sighting a Building Rules consent or Development Approval or any plans stamped with such approval. The respondent did not satisfy itself that Building Rules consent or Development Approval had been obtained, nor did it seek to make itself aware of the terms of the consent or of any conditions attaching to it.

Evidence

Evidence Before The Court

Decision

Reasons for decision

There were, therefore, significant matters which the Judge failed to take into account in exercising the discretion not to record a conviction. The reasons advanced at the hearing and on the appeal were insufficient either to enable the discretion to be exercised or to justify its exercise.Conclusion For these reasons I consider that the Judge should have recorded a conviction. The appeal is allowed. The order of the Environment Resources and Development Court made on 10 March 2010 is varied to record a conviction of the respondent. In all other respects the order of the Environment Resources and Development Court is confirmed.

Ratio Decidendi

Legal Principle Established

It was not suggested in these proceedings that that was other than the correct approach. If the conditions precedent of paragraphs (a) and (b) are fulfilled, there remains a discretion in the court as to whether a conviction should be recorded.The Judge’s consideration of the conditions precedent When considering the conditions precedent to the application of s 16 in this case the Judge of the Environment Court said:I am satisfied that the defendant is unlikely to commit an offence of this nature again, having noted that is has upgraded its systems with a view to ensuring that no development is commenced prior to the issue of a development approval. The company has no convictions for offences of this nature. I am also satisfied that there is good reason for not recording a conviction. While nothing can excuse the Ahrens Group for commencing development work in the absence of the development approval, the responsibility to obtain that approval belonged to others, in particular the first defendant in these proceedings, who has already been convicted and fined. In addition, Ahrens Group commenced the building work at the request of others involved in the project. I consider that these are extenuating circumstances which, along with my opinion that the defendant is unlikely to again undertake development without consent, provide good reason for not recording a conviction against Ahrens Group.The Judge then went on to consider the exercise of the discretion and decided not to record a conviction. It was not argued on the appeal that it was not open to the Judge to find that the defendant was unlikely to commit an offence of that nature again. In other words, it was not suggested that paragraph (a) of s 16 had not been satisfied. However, the appellant attacked the sufficiency of the Judge’s reasons for finding that there were extenuating circumstances which would satisfy paragraph (b) of the section. The appellant submitted further that, even if the condition precedent of paragraph (b) were made out, it was not open to the Judge to exercise the discretion in favour of not recording a conviction.Whether there were “extenuating circumstances” In my opinion the Judge erred in holding that there were extenuating circumstances providing good reason for not recording a conviction. The Judge identified two circumstances on which reliance was placed:(1) That the responsibility to obtain approval belonged to others, and(2)That the respondent commenced the building work at the request of others involved in the project.In my opinion these do not either individually or collectively constitute extenuating circumstances. The particulars of the offence alleged against the respondent were undertaking the “development, namely building work by constructing or causing the construction of a warehouse and office buildings on the subject land” when the development was not an approved development. The extenuating circumstances identified by the Judge did not relate to any action or failure on the part of the respondent to ensure compliance with the requirements of the Development Act. The Judge relied solely on the action or inaction of others.