Cheshire Contractors Pty Ltd v Everett
[2018] QSC 228
•8 October 2018
SUPREME COURT OF QUEENSLAND
CITATION:
Cheshire Contractors Pty Ltd v Everett [2018] QSC 228
PARTIES:
CHESHIRE CONTRACTORS PTY LTD
(ACN 124 700 385)(Plaintiff)
v
MARK LANSDOWNE EVERETT(Defendant)
FILE NO/S:
154 of 2016
DIVISION:
Trial
PROCEEDING:
Claim
ORIGINATING COURT:
Supreme Court at Cairns
DELIVERED ON:
8 October 2018
DELIVERED AT:
Cairns
HEARING DATES:
2, 3, 10, 11 August 2017; 8, 9 November 2017;
15, 16, 17 January 2018; 10, 11 April 2018.
JUDGE:
Henry J
ORDERS:
Judgment for the plaintiff in the amount of $450,493.59.1.
I will hear the parties as to costs if not agreed in the meantime at 9.15 a.m. on 24 October 2018.2.
CATCHWORDS:
CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES – DISCHARGE, BREACH AND DEFENCES TO ACTION FOR BREACH – REPUDIATION AND NON-PERFORMANCE – where there was an oral contract for works – where full payment for works was not made – where there were complaints of non-compliance of works performed – where there were complaints of other breaches of implied terms – whether the works were compliant – whether there were remedial works required – whether there was loss or damage occasioned.
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – where there was an oral contract for the commencement of works – where there were two phases to the works involved – where phase one was a work for pay engagement – where phase two had no substantive pay arrangement – where payment was to be by reference to hourly rates for phase two – where there existed a promise to delay the seeking of payment – whether that promise amounted to a promissory estoppel.
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – THE CONTRACT – CONSTRUCTION OF PARTICULAR CONTRACTS – where there were two phases to the works involved – where there existed an oral contract for phase one works – whether a further oral contract, joint venture or new contract existed for further works – where there were works completed after payment in full was not received for phase one and other works completed– whether there existed any agreement for payment for the further works.
Amos v Citibank Ltd [1996] QCA 129, cited.
Bellgrove v Eldridge (1954) 90 CLR 613, cited.Combe v Combe (1951) 2 KB 215, 219, followed.
Foakes v Beer, (1884) 9 AC 605, followed.
Giumelli v Giumelli (1999) 196 CLR 101, cited.
Hughes v Metropolitan Railway Co (1877) 2 AC 439, cited.
John Alexander’s Clubs v White City, (2010) 241 CLR 1, followed.
Legione v Hateley (1983) 152 CLR 406, followed.
Masters v Cameron (1954) 91 CLR 353, cited.
Riches v Hogben [1985] 2 Qd R 292, cited.COUNSEL:
WGC Lawyers for the plaintiff
Ascione & Associates for the defendant
SOLICITORS:
C E Taylor for the plaintiff
C J Ryall for the defendant
Introduction
The plaintiff, a civil contractor, performed development work on a proposed rural subdivision of the defendant’s property west of Ingham. It claims $966,890.74 as damages for breach of contract or as a debt pursuant to a contract.
The work was performed in two phases, the first in 2011 (“phase one”), the second in 2014 (“phase two”). There was no apparent dispute by the end of phase one that the defendant, Mr Everett, was obliged to pay the plaintiff, Cheshire Contractors Pty Ltd (“Cheshire Contractors”) for the work it had performed. The problem at that stage was that Mr Everett could not afford to pay. To cope with this dilemma, he successfully prevailed upon Cheshire Contractors to confirm in an email of 20 December 2011 that it would not seek payment for work performed until there were sufficient sales or presales to allow Mr Everett to make payment. Mr Everett is hiding behind this email and recently conceived technical complaints as an unrealistic basis to avoid his obligation to pay for the phase one works.
He is not the only party who will not concede the obvious. After two further years went by without payment to it, Cheshire Contractors took the fateful decision to become proactively involved in assisting Mr Everett to advance the project. Amidst talk of a joint venture Cheshire Contractors rolled the dice and ploughed on into the phase two works, without agreement about payment for the works having been reached. Cheshire Contractors eventually ceased its phase two works, optimistically asserting that it ought be paid for its speculative folly.
So it is, with each party bogged in unrealistic positions, it is necessary to wade the evidentiary mire of several years of ill-fated property development to expose the reality of their commercial obligations to each other.
Determining the case
Cheshire Contractors says its case is straightforward – its invoiced work should be paid. What began as a listed hearing of four days but became an eleven day trial, involving broken sets of hearing days spanning many months, as well as the determination of a separate question,[1] was far from straightforward.
[1][2017] QSC 287.
Cheshire Contractors asserts in respect of both phases of work it had an agreement with Mr Everett to perform the works for payment at agreed rates, that it performed the works and that it is entitled to be paid what it invoiced at the agreed rates for the performance of the works. The consequent loss and damage is claimed as damages for the breach of contract inherent in Mr Everett’s non-payment or alternatively as money due and payable as a debt payable under each contract. The quantum of its claim is founded upon the invoiced sums.
No reliance was placed at trial on a quantum meruit or unjust enrichment claim.[2] There was at one point a mid-trial application to amend the pleadings in a way which may have varied that position but following a ruling on a separate question,[3] that application was dismissed.[4] As a result of the ruling the parties agreed the plaintiff’s claim would be reduced by $96,000.[5]
[2]See, eg, T2-88-89, T2-95-96.
[3][2017] QSC 287.
[4]T6-5 L41.
[5]T6-5 L9.
Cheshire Contractors’ relatively simple pleading of its case attracted a lengthy defence, the content of which raised a plethora of issues of varying significance. A lengthy reply followed.
In respect of phase one, Mr Everett does not deny there was an agreement. Rather he alleges that, in breach of the implied terms of the agreement, the works were not performed consistently with the project’s progressive compliance testing and inspection requirements, the amounts charged for the phase one works were not invoiced for several years and exceeded the agreed amounts and some of the invoiced work was not required by the agreement or any variation thereto (“performance compliance complaints”). He sets off the damages allegedly arising therefrom.[6]
[6]The determination of the separate question dispensed with a counterclaim.
Quite apart from the performance compliance complaints, Mr Everett raises an over-arching complaint of significance. He asserts Cheshire Contractors is precluded from claiming for the phase one works by reason of its allegedly binding promise, contained in its email of 20 December 2011, that it would not seek payment for work performed until there were sufficient sales or presales to allow Mr Everett to make payment.
In respect of phase two, Mr Everett denies there was any agreement akin to that for phase one. Instead he asserts phase two proceeded pursuant to a joint venture agreement, consistently with the promise not to seek payment presales. He contends by that agreement sales profits were to be shared, any outstanding amount owing to Cheshire Contractors became a liability of the joint venture and the works performed by Cheshire Contractors were part of its contribution to the joint venture. He complains Cheshire Contractors breached the joint venture agreement in declining to continue work in late 2014.
Alternatively, Mr Everett asserts that if there was an agreement pursuant to which Cheshire Contractors was to be paid for works performed in phase two, those payments were to be confined to a budgeted total exceeded by the claim. Mr Everett also alleges if there was such an agreement it was breached in ways similar to those alleged in respect of the performance compliance complaints regarding phase one. An additional breach is said to arise by reason of Cheshire Contractors allegedly agreeing but failing to affect the subdivision of lot 77 of Mr Everett’s land, thus preventing its sale and consequent satisfaction of Mr Everett’s debt to the bank with consequent loss to Mr Everett and deprivation of his capacity to advance the development or sell it. He claims a set off of his losses caused by Cheshire Contractors’ alleged breaches.
The task of ascertaining what are alleged to have been essentially oral agreements is plagued by a lack of evidentiary precision about them. Neither of the main protagonists, Mr Everett and Mr Barry Cheshire, the managing director of Cheshire Contractors, impressed as having a reliable recollection of matters of detail. Mr Everett was unwilling to make reasonable concessions and appeared too ready to shift responsibility rather than concede his own involvement in and knowledge of relevant events. His answers implausibly cast him as a powerless, ignorant bystander in his own property development. Mr Cheshire tended to testify in broad and sometimes unresponsive terms and was at his vaguest about the supposed agreement under which he performed the phase two works. If there exists a sensible explanation for why Cheshire Contractors embarked upon the phase two works in 2014, other than that it gambled on the parties reaching an agreement and the project succeeding, the Court did not hear it from Mr Cheshire.
Determination of the performance compliance complaints may be assisted by the content of the admittedly limited documentary communication and the industry and project document requirements for work of the kind undertaken. This may include documents like plans and approvals dealing with development compliance requirements, such as progressive inspections of works at so-called hold points, some of which the defendant complains were not complied with. That said, the significance of such compliance documents or industry requirements is dependent upon whether such agreement as was reached expressly or implicitly required Cheshire Contractors to perform a role in respect of compliance requirements.
The case requires the analysis of relevant events during and between each of the two phases of works, with a view to identifying any agreements and the extent to which they were complied with. The analysis ought also deal with events between the phases, particularly in connection with the 20 December 2011 email. The length of the pleadings in this case makes it unhelpful to structure these reasons around them. It is simpler to integrate the resolution of the issues to which the pleadings give rise within the above analysis.
These reasons will therefore progress in four parts:
Part A - General factual background
Part B -Phase one analysis
Part C-The December 2011 promise
Part D - Phase two analysis
Part E - Determination of award and or set off.
PART A - GENERAL FACTUAL BACKGROUND
Ph 1 works
The phase one works focussed upon the western end of Mr Everett’s property, which was owned by him in his representative capacity as trustee of the Everett Family Trust.[7]
[7]SOC [1], Def [1].
The residential development planned for the property was then known as Hinchinbrook Habitats. The development was planned to extend over a number of areas on the property, not just the area the subject of the phase one works.[8] Various areas of the property were excluded from the development as sensitive environmental habitats, pursuant to a development approval for material change of use of 14 May 2010.[9]
[8]See, eg, Ex 45.
[9]Ex 47.
The works consisted principally of the installation of a road along an existing road easement through the property.[10] The primary purpose of the phase one works was to provide better access to the property and the lots for potential purchase, so as to excite expressions of interest by prospective purchasers. In addition, as Barry Cheshire conceded, the works “were also part of the proposed completed development”.
[10]T2-92 L15.
The road was built to subgrade level. This, Barry Cheshire explained, is the layer directly beneath the pavement layer. The latter layer typically involves a further two or three layers of gravel followed by bitumen or asphalt.[11]
[11]T2-50 L33.
Barry Cheshire testified that other work performed at Mark Everett’s request during phase one included the clearing of mangroves,[12] the removal of an old bridge which was part of a causeway,[13] putting a drain along some lots on the high side of the road,[14] building a boat ramp,[15] applying extra fill so the batters were less steep and could be mowed,[16] the clearing of 15 lots,[17] rock work near the dam,[18] excavation up the hill,[19] the installation of ag pipe to drain some blocks[20] and putting some gravel running surface on the road for use during construction when the surface was slippery.[21]
[12]T2-56 L14, T3-14 L41.
[13]T2-59 L8, T3-15 L33.
[14]T3-15 L44.
[15]T2-54 L25 – T2-55 L1.
[16]T2-55 L23.
[17]T2-55 L42.
[18]T2-56 L28.
[19]T2-58 L16.
[20]T2-58 L33.
[21]T2-59 L29, T4-8 L28.
Some excavation material, which was excess to the needs of a project being conducted on the Mt Cudmore Road near the Cardwell Range, was supplied by an entity known as Abigroup for Cheshire Contractors’ use on embankments and bridging out an area of mangrove in the phase one works.[22] Barry Cheshire testified the work involved in respect of the material brought on site from Abigroup was “considerable”.[23] Mr Cheshire explained a large compactor was used to break down the fill material, which was quite coarse, for use in lessening the batter slopes. This involved stripping back topsoil, placing and compacting the material, levelling it out and then putting the topsoil back over the top again.[24]
[22]T1-75 LL15-47.
[23]T3-14 L38.
[24]T4-6 LL35-45.
The nature of the works additional to building the road to subgrade was canvassed more extensively in exhibit material such as timesheets. It was work for which Cheshire Contractors invoiced Mr Everett. There was a belatedly conceived and faintly argued debate, with which I now dispense, about some work not being performed or required. I accept the work which was invoiced for was in fact performed and required.[25] Mr Everett was unconvincing in his denials of the occurrence of some work, which of its nature he would be unlikely to realise had happened unless witnessing it directly.[26] I accept the performance of works additional to those initially agreed to was requested by Mr Everett. I reject as implausible the notion inherent in Mr Everett’s unconvincing testimony about this debate[27] that additional works were performed without request by Mr Everett.
[25]Subject to the invoicing errors discussed below.
[26]Eg T8-46 L46, T8-47 L25.
[27]Eg T7-18 L27, 7-20 L1
Ph 2 works
The phase two works focussed upon the eastern end of Mr Everett’s property. By this time the planned residential development was known as Riverviews Estate. Once again, the works did not constitute the whole of the project and were targeted upon getting the first 31 lots in an adequate state to go to market with disclosure notices to attempt to secure presale contracts.[28] The 31 lots included the original 15 lots reconfigured into 10 lots.[29]
[28]T8-75 L15.
[29]T8-78 L37.
Barry Cheshire described the phase two works as including building a road to subgrade level, which included creating a road away from the existing track into alignment with Mt Separation Road. Barry Cheshire explained the works also involved levelling and draining lots and removing and restoring topsoil so that the lots were at what he described as the disclosure stage, meaning they were ready for sale without much further work.[30] Barry Cheshire testified the works also involved application of hydro mulch, the provision of environmental controls, the creation of rock check dams and the installation of culverts.[31]
[30]T2-78 L33 – T2-79 L22.
[31]T2-81 L40.
The phase two works performed by Cheshire Contractors extended beyond mere construction work. Cheshire Contractors was involved in managing and marketing the project – a marked difference from its “construction only” role in phase one.
Roles
Barry Cheshire only attended construction “possibly weekly”.[32] He explained he discussed matters daily with Mr Everett and visited him weekly.[33] Mr Everett testified that while the phase one work was being performed he was on site for a “little bit of time most days”[34] and he worked on site “every day” during the phase two works.[35]
[32]T2-38 L35.
[33]T4-14 L43.
[34]T5-5 L41.
[35]T7-44 L22.
The foreman throughout the entirety of the phase one and phase two works was Barry Cheshire’s son Shannon Cheshire.[36] Another of his sons, Clinton Cheshire, worked in office administration dealing with wages, age receivables, age payables and the bookwork in general.[37] Cheshire Contractors’ administrator was Daniel Spencer[38] and its safety officer was Nicki Spencer.[39]
[36]T1-45 LL5-10.
[37]T1-77 L2.
[38]T2-38 L16.
[39]T2-38 L17.
Shannon Cheshire’s recollection was that Mark Everett assisted during the works by driving a dump truck, driving his own excavator (Shannon Cheshire recalled Mr Everett acquired a new excavator for the phase two works), putting in drains, moving logs, digging holes to let spring water out and laying stormwater pipe.[40] Shannon Cheshire testified Mark Everett was not charged for performing such works by Cheshire Contractors.[41]
[40]T1-74 L43 – T1-75 L12.
[41]T1-68 L11.
Mr Everett testified he did perform some work in phase one with an excavator, albeit one owned by Cheshire Contractors.[42] Mr Everett testified that during phase two he worked on site every day doing the works, with an excavator he had bought by then, and also watered the roads on the weekend.[43]
[42]T7-17 L47.
[43]T7-44 L23.
David Johnstone of LCJ engineers, the project designers, testified LCJ’s main dealings with the clients for phase one were with Mark Everett and his nephew Glen Everett. Indeed, LCJ’s drawings name Glen Everett as the client.[44] Mr Johnstone testified that Glen Everett appeared to be more involved in phase one and Mark more involved in phase two.[45] Glen Everett was not called as a witness.
[44]Ex 1 Vol 1 Tab 10.
[45]T2-6 LL9-15.
Of the work performed by LCJ in phase one, Mr Johnstone’s recollection was that LCJ designed documentation such that plans were produced to construct works and that LCJ’s Owen Carter did work to obtain approvals from Government agencies.[46] Mr Johnstone, the only witness from LCJ, could give little direct evidence relevant to LCJ’s role in phase one.
[46]T2-6 L33 – T2-7 L1.
Timesheets
Shannon Cheshire testified timesheets were filled out daily by all staff working on the project and verified and signed off by him as foreman the following morning.[47] Every employee had a triplicate copy timesheet book.[48] It recorded name, date, hours, work/machine type description and work’s description.[49]
[47]T1-55 LL37-43.
[48]T1-55 L30.
[49]T1-55 L33.
The exhibited timesheets for phase one[50] recorded work occurring from 7 July 2011 to and including 7 December 2011.
[50]Ex 1 Vol 3.
The exhibited time sheets for the phase two works recorded work occurring from 16 July 2014, with physical work on site from early August, to and including 17 November 2014.[51]
[51]Ex 1 Vol 4.
Shannon Cheshire explained the accuracy of the timesheets he checked was important to not charging the client for more work than was performed and also to the efficacy of Cheshire Contractors.[52] On his account, copies of them were posted back to Cheshire Contractors’ office weekly.[53]
[52]T1-56 L16.
[53]T1-55 L46.
Shannon Cheshire testified that client copies of the timesheets were not collected by the client during the project nor did the client sign the timesheets.[54] Barry Cheshire explained in evidence that he had told Mark Everett the timesheets were available all the time on site, but Mr Everett said he did not want them.[55] Mr Everett claimed to the contrary in his testimony,[56] but I accept Mr Cheshire’s evidence.
Invoices
[54]T1-56 L30.
[55]T2-53 L6.
[56]T8-46 L11.
The issuing of the invoices
Clinton Cheshire generated invoices to the client from the timesheets, creditors’ invoices, dockets and purchase orders.[57]
[57]T1-77 L42.
Clinton Cheshire testified he would forward the client the invoice, the job sheet listing the various work charged by reference to numbered timesheets and the timesheets with the relevant entries highlighted.[58] He testified that during phase one he was emailing each invoice and its associated documents to Mr Everett about a fortnight after the work dates referred to in the invoice. Evidence given by Clinton Cheshire in re-examination seemed to implicitly accept the invoices were sent via the post in contrast to via email.[59] Despite this variation in testimony and despite the absence of exhibited copies of any covering letters or email communications annexing the invoices, Clinton Cheshire’s assertion that the invoices were sent was credible.
[58]T1-79 LL10-38.
[59]T1-82 L20.
Clinton Cheshire explained he sent invoices to Mr Everett less regularly in phase two, doing so only when Barry Cheshire told him to.[60] That is unsurprising and fits the different character of the commercial arrangement in play. As will be seen, phase one was a conventional, work for pay engagement. Phase two was more speculative as to payment.
[60]T1-80 LL1-13.
A suggestion put to Mr Cheshire, that all Cheshire Contractors had done was to bundle timesheets and hand them over to Mr Everett, was rejected as untrue.[61] Mr Everett testified he did not receive any claim for payment from Cheshire Contractors during phase one.[62] It is not entirely clear whether this was meant to amount to testimony that no invoices were received. Assuming it was, I in any event accept Clinton Cheshire’s evidence that the invoices were sent to Mr Everett regularly during phase one and infer they were in turn received by Mr Everett.
[61]T3-19 L26.
[62]T7-23 L37.
Over two years subsequent to the conclusion of phase one, on 16 May 2013, Barry Cheshire emailed Mark Everett setting out the costs of completing further works. His email noted the “costs of work to date” was $643,870.50.[63] Counsel for Mr Everett at one point seized upon this email in support of the notion that Cheshire Contractors had not delivered any invoices to Mr Everett for phase one, a suggestion rejected by Barry Cheshire.[64] While Mr Cheshire could not recall why he had sent the email of 16 May 2013,[65] Mr Everett’s memory was that the email was sent in response to a request from him to know how much it would cost to complete the development.[66] The content of the email, which is quite detailed about the future costs, is entirely consistent with such a request. The email provides no implicit support for what turned out to be an unconvincing attempt to contend invoices were not sent during phase one.
[63]Ex 27 (also Ex 62).
[64]T3-19 L22.
[65]T4-7 L47.
[66]T7-63 L4.
The coup de gras to Mr Everett’s claims about not having received invoices were his own words in correspondence by him with a solicitor acting in the settlement for sale of a lot from Mr Everett’s property – lot one – to Mr Cheshire and others in 2014. In that email of 22 July 2014 Mr Everett wrote:
“[J]ust a quick note to let you know that the balance of settlement will be made up by work completed by Cheshire Contractors to the value of $200,000 plus GST. I have been invoiced for this work and I am happy for this to happen.”[67] (emphasis added)
The above emphasised words were a reference to the phase one invoices. Mr Everett’s remarkable explanation for those words was to maintain that in fact he had not received invoices by that time and had merely written what Barry Cheshire had told him to write.[68] I reject that evidence.
[67]Ex 103.
[68]T9-33 L14.
Phase One Invoices
The main particulars of the 12 invoices tendered in evidence in respect of phase one[69] are as follows:
[69]Ex 1 Vol 2 pp 236-312.
Date
Invoice No
Description
Amount
30/07/2011
00300021
Multiple quantities of concrete (listed).
$96,865.88[70]
31/07/2011
00300035
Machine & labour hire, as per attached worksheets which list various work performed by named personnel by reference to numbered timesheets from 04/07/2011 through to & including 28/07/2011.
$ 19,219.75
15/08/2011
00300034
Pegs for & rolls of silt fence and dust.
$ 1,345.97
[70]This is the total of the invoice’s nominated total sales amount of $88,059.89 plus its nominated GST amount of $8,805.99, which should more accurately have been $8,805.99. The correct total is therefore $96,865.88. The invoice’s “balance due” is “$0.00” – an unexplained anomaly.
15/08/2011
00300039
Machine & labour hire, as per attached worksheets which list various work performed by named personnel by reference to numbered timesheets from 02/08/2011 through to & including 31/08/2011.
$ 28,804.88
15/09/2011
00300697
Work performed at Hinchinbrook Habitat listed in attached spreadsheet, which lists various work performed by named personnel by reference to numbered timesheets from 01/09/2011 through to & including 15/09/2011.
$103,626.88
01/10/2014
00300688
Work performed at Riverviews Estate
$110,500.50
30/09/2011
00300698
Work performed at Hinchinbrook Habitat listed in attached spreadsheet, which lists various work performed by named personnel by reference to numbered timesheets from 24/09/2011 through to & including 30/09/2011.
$106,647.75
30/09/2011
00300699
Work performed at Hinchinbrook Habitat listed in attached spreadsheet, which lists various work performed by named personnel by reference to numbered timesheets from 01/10/2011 through to & including 31/10/2011.
$100,502.88
30/09/2011
00300700
Work performed at Hinchinbrook Habitat listed in attached spreadsheet, which lists various work performed by named personnel by reference to numbered timesheets from 01/11/2011 through to & including 07/12/2011.
$ 20,900.00
01/10/2011
00300045
Various quantities of substances like crusher dust, mortar & concrete listed along with water truck hire & transportation costs, charges for multiple field density determinations (5, 6 and 68 determinations), moisture density relationship tests (5, 6 and 67 tests), soil tests (7 tests) as well as soil testers.
$ 64,680.15
31/10/2011
00300083
Charges for construction equipment such as excavator hire.
$ 10,511.53
01/01/2012
00300130
Guide posts, concrete pipes, headwalls & soil tests.
$ 3,364.42
Total charge:
$666,970.59
Curiously invoice 00300688 is typewritten dated 1/10/2014 but there is also a handwritten date of 31.8.11 on it. The timesheets annexed to it span from 16/08/2011 to 31/08/2011. While not the particular focus of argument this date anomaly was borne in mind by me in nonetheless accepting the evidence that the above invoices were rendered in the era of the phase one works.
It is evident that the early and latter above invoices related to the costs of various equipment and supplies. The invoices for the physical works performed on site range from invoice 00300697 of 15 September 2011, with its attached spreadsheet listing active site work from 1 September 2011, through to and including invoice 00300700 of 30 September 2011, which lists active work on site through to 7 November 2011. By then clean-up tasks were being performed, although a number of other miscellaneous aftermath tasks evidently continued through the balance of November into early December.
Phase Two Invoices
The main particulars of the seven invoices tendered in evidence in respect of phase two[71] are as follows:
[71]Ex 1 Vol 2 pp 318-408.
Date
Invoice No
Description
Amount
27/08/2014
00300644
Progress claim 1 – Riverviews Estate subdivision
$139,596.75
11/11/2014
00300027
LCJ Engineers - for professional services rendered on consultation, detailed design & documentation & submission to Council for operational works approval for Riverviews Estate – Stage 1.
$ 77,147.40
26/11/2014
00300701
Work performed at Riverviews Estate, listed in attached spreadsheet.
$396,236.45
26/11/2014
00300702
Work performed at Riverviews Estate, listed in attached spreadsheet.
$ 53,532.97
26/11/2014
00300703
Work performed at Riverviews Estate, listed in attached spreadsheet.
$118,775.25
16/01/2015
00300028
Professional fees for survey services Progress Claim 4.
$ 30,022.08
03/03/2015
00300740
Surveying fees from G Pozzi.
$ 62,598.40
Total charge:
$877,909.30
Of the above invoices for phase two the first, a reference to progress claim 1, does not of itself indicate what the work claimed for involved. Invoice 00300701 dated 26 November 2014, while referring to “work performed”, annexed a variety of supporting documents relating to the physical cost for equipment and services paid by Cheshire Contractors to others. Invoice 00300702 of 26 November 2014 similarly involved a description of “work performed” which was supported by documents in respect of various costs of goods and services paid by Cheshire Contractors.
Invoice 00300703 of 26 November 2014, which again referred to “work performed at Riverviews Estate” attached a schedule containing multiple entries for “project managing, marketing/advertising and accounting” spanning from 3 March 2014 through to and including 26 November 2014. It is readily apparent from this annexure that the majority of the charges do not merely relate to the administrative costs of Cheshire Contractors managing the physical works it performed on the project. As much is also implicit in the descriptions, “project managing” and “marketing/advertising”. However, any doubt on the point is removed by the fact that such descriptions of work appear throughout March, April, May and June, substantially before the commencement of any physical works on site in early August 2014.
Monies allegedly outstanding
Phase one
The total of the above listed invoices for phase one is $666,970.59.
It is common ground that if such a sum was owing it was reduced by a credit of $220,000 on 7 August 2014, that amount being applied in part reduction of an amount owed for purchase from Mr Everett of lot one of his property by Mr Cheshire and others (discussed further below). On Cheshire Contractors’ case this gives an amended balance claimed of $446,970.59.
However, in the course of the trial, as a result of the aforementioned ruling on a separate question, there was a further reduction of the amount allegedly owed by $96,000. This gives rise to a further amended unpaid balance claimed for phase one of $350,970.59.
Phase two
The total of the above listed invoices for phase two is $877,909.30.
Pozzi Surveying’s claim for $62,598.40 for their services, constituted by their progress claims 1 to 4, was invoiced in invoice 300740. However, progress claims 1 and 3, totalling $26,570, were also claimed in invoice 300702 and progress claim 4, totalling $30,022.08, was also claimed in invoice 300028. This erroneous double invoicing of three of the Pozzi progress claims necessitates a reduction of the invoiced total by $56,592.08 to an amended balance claimed of $821,317.22.
It is common ground Mr Everett made two payments to Cheshire Contractors, namely, $139,596.76 on 18 September 2014 and $62,598.40 on 4 March 2015. Those payments so coincide with the amounts and general timing of invoices 300644 of 28 August 2014 and 300740 of 3 March 2015 as to compel the conclusion they were made in payment of those invoices. Those payments, totalling $202,195.16 should also be deducted from the above balance claimed. So too should an amount of $3,201.81 incorrectly invoiced for design fees.
Making those reductions gives a further amended unpaid balance claimed for phase two of $615,920.25.
PART B - PHASE ONE ANALYSIS
Ph 1: An agreement is reached
Barry Cheshire’s involvement in phase one commenced via a mutual acquaintance, resulting in Mr Everett asking him to attend a meeting at Mr Everett’s house, located on a hill of the property. He attended the meeting. Mr Everett, his nephew Glen and his son Stephen were present, along with Owen Carter of LCJ, perhaps another representative of LCJ, a number of persons from the local Council and Mr Everett’s then project manager Mr Roselle, from an entity known as Empero.
Mr Cheshire testified the purpose in him attending was to give an opinion to Mr Everett. The opinion given was that the costs to Mr Everett proposed by Empero were too high.[72] On Barry Cheshire’s account, Mr Roselle was speaking of the project being a full-blown subdivision with reticulated power and sewage and $1 million worth of landscaping.
[72]T2-39 LL1-27, T7-8 L34.
Barry Cheshire testified Mark Everett asked him to look at Mr Everett’s Bill of Quantities. Mr Cheshire subsequently did so and on his account forwarded Mr Everett Cheshire Contractors’ hourly rate price list.[73] Mr Everett testified he did not receive such a document.[74] It is obvious that he did - a copy of an email dated 12 July 2010 to Mr Everett attaching Cheshire Contractors hourly hire rates was exhibited at trial.[75]
[73]T2-40 L8, Ex 2 Tab 12 p 1.
[74]T7-16 L38.
[75]Ex 78.
Mr Cheshire testified that “they” – apparently a reference to LCJ – forwarded a Bill of Quantities to Cheshire Contractors for pricing in August 2010.[76]
[76]T2-40 LL25-38.
On 16 August 2010 Daniel Spencer from Cheshire Contractors emailed Mark Everett enclosing Cheshire Contractors’ priced submissions schedule for the project.[77] The covering email said:
“Please find attached our price to complete works for Mount Cudmore Road access and stage 1 for the abovementioned project. Please note this price includes project management and landscaping.”[78]
[77]Ex 14.
[78]Ex 14.
Notwithstanding the covering email’s reference to the price including “project management”, the attachment, styled “Submissions Schedule Hinchinbrook Habitats Mt Cudmore Access and Stage 1”, listed a variety of physical works of the kind to be expected for a construction contractor but listed no specific project management tasks. Barry Cheshire accepted that the total price of $1,239,156.05 quoted in the attachment, was the price he had priced for the project (as distinct from the smaller component of it which would become phase one).[79]
[79]T2-57 L38.
Mark Everett testified he was “pretty keen” on Cheshire Contractors’ pricing submission of 16 August and told Mr Cheshire, “looks like you’re doing it”.[80]
[80]T7-9 L12.
Barry Cheshire testified that in early 2011 he attended a meeting at Mark Everett’s house with Mark Everett and Tony Duggan of NAB. Mr Everett’s recollection was that the meeting occurred earlier, in August 2010.[81] Mr Everett also testified Mr Duggan said the lending value ratio of the land looked good and the bank would fund the cost of building the access road and stage 1 of the development.[82] Mr Everett was aware of a valuation dated 1 April 2011 which valued the “as is” land value of the property at $4,500,000.[83] On Barry Cheshire’s recollection, Mr Duggan said the lending value ratio of the property looked good and both Mr Duggan and Mr Everett told Barry Cheshire that funding would be available for the works.[84]
[81]T7-10 L7.
[82]T7-10 LL20-33.
[83]Ex 48 p 33.
[84]T2-43 LL15-33.
On Mr Everett’s account, when Mr Duggan left the meeting, Mr Everett informed Mr Cheshire he could not afford to pay for works without the NAB providing funding.[85] He testified that when Mr Cheshire subsequently told him they would soon be delivering machinery to the property to start the works Mr Everett said he could not pay without the bank funding whatever was done, to which Mr Cheshire allegedly responded, “That’s okay. I’ll get started, and we’ll sort it out later”.[86] I reject the notion Mr Everett told or implied to Mr Cheshire that there was doubt hanging over his capacity to fund the phase one works. Such evidence may have been more credible if it had been given regarding phase two, when there was a speculative commercial quality about Cheshire Contractors’ involvement. I accept the true position, as evidenced by Mr Cheshire, is that Mr Everett represented he would have funding available for the works. Phase one was a conventional engagement and Mr Cheshire had no reason to embark upon it had he known there was a material risk of non-payment.
[85]T7-16 L15.
[86]T7-17 L4, T8-40 L45.
On Barry Cheshire’s account, Mr Everett asked Mr Cheshire in early 2011 to perform the works on an “hourly hire and cost plus basis”.[87] Mr Cheshire testified he discussed with Mark Everett doing the phase one works on, what Mr Cheshire described as, a “contract basis”, namely a lump sum or fixed price project, or an hourly rates “plus” basis.[88] He testified it was agreed the works would be performed on an hourly rate for Cheshire Contractors’ equipment and labour, and any materials or services which Cheshire Contractors had to pay for would be “cost plus the margin”.[89]
[87]T2-42 L18.
[88]T2-40 L43.
[89]T2-53 L30.
Mr Cheshire explained it was Mr Everett who made the decision that the roadworks would only go to the top of subgrade because of the expense of going higher.[90]
[90]T2-51 L10.
On Mr Everett’s account there was no discussion at the meeting with Mr Duggan or, implausibly, on any other occasion about what rates would be charged by Cheshire Contractors.[91] He later seemed to retreat from that position, conceding that Mr Cheshire told him it would be cheaper to work on an hourly rate and cost plus.[92]
[91]T7-15 L40 – T7-16 L1.
[92]T8-43 LL29-34.
Mr Cheshire testified he agreed with Mr Everett to build the road in to get access, up to subgrade, according to LCJ’s plans, at an hourly rate and cost plus (terms explained above), and any other work that was requested by Mr Everett.[93] I accept that evidence accurately states the oral agreement reached between the parties.
[93]T2-48 L40 – T2-49 L5.
The evidence was muddy as to the point at which the agreement was reached – there were evidently multiple conversations. However, I infer it was by about 1 July 2011.[94] On that date Owen Carter of LCJ emailed Barry Cheshire and Daniel Spencer requesting insertions for a Bill of Quantities with blank rates,[95] enclosing various approvals for “implementation during construction” and inviting the arranging of a prestart meeting.[96] While the content of that email did not of itself dictate the terms of any agreement as between Cheshire Contractors and Mr Everett, it is obvious Mr Everett had given his agents, LCJ, authority to initiate activity calculated at getting the phase one works underway. It is inevitable, for Mr Everett to have taken that logistical step, that he must by then have reached agreement with Cheshire Contracting.
[94]The parties admit agreement was reached on or about that date.
[95]Ex 4.
[96]T2-45 L27.
It is convenient to now deal with a number of additional terms and complaints raised by Mr Everett in respect of phase one.
Ph 1 implied term: Works to be charged on a “cost plus” basis not exceeding the Bill of Quantities?
Mr Everett pleads:
“That the cost of the works were to be completed on a “Cost Plus” basis that would not exceed the amounts specified in the Bill of Quantities produced by LCJ Engineers …”.[97] (emphasis added)
[97]Def [3c].
I have already found the works were to be performed at an hourly rate and cost plus basis.
As to the works not exceeding the Bill of Quantities it is not entirely clear what document the pleading means. Mr Everett testified the Bill of Quantities was a document “that had to go to Council”.[98] He went on to testify a Bill of Quantities, dated 17 October 2011,[99] “was submitted to Council as part of our operational works application”.[100] However Council’s operational works permit had been granted back on 1 April 2011.[101] Mr Everett retreated from his assertion when the anomaly was pointed out to him.[102] The evidence did not explain how a Bill of Quantities which did not yet exist featured in some binding way in the agreement reached by 1 July 2011.
[98]T7-9 L16.
[99]Ex 1 Vol 1 Tab 8 p 11.
[100]T7-9 L34.
[101]Vol 1 Tab 4 p 15.
[102]T8-38 L40.
True it is Mr Cheshire conceded he may have stated the works would not cost more than the amount quoted in the Bill of Quantities, but he qualified this by explaining if the volume of work contemplated by the Bill of Quantities was exceeded, then it would cost more.[103] He also explained they were not “working on a Bill of Quantities”.[104] I accept that testimony. Indeed, as much is inherent in the fact, already found, that they were working at an hourly rate and cost plus. Further to those considerations, it is in any event determinative of this point that Mr Everett requested additional works, inevitably taking the potential cost beyond the province of the works eventually alluded to in the Bill of Quantities. The evidence does not support the inference it was agreed the cost of works would not exceed the amount calculated by LCJ in a Bill of Quantities.
[103]T2-53 L39 – T2-54 L16.
[104]T3-14 L46.
Ph 1 implied term: Exercise of reasonable skill?
Mr Everett pleads it was an implied term of the contract for phase one that Cheshire Contractors would, in the performance of services, “exercise the degree of skill, expertise, diligence and foresight which would from time to time be expected of reasonably skilled and competent contractors or suppliers engaged in similar civil works and construction projects”.[105]
[105]Def [3h].
Mr Everett pleads such a term was necessary to give business efficacy to the contract and was so obvious as to go without saying. I agree it is an obvious implied term of the agreement. An expectation of professional competence in performing the contracted service is unremarkable. However, that expectation is necessarily confined to the performance of the contracted service. That service was the performance of civil construction works, not the overall management of the development project. I do not accept the implied exercise of professional competence here extended to some form of prescience in anticipating, or obligation to make up for, shortcomings in the principal’s management or delegation of management of the development project.
Ph 1 implied term: Fitness for purpose?
The defendant pleads it was an implied term of the contract for phase one that Cheshire Contractors would provide services and materials that were reasonably fit for the purpose for which they were supplied.[106] The purpose pleaded was:
“…to supply an access road suitable for the promotion of presales of lots 1-31 on the proposed subdivision and to serve as part of the works necessary to complete the proposed subdivision works in accordance with the original decision.” (emphasis added)
[106]Def [3g].
Mr Everett pleads the implication of the fitness for purpose term was necessary to give business efficacy to the contract and so obvious as to go without saying. Cheshire Contractors denies there was such an implied term.[107]
[107]Further amended reply to defence (“Reply”) [12].
Barry Cheshire testified, in respect of the need for the works to be “fit for purpose”, the purpose that he undertook the works for was:
“To allow vehicle traffic, buyers to view the lots”.
Mr Everett acknowledged in cross-examination that the road constructed by Cheshire Contractors had been in place for in excess of five years and in use during that time, including being used by Mr Everett to go to and from his house. He acknowledged the road remains usable and that there had been no failure in it causing him to be unable to use the road.[108]
[108]T9-40 LL29-45.
The difficulty with the fitness for purpose term contended for by Mr Everett is that it goes beyond the readily inferred purpose of allowing vehicular access to view lots. It enlarges the purpose as being to serve as part of the works necessary to complete the proposed subdivision works “in accordance with the original decision”. Such a broad term does not arise by implication. Whether the works, which were but part of the proposed subdivision, were fit for such an enlarged purpose was not inevitably a matter within the control of Cheshire Contractors. Cheshire Contractors was to perform civil construction works, not manage the overall development. Whether the works they were asked to perform met the purpose of the intended overall development was the responsibility of the person or persons in control of the overall development. If, as now discussed, Cheshire Contractors did not have that control, then whether there was an implied agreement that its works were to in some specific way accord with “the original decision” would depend on whether it agreed to meet some specific requirement.
To put the point another way, it is self-evident that the phase one works were intended to be part of a broader project, but it was for the project’s principal to ensure those works fitted the purposes of the broader project. If there was anything the principal specifically wanted Cheshire Contractors to do to meet those purposes it was necessary for there to be agreement on such specifics. To talk generally of the works needing to be fit for purpose, without identifying the specifics now complained about takes the matter nowhere.
Ph 1: Who was to be in control of the overall development?
As Shannon Cheshire testified, it is usually a so-called “superintendent” who directs works in a project of this kind.[109] The defendant’s expert witness, construction engineer Patrick Brady, of UDP Consulting Engineers, a firm involved in land subdivisions in the Townsville region, explained in a project of the present kind the contractor ought not also be the superintendent. He said that is because the superintendent’s role is to oversee the performance of the work, ensuring its adequacy of completeness and compliance which may require issuing directions from time to time to the contractor.[110]
[109]T1-57 L10.
[110]T4-40 L30, T4-41 L4.
Shannon Cheshire explained he regarded Mark Everett as superintendent because the superintendent is the agent of the customer and the customer had not appointed an agent[111] and because Mr Everett was “on the job” almost daily and would go through different tasks he wanted done with Shannon Cheshire.[112]
[111]T1-67 L37.
[112]T1-57 L35 – T1-58 L8.
Barry Cheshire agreed in cross-examination that the purpose of a superintendent is to act as the principal’s agent in the administration of the contract.[113] Later, in re-examination, Mr Cheshire explained that in his experience the superintendent would deal with Council and other authorities in relation to:
“Anything to do with the subdivision, as in test inspections, environmental, anything that’s involved in that type of thing is dealt with by the superintendent.”[114]
[113]T3-3 L12.
[114]T4-3 L40.
As to who the superintendent was, Barry Cheshire claimed that person would usually be the design engineer on subdivisions. He testified the superintendent’s role was fulfilled by LCJ in both phases one and two.[115]
[115]T2-92 LL38-46.
Under cross-examination Barry Cheshire seemed evasive when asked whether there were any conversations between him and Mark Everett in which Mark Everett said he was going to appoint LCJ as the superintendent of the project. He eventually asserted Mark Everett said LCJ was to be appointed as superintendent at the first meeting which Barry Cheshire had with Mr Everett in mid-2010.[116] It is unlikely there was any such conversation at this first meeting, given it was a meeting where Mr Everett’s then project manager Mr Roselle, from Empero, was present. It was not the sort of meeting at which specifics as to who would be superintendent were likely to be discussed and, on Barry Cheshire’s own account, it was only after that meeting that he made the suggestion to Mr Everett that he could do the works less expensively.[117]
[116]T3-3 L25 – T3-4 L13.
[117]T3-4 LL14-30.
In cross-examination it was put to Barry Cheshire that during the phase one works he told Mark Everett he would supervise the works for Mr Everett and manage the works for him, in response to which Mr Cheshire answered: “I said I’d help him.”[118] It was also put that it would have been up to Barry Cheshire to liaise with anyone in relation to inspections and tests, to which Mr Cheshire responded, in apparent rejection of the propositions, “Construction only”.[119] He elaborated upon this response in re-examination, explaining there was liaison by Cheshire Contractors in the context of their construction in as much as they contacted Council in relation to inspections.[120]
[118]T3-4 L42.
[119]T3-4 L45.
[120]T4-3 L8.
It is noteworthy that in HSC’s operational works permit dated 1 April 2011 clause 8(a) of its conditions of approval provided, “Civil works must be constructed as per the submitted drawings” and thereafter listed the specifications of various submitted drawings by LCJ. This included LCJ’s drawing EVEA001 C01. As Cheshire Contractors’ expert witness engineer, Darren Weir, highlighted,[121] that drawing includes the following:
“ROADWORKS AND EARTHWORKS NOTES
1. EARTHWORKS ARE TO BE CARRIED OUT IN ACCORDANCE WITH “AS3798, GUIDELINES ON EARTHWORKS FOR COMMERCIAL AND RESIDENTIAL DEVELOPMENTS”, EXCEPT WHERE VARIED BY THESE NOTES. CERTIFICATES OF ALL DENSITY TESTS TO THE ENGINEER.” (emphasis added)
[121]Ex 39 p 22.
As Mr Weir demonstrated, AS3798 contains a designation of personnel. Its s 1.3(d) defines “superintendent”, for the purposes of the standard, as being “The principal’s authorised person, sometimes referred to as the engineer or the architect.”[122] The same section refers to the “constructor” as “sometimes referred to as the contractor or the builder”. This supports the conclusion Cheshire Contractors was not the superintendent.
[122]Ex 39 p 26.
It is also relevant to note that the defendant’s own expert engineer, Mr Brady, acknowledged in cross-examination that it is for a principal to appoint a superintendent.[123] He said he would have expected such an appointment for a project of this size.[124] He testified that often the design engineer takes the role of superintendent in a development contract.[125]
[123]T4-33 L26.
[124]T4-33 L30.
[125]T4-33 L35.
Cheshire Contractors’ Project Management Plan may be of some relevance to this issue. Mr Cheshire testified that prior to the prestart meeting Cheshire Contractors’ Project Management Plan was emailed to Council.[126] That plan refers to the project name as “Hinchinbrook Habitats Stages 1A”. Issue one of the plan was exhibited.[127] Its title page is dated 26 July 2011, the day before the prestart meeting (the date at the foot of the ensuing pages of the exhibit, prior to its attachments, is 16 August 2011, but no point was taken about that anomaly).
[126]T2-46 L31.
[127]Ex 1 Vol 2 Tab 13.
The Cheshire Contractors’ Project Management Plan was produced in-house by Nikki Spencer of Cheshire Contractors.[128] Barry Cheshire testified by way of explanation:
“The only way you can start the job is that you’ve got to have a Project Management Plan to give to Council. And Mr Everett, obviously, didn’t have a Project Management Plan.”[129]
[128]Ex 1 Vol 2 Tab 13 p 8 et seq.
[129]T2-46 L25.
Cheshire Contractors’ Project Management Plan did not define many of the terms it used, save for its annexed “Organisational Chart”, which named various of its own staff as holders of various positions internal to its performance of its role in the project. This included naming Mr Steve Camp, of Cheshire Contractors, as “Project Manager/Engineer”.[130] Contextually it is clear that designation of project manager and engineer was internal to Cheshire Contractors, referring to Mr Camp managing or engineering Cheshire Contractors’ works project, not managing or engineering the broader development project in which the works were being performed. The chart contains no reference to a superintendent. The Project Management Plan’s various earlier references to position titles that are listed in the Organisational Chart, are obviously to the holders of the positions which appear in the Organisational Chart, not to persons external to Cheshire Contractors. On the other hand, it is equally obvious the performance management plan’s references to the “principal” and the “superintendent” are to persons external to Cheshire Contractors.[131]
[130]Ex 1 Vol 2 Tab 13 p 26.
[131]See, eg, [9.4] and [13.2].
At a later stage of the Project Management Plan there appears an induction booklet which begins:
“Job Number: MEV10710 Job Name: Hinchinbrook Habitats Stage 1A Project Address: Mt Cudmore Rd Bermerside, Qld Client: Mark Everett Superintendent: Superintendent Representative: PRINCIPLE CONTRACTOR: Cheshire Contractors Pty Ltd ENGINEER: LCJ Engineers”[132] [132]Ex 1 Vol 2 Tab 13 p 31.
The plan’s induction booklet’s absence of any notation as to who the superintendent or the superintendent’s representative was, begs the question who the reference is to the superintendent in the earlier more substantive part of the plan?
Barry Cheshire testified the references in the Project Management Plan to the superintendent were, he believed, to the engineer.[133] Mr Cheshire maintained he believed LCJ acted as the superintendent in both phase one and two.[134] He explained:
“[T]hey did the design. I believe they were working with Mr Everett.”[135]
[133]T2-47 L39, Eg Ex 1 Vol 2 p 180.
[134]T3-2 L43.
[135]T2-47 L25.
Barry Cheshire claimed the Project Management Plan’s reference to “the project manager”[136] was to Mark Everett, explaining:
“Well it’s his project. We work on an hourly hire…plus costs basis…I don’t remember any of our invoices or anything that charged for a project manager; if it wasn’t charged for, it wasn’t supplied.”[137]
[136]Eg Ex 1 Vol 2 p 19.
[137]T2-47 LL7-13.
That was an obviously erroneous interpretation – as already explained, Cheshire’s Steve Camp was listed in the plan’s organisational chart as Cheshire’s project manager. Much of Barry Cheshire’s evidence of his opinion of the meaning of his company’s Project Management Plan was of dubious admissibility. His opinions were in any event valueless because they seemed to overlook the distinction between Cheshire Contractors’ internal roles and the broader respective roles in the project of Mark Everett, LCJ and Cheshire Contractors. For instance, while Cheshire Contractors may have had its own project manager – that is to say an internal manager of Cheshire Contractors’ performance of the works project it had been engaged to perform – it does not follow that person was managing the overall property development project for the principal, Mr Everett.
In any event Cheshire’s Project Management Plan does not credibly support the notion that Cheshire Contractors was to superintend or manage the development project. Nor does any other aspect of the evidence.
To the extent any appointment of a superintendent could arguably be said to be supported by implication from the evidence it would support LCJ. On the known evidence however, it seems clear there was no express appointment of a superintendent. Control of the overall development remained in the hands of the principal, Mr Everett. He evidently delegated a degree of that control to LCJ, but he did not delegate that control, or the role of superintendent, to Cheshire Contractors.
Ph 1 implied term: Compliance with specific requirements?
It is pleaded by Mr Everett to be a material term of the agreement that:
“The works were to be completed in accordance with the design completed by LCJ Engineers Pty Ltd and the specifications endorsed on the drawings recording the design (“the original design”).”[138]
[138]Def [3b].
Cheshire Contractors’ reply admits that term “to the extent that such design is as shown on the LCJ Engineers’ drawings referred to in condition 8(a) of the Development Approval”.[139] However it denies the need to comply with the specifications in the drawings. That is on the basis that the specification for the works and the scope of works to be completed relevant to LCJ’s drawings was limited to:
- construction of the road to subgrade level to the extent necessary to enable access for potential buyers to present an expression of interest in purchase,
- the stormwater and drainage works necessary to facilitate such construction of the road, and
- the earthmoving and site clearing required to facilitate construction of the access road and the stormwater and drainage works pending final construction. [140]
[139]Reply [7].
[140]Reply [7] read with [6(c)].
It is not suggested Cheshire Contractors were given any plans other than those in LCJ’s drawings in entering into the agreement to perform the works. LCJ’s drawings contained plans describing what the works Cheshire Contractors was engaged to perform were supposed to achieve, save that the plans were for a broader development, not merely the phase one works. It is reasonable to infer it was an implied term of the agreement that the phase one works to be performed by Cheshire constructions would be in accordance with the design described in the plans of those works in LCJ’s drawings, insofar as the plans related to the phase one works. However, the drawings were not an agreement. The extent to which specifications in those drawings were for Cheshire Contractors to perform obviously depends upon what was agreed. This is discussed further below.
Mr Everett also pleads it was an express or implied term of the first contract that:
“I.the plaintiff was to undertake all liaison with local, state and statutory authorities in respect of the completion of the work; and/or
II.comply with the requirements of local, state and statutory authorities in the completion of the work.”[141]
[141]Def [3i].
Cheshire Contractors’ reply denies that such a term was an express or implied term of the agreement.[142]
[142]Reply [14].
Mr Everett pleads the term was necessary to give business efficacy to the contract and so obvious as to go without saying. On the face of it, such an assertion is unsustainable. It would obviously be necessary for Mr Everett to point to some more specific aspect of what was agreed in support of such a term. It was not suggested such a term was specifically discussed and agreed between the parties.
Mr Everett’s particulars of this aspect of the pleading are:
“A.The defendant supplied drawings of the works to be completed prepared by LCJ Engineers EVEA001-C01 to C36 in a way that in the circumstances communicated to the plaintiff that the works were to be done in accordance with the drawings and specifications contained in them. LCJ drawing EVEEA001-C01 states in the general notes as note 4 “All liaison with local, state and statutory authority is the contractor’s responsibility”.
B.The plaintiff prior to commencement of works produced a Project Management Plan that included in it provision that “works shall not proceed past a “hold point” until the principal has released that hold point. Written evidence of the release of the hold point will be kept by Cheshire Contractors Pty Ltd”
C.In the premises, it must be inferred that the plaintiff and defendant intended the plaintiff was to liaise with the authorities in respect of inspections and the like necessary to produce compliant works. …”[143]
[143]Def [3i].
Again, such assertions are best considered in an issue specific way. That can be done by recourse to the content of LCJ’s drawings and the Project Management Plan alluded to in particulars A and B, as well as HSC’s operational works permit for the project.
LCJ’s Drawings
Barry Cheshire agreed that, for the phase one works, the LCJ drawings and the HSC approvals set out the technical requirements for the work he had to do.[144] Of the LCJ construction drawings he agreed that Cheshire Contractors had regard to the drawing notes, but not that part of the general notes which said:
“4. All liaison with local, state and statutory authorities is the contractor’s responsibility.”[145]
[144]T3-5 L33.
[145]Ex 1 Vol 1 construction drawing sheet CO1.
On the face of it, Cheshire Contractors was the contractor referred to in the above quoted note. But care is required in drawing inferences as to contractual terms from such notes given the obvious prospect of a disconnect between what the drafter contemplates and what is agreed between contractor and principal. For instance, the drawings’ roadworks and earthworks note 2 refers to “the superintendent”. This reveals the drafter contemplated a superintendent would be appointed but says nothing of what the principal actually did in that regard either.
There was no express agreement between Cheshire Contractors and Mark Everett that Cheshire Contractors would have a role in dealing with government authorities.[146] Nor could such a role be inferred from the general nature of the engagement – as already discussed Cheshire Contractors was not the superintendent or manager of the development project. It does not follow as a matter of inference from general note 4 that Cheshire Contractors agreed to perform the role of “all liaison with local, state and statutory authorities”. The words “all liaison” are so broad as to render such an inference unrealistic and their meaning is not confined by any accompanying definition. Moreover, such an implication is inconsistent with some content of HSC’s operational works permit and Cheshire Contractors’ Project Management Plan, which contemplate others being involved in such liaison. I reject the implication that the general role imputed by general note 4 to the contractor was a role on which the parties agreed. That is not to say that agreement to perform some specific tasks involving some liaison does not arise by implication from Cheshire Contractors’ Project Management Plan discussed below.
[146]T2-52 L36.
Operational works permit
HSC’s operational works permit, which identified the “applicant” as the Everett Family Trust Pty Ltd, contained conditions at paragraph 8.[147] These included at 8(a) that, “Civil works must be constructed as per the submitted drawings”, which drawings were listed as including LCJ’s drawings. Further, paragraph 8(g) required, “A Certificate of Completion is to be supplied by the Superintendent as works are finalised”.
[147]Ex 1 Vol 1 Tab 4 p 16.
Paragraph 8(f) of the conditions of approval provided:
“The applicant is required to submit a “Test and Inspection Plan” which includes “Hold Points” requiring Council’s approval prior to progressing works beyond the nominated points for the following stages of work:-
(i)At the completion of subgrade works prior to commencing the placement of base layers;
(ii)At the completion of pavement prior to priming;
(iii)Prior to the installation of stormwater pipes, kerb and channel and inverts;
(iv)Prior to backfilling sewerage mains and structures including inspection openings and manholes;
(v)Prior to the backfilling of water mains, valves and hydrants;
(vi)Prior to backfilling all stormwater pipes and culverts;
(vii)At practical completion to allow for the preparation of a defects list prior to the commencement of the main list liability period…”
The reference to the “applicant” therein was to the Everett Family Trust Pty Ltd. Mr Everett was the trustee[148] and his case was conducted in implicit acceptance that he was the representative of the applicant. The permit’s requirement that the applicant submit a test and inspection plan to Council was effectively a requirement for Mr Everett to fulfil.
[148]T4-56 L8.
On 1 July 2011 Owen Carter of LCJ emailed Barry Cheshire and Daniel Spencer inter alia attaching “Council, DERM and EPBC approvals…for your implementation during construction” and noting, “Council has addressed the hold point on the jobs on which they wish to inspect as well as ourselves”.[149] Barry Cheshire confirmed in his testimony that the email did annex the relevant approvals. He confirmed the prestart meeting, to which the email of 1 July 2011 referred, did occur although Mr Cheshire did not go himself.[150]
[149]Ex 4.
[150]T2-45 L27.
On 15 August 2011 Hinchinbrook Shire Council wrote a letter to Owen Carter of LCJ in terms commencing:
“Thank you for recently meeting onsite with Council’s Manager Engineering Services, Bruce Leach, and Infrastructure Engineer, Jenna Devietti, at the abovementioned location on Wednesday, 27th July 2011, to discuss operational works for the Hinchinbrook Habitats development.”[151]
[151]Ex 5 (also part of Ex 64).
The letter acknowledged receipt of the “Hinchinbrook Habitat stage 1A Project Management Plan and revision E construction plans, which were delivered onsite”. It went on to ask, “Please ensure you allow adequate time when requesting Council undertake an inspection of the hold points” and again set out paragraph 8(f) of the conditions of approval of operational works. [152]
[152]Ex 5.
Project Management Plan
As earlier mentioned, Cheshire Contractors’ Project Management Plan,[153] was provided to HSC. Cheshire Contractors well knew it was a document others would act upon as representing how Cheshire Contractors would perform the works. To the extent that plan represented what Cheshire Contractors would do in carrying out the works it is reasonable to infer it was an implied term of its agreement with Mr Everett that it would do those things.
[153]Ex 2.
The performance management plan deals with “Quality” in part 9. Part 9 provides, inter alia:
“9.2 Inspection and Test Plans
Providing high quality work that satisfies or exceeds our clients’ expectations is our main goal. Inspection and test plans (ITP’s) generally include observations, measurements and/or tests at Cheshire Contractors Pty Ltd’s facilities. The project manager will be responsible for arranging all tests and inspections on the project.
Frequencies for inspection and testing will be outlined in the inspection and test plans (ITP’s) in appendix M. …
9.4 Hold Points
Work shall not proceed past a “Hold Point” until the Principal has released that Hold Point. The Project Manager is responsible for ensuring that the Principal is given sufficient advance notice of Hold Points.
Written evidence of the release of a Hold Point will be kept by Cheshire Contractors Pty Ltd.
9.5 Contract Requirements
A list of contract specifications, legislation, approvals, licences and permits relevant to this contract have been provided in appendix N. Any obtained licences and permits will also be filed in appendix N, once obtained. …” (emphasis added)
The appendices to the Project Management Plan appear to be included with the exhibit, albeit not marked with an appendix number.
It is not in dispute that Cheshire Contractors’ project manager did not gather written evidence of the release of hold points by the principal. [154] The principal was Mr Everett. It will be recalled he was on the job daily. He was in a position to witness the progression of the works. There is no suggestion he intervened or did not approve of the progression of the works.[155] Whether there were hold points reached to require his release is returned to hereunder.
[154]T1-69 L10, T3-5 L28.
[155]T8-45 L38.
The inspection and test plan, inferentially appendix M, contains a table itemising various elements of work against which appear entries regarding witness and hold points under the heading “Engineer’s responsibilities” and the heading “Council’s responsibility”.[156] The entries in the Project Management Plan’s inspection and test plan identify the following potentially relevant elements of work and responsibilities:
[156]Ex 1 Vol 2 Tab 13 pp 180-182.
“Elements of work Engineer’s responsibility Council’s responsibility Subgrade
Compaction
CBR tests (if ordered)
Horizontal and vertical alignments
ProfileRoutinely visit site. HOLD POINT. Attend during proof rolling. Examine and assess all test results and cross section geometry. Forward to Council for approval. Visit site for random audit inspections. HOLD POINT Joint inspection during proof rolling.
…
Stormwater drainage
Location of structures
SL & IL of structures
Material quality
Manholes
Drain lines
BackfillingHOLD POINT. Visits to assess compliance and to view progress and works. WITNESS POINT. Visit site for inspection prior to backfilling, laying of pipe and bedding.”
It follows that Cheshire Contractors’ project manager was responsible for arranging the inspections contemplated by that table. Whether that occurred is in issue.
After the inspection table, the appendix contains a table of “test requirements”, therein detailing the relevant “construction activity”, “verification requirement – test description”, “test method”, “test frequency”, “specification” and “minimum no. of test number”.[157] These are the requirements to be met by the testing which was to be carried out by Cheshire Contractors’ project manager. For present purposes it is sufficient to describe the relevant testing as compaction testing. Whether compaction testing occurred as contemplated by the table is also in issue.
[157]Ex 1 Vol 2 Tab 13 pp 183-187.
No loss occasioned
Issues about compliance breaches in phase one are a relatively recent development in this case. It is noteworthy that even as recently as an emailed statement by Mark Everett directed to his son Stephen to help in the settling of the initial defence of this case,[158] Mr Everett expressed no concerns that there had been a failure to comply with specifications during phase one. He wrote:
“It should be noted that the first access road was built to Council’s specs after we had operational works approval. The second stage has not been checked by Council nor has any testing been carried out. The work was all but complete before we had operational works approval and all of the pipes and driveways have to be pulled up and redone as they are only temporary to try and get presales as per Cheshire’s instructions.” (emphasis added)
[158]Ex 67, T8-4 LL25-35.
Mr Everett conceded he did not have any discussions with Mr Cheshire in the early days of the project about testing and inspections[159] or about liaising with local authorities.[160]
[159]T8-44 L2.
[160]T8-44 L10.
The debate about inspection and testing of works in respect of phase one had a surreal character. The fact is that the development stalled and even by the time of trial, years after the completion of subgrade, there is no evidence of the development being sufficiently completed for it to meet the requirement of the development approval. As Mr Weir observed, the lapse of time is such that some further trimming and testing of the works would now be required to meet the requirements of the development approval.[161] I accept that evidence.
[161]Ex 39 p 2 [10],
It is convenient here to consider the attempt via Mr Brady to undermine the evidence of compliance with testing and inspection and its consequences. The evidentiary foundation for many of Mr Brady’s opinions was not identified. Mr Brady’s expert report[162] outlined various opinions premised upon some assumptions about contractual terms. The value of his opinion is necessarily influenced by whether there were in fact contractual terms of the kind upon which his opinions are premised. Notably his opinion imports the AS4000 general conditions of contract. It was no part of the expressed or implied terms of any agreement between Mr Everett and Cheshire Contractors that it included the general conditions of contract contained in AS4000.
[162]Ex 42.
A significant aspect of Mr Brady’s opinion is that, because of the absence of documentation of the inspection process, the works are unlikely to be accepted by HSC as complying with its approvals. Mr Brady does not purport to express any opinion as to whether any of the material supplied by Cheshire Contractors was fit for purpose. He accepted that the phase one works were fit for purpose, if their purpose had been to allow potential purchasers access to the site.[163] To the extent he expresses an opinion that the works are not fit for purpose, it is by reason of his view that the absence of documentation of the inspection process or of a statement of compliance makes it unlikely HSC will accept the works are compliant.[164]
[163]T4-31 L20.
[164]T4-30 L43 – T4-31 L7.
That opinion’s reference to the absence of a statement of compliance is a distraction – such a statement was the responsibility of a superintendent, not Cheshire Contractors, per paragraph 8(g) of the operational works permit. The foundation for the opinion arising from the absence of documentation of the inspection process is lacking in a number of ways.
Firstly, there is no evidence that the Council regards the works as uncompliant. Indeed, the phase one works did not advance the development to the point where Council has had to form a final view of the matter. Evidence from James Stewart, an executive manager from Hinchinbrook Shire Council, called as a witness by Mr Everett, fell well short of demonstrating Council regards the works as non-compliant. In an email to Mr Everett of 9 March 2016 Mr Stewart alluded to having driven on the road at the development and having concerns about its condition and compliance with construction drawings. The truth of this aspect of the email was not sought to be proved by evidence-in-chief but in any event it was neutralised in cross-examination when Mr Stewart conceded the road’s condition was of an acceptable standard given how long ago it was built and allowing for wear and tear in the meantime.[165]
[165]T4-22 L46 – T4-23 L13.
Secondly, Mr Brady’s view as to the likelihood of what Council may or may not do is premised, by reason of what he understands to be the advice of James Stewart, on Council taking the view that no compliance inspections were requested or undertaken. As is soon explained, that is not supported by Mr Stewart’s evidence. Thirdly, there appears to be no evidence of an absence of Council’s records of it conducting inspections during the phase one works.
In Mr Stewart’s email to Mr Everett of 9 March 2016[166] he indicated he could not locate evidence that conditions (c), (e), (f) or (g) of the operational works permit issued on 18 October 2014 had been addressed and complied with and could find no record of inspections requested or carried out in accordance with condition (g) of that permit. Mr Stewart confirmed the truth of those propositions in his testimony, although he acknowledged having found some further documents relevant to the project since his email.[167] None of this however related to any search for records of inspections requested or carried out in accordance with the conditions of the operational works permit issued in 2011. In short it was evidence relevant to the phase two works.
[166]Ex 41.
[167]T4-20 L35.
Its relevance even to phase two was neutralised when it emerged in cross-examination that Mr Stewart’s inability to find records of inspections having occurred did not mean the inspections had not occurred. He confirmed the accuracy of what he had previously said in an affidavit on the topic to the following effect:
“The results of that review have failed to locate records of inspections having been performed. That is not to say that they were not performed. The relevant staff members whom should have been tasked for that function are no longer employed by Council, and it is thus not possible to confirm with certainty the status of the record of inspections. … I am thus unable to state with certainty that inspections were done or not done. All I can say that on my review, I have not been able to locate records of such inspections.”[168]
It is unknown whether, like Mr Stewart’s email, that affidavit related to an attempt to locate records relevant to compliance with the conditions of the 2014 operational works permit.
[168]T4-22 LL11-24.
Further to all of this, Mr Brady accepted in cross-examination that normally when a Council inspector attends an inspection of works of the kind with which this case is concerned, the inspector does not leave the contractor with documentary evidence of that inspection.[169] He also acknowledged in cross-examination that, whilst rare, it does happen that Council inspectors contacted by a contractor with a request to attend site for an inspection may indicate they cannot soon attend but that the works can keep going rather than being held up waiting for the inspector.[170]
[169]T4-31 L30.
[170]T4-31 L45 – T4-32 L2.
My very strong impression of the evidence overall is that the quality of the product provided by Cheshire Contractors was good, that is, I am satisfied Mr Everett received the product he bargained for. If any shortcomings regarding testing and inspection were to be causative of loss it would be that because of them Council would not approve the development or further development without requiring remedial action. There is no evidence from Council to indicate their actual position. Mr Brady’s opinion that Council lacks documentation of the process is without evidentiary foundation. Thus, the premise for his opinion that Council would likely require substantial repetition of the works because of no documentation, is missing. Further, his prediction of what Council would do is itself bereft of an identified foundation, that is, the basis for him being able to forecast what Council will require is not explained.
The apparently satisfactory quality of the works makes it inherently unlikely that remedial action required by Council would in all seriousness be the removal of the works so that they may be started again from scratch. The much more probable scenario, consistent with Mr Weir’s evidence, is that regardless of how satisfactory Council understands the old testing and inspection process was or was not, Council would in any event, because of the lapse of time, request the tidying up and testing of the works as they now present.
It is fatal to Mr Everett’s recently conceived complaints that even if the alleged compliance breaches are proven they have occasioned no loss and are not of such magnitude as to avoid the contract. While this is sufficient to dispense with Mr Everett’s complaints I will nonetheless deal with their substance.
Ph 1: Did Cheshire Contractors comply with inspection notification and hold point requirements?
Inspections
Shannon Cheshire testified he would give LCJ and Council notice when Cheshire Contractors was going to dig or lay stormwater piping.[171] On his account, he would phone Council and LCJ and sometimes Council would opt not to come with its representative saying that they were too busy, however LCJ would come every time.[172]
[171]T1-59 L40 – T1-60 L5.
[172]T1-65 LL15-45.
On Shannon Cheshire’s account, Council and or LCJ would, when inspecting, just say the work was fine and to continue.[173] He testified he received no documents from Council or LCJ when they conducted their hold point inspections.[174] Mr Johnstone of LCJ testified LCJ “completed inspections” during construction in phase one.[175] He explained he had seen records of such inspections held by LCJ.[176]
[173]T1-66 L4.
[174]T1-66 LL15-20.
[175]T2-7 L5.
[176]T2-7 L29.
Mr Cheshire explained in re-examination that the surveying off of lot 77 had not been “part of the original plan”.[328] He testified:
“Well, I knew nothing about it until I received a email from Mr Everett, saying, “What do we do about this?” And I found out that the – from that that a part of his funding from the bank was to have that lot cut off. … I don’t believe it was anything to do with the subdivisional side of it until such a time as the titles were to be, basically, in the Council and the job was finished.”[329]
The reference to an email in that testimony was not specific but was likely intended to be a reference to the email of 21 September 2014. This fits a chronology outlined in a memorandum dated 17 August 2015 by Mr Hopkins of Pozzi Surveyors, setting out the chronology of their role. That memorandum describes how in August 2014 Mr Cheshire had approached Pozzi Surveyors to carry out the boundary survey for Riverviews Estate and soon afterwards had advised that the excision of lot 77 would be the priority.[330]
[328]T4-10 L23.
[329]T4-10 LL11-16.
[330]Ex 11.
Mr Everett agreed in cross-examination that the first occasion he raised the topic of lot 77 was around the same time as the settlement of lot one in August 2014.[331] Curiously, he rejected the suggestion he had requested Mr Cheshire to organise a surveyor for that purpose[332] although he acknowledged he subsequently paid via his accountant for the cost of the surveying work performed.[333]
[331]T8-83 L46.
[332]T8-84 L12.
[333]T8-84 L15.
On 26 September 2014 Barry Cheshire emailed Mark Everett a number of emails. According to Mr Everett’s testimony this occurred after he complained to Mr Cheshire about not being kept informed of what was going on with the development and Mr Cheshire said he would send everything through.[334] One of the emails sent on 26 September was a copy of an email to Cheshire Contractors from Evan Yelavich of RPS. [335] Mr Cheshire had used RPS in relation to some of the town planning aspects of phase two,[336] apparently including securing HSC’s amended decision notice of 22 July 2014 approving development permits for reconfiguring a lot and material change of use.[337] The email of 26 September 2014 related to RPS’s proposals on how to persuade Council to approve an amended development proposal.[338] Barry Cheshire agreed Cheshire Contractors paid RPS to be doing this “under instruction from Mr Everett” who could not pay for it.[339] This is further powerful evidence that Cheshire Contractors was, by this stage, an active player in advancing the development, not just a firm contracted to perform works for money.
[334]T7-45 L17.
[335]Ex 28.
[336]T3-54 L36; see also, eg, Ex 59.
[337]Ex 1 Tab 6 p 35.
[338]Ex 28.
[339]T3-23 LL7-13.
Also on 26 September 2014, at the same time as the above email was sent, Barry Cheshire emailed to Mark Everett an email internal to Cheshire Contractors of 30 January 2014, in which Daniel Spencer wrote:
“Jobs set up as follows:
·RVE10114 – River Views Estate subdivision – construction of the development
·RVE20114 – River Views Estate project management – project management, marketing, town planning, engineering, etc anything not associated with construction of the project”.[340]
[340]Ex 29.
According to Barry Cheshire, this was a “normal costing program we use for every job we do”.[341] Clinton Cheshire testified he was told to split the job administration like that.[342] Such a split suggests Cheshire Contractors had not been approaching phase two in the capacity of a mere contractor engaged to construct works.
[341]T3-24 L3, T4-9 L30.
[342]T1-83 L5.
In cross-examination, Barry Cheshire agreed that for phase two Cheshire Contractors took on the role of project manager but said that was only for construction.[343] He conceded that he had asked LCJ to organise the various consultants so that Cheshire Contractors could obtain an operational works permit.[344] He also explained Cheshire Contractors had engaged LCJ Engineers on the basis they would be the quickest and because Mr Everett had not paid them for their earlier work.[345] An undated Bill of Quantities, apparently relating to phase two by LCJ, was entitled:
“Riverviews Estate
For Cheshire Contractors Pty Ltd
Bill of Quantities”[346] (emphasis added)This is further evidence of the extent to which, in contrast to the phase one works, Cheshire Contractors was actively involved in advancing the property development project during the time of the phase two works.
[343]T3-7 L5.
[344]T3-7 L17.
[345]T2-80 L27 – T2-81 L3.
[346]Ex 1 Vol 1 Tab 9 p 12.
On 7 October 2014 Peter Ellis of LCJ Engineers emailed Barry Cheshire about planning site inspections and seeking a “construction program” so LCJ could arrange inspections at “hold/witness points”, listing those points as including “pipes prior to backfill” and “proof roll of sub base”.[347]
[347]Ex 26.1.
In cross-examination, Barry Cheshire was obviously reluctant to concede that since Cheshire Contractors was both directing and conducting the works, there was no room for a superintendent. He claimed they still needed a superintendent to deal with the principal and the Council, and that Cheshire Contractors was not qualified to be and did not have the necessary insurance to be a superintendent.[348] It is noteworthy that LCJ apparently continued to have a role as the engineers in phase two. For example, in the operational works permit issued by HSC on 18 October 2014 the applicant for the permit was described as LCJ Engineers.[349]
[348]T3-7 LL20-42.
[349]Ex 1 Vol 1 Tab 7 p 49.
On 13 October 2014 Barry Cheshire emailed Mark Everett offering his thoughts on potential sale prices for lot 77.[350] Mr Cheshire explained of this email, “It was a suggestion of mine…so I could get paid”.[351] Mr Everett’s recollection was that the email followed him seeking Mr Cheshire’s advice on how to price lot 77.[352] In any event, that email, like so much of what occurred in 2014, is inconsistent with Cheshire Contractors merely performing work for payment.
[350]Ex 31 (also Ex 63).
[351]T3-28 L17.
[352]T7-63 L31.
An operational works permit issues in the midst of works
HSC, by correspondence dated 18 October 2014 addressed to Peter Ellis of LCJ Engineers, granted an operational works permit.[353] By this time works were already underway on site, and had been since early August.
[353]Ex 1 Vol 1 Tab 7 p 49.
It remains a mystery why Cheshire Contractors took the risk of lurching so prematurely into works, not only without waiting to reach an agreement with Mr Everett but also without waiting for the operational works permit to issue.
The joint venture documents are not finalised
There had still been no completion of any joint venture negotiations by the time of issue of the operational works permit, notwithstanding that the phase two works on site were well advanced.
On 16 October 2014 Mark Everett emailed Barry Cheshire seeking a copy of the dot points he had provided in his email to Mark Everett’s solicitor Peter Elliott of 12 August 2014.[354] Mr Everett acknowledged in that email that he probably should have asked for the dot points “way before now”, consistent with the reality, which Mr Everett was curiously reluctant to concede in cross-examination, that no joint venture agreement had been finalised.[355] Mr Everett received a response and, on his account, became concerned that the proposed joint venture was weighted heavily towards Cheshire Contractors.[356] Mr Everett enlisted the assistance of his accountant in relation to the proposed joint venture.[357]
[354]Ex 20.
[355]Eg T8-23 L14.
[356]T7-47 L9, T7-47 L17, T7-48 L44, T7-49 L4.
[357]Ex 74.
On 11 November Mr Everett emailed Mr Cheshire a copy of the most recent draft joint venture agreement.[358] On 12 November 2014 Robert Carey, Mark Everett’s accountant, emailed Mr Cheshire, saying, inter alia:
“I had a meeting with Mark yesterday to discuss the Riverviews Estate joint venture arrangement. I have also had an opportunity to review the Joint Venture Deed prepared by Peter Elliott (lawyer).
There are a number of matters in the Deed that require some adjustments or amendments and Peter Elliott has forward to me a copy of the draft agreement in Word format so that I can provide my input in a “marked up” version. The following information is also required for the JV Deed: …
6. Under the heading “Development costs”, there is an item called “Interest”!! Can you please advise specifically what interest that this refers to (JV borrowings, existing borrowings of the owner, new JV borrowings!!)
7. Would you kindly forward the most recent development cost, advertising and marketing estimates schedule for the initial stage 1 of 31 lots.
8. Please forward a copy of the Developer’s Public Risk insurance policy as outlined on the proposed agreement at clause 5(ii)(b).
9. Both the Developer and owner have independently paid costs towards the JV which will need to be reconciled. …”[359]
[358]Ex 21.
[359]Ex 40.
Mr Cheshire emailed a response, at a time when he evidently did not realise a copy of the draft had been emailed to him the day before. He wrote, inter alia:
“Thanks for your email.
I find it all very interesting but I have never received a copy of the draft JV so really have no idea of what we are talking about.
Peter Elliott asked for some dot points to prepare the JV which I supplied about 3 months ago on the 12/08/14.
Mark did not want to be involved at that stage so I sent what I thought was relevant.
I did read the draft at Mark’s house some time back but don’t recall all of the details. …I realise this JV should have been in place before any work started on the development, but due to time and financial restraint issues by the NAB it was necessary for Cheshire to expend considerable money and work to get to a position to enable land sales before certain time lines were reached. …”[360] (emphasis added)[360]Ex 22.1.
The following exchange occurred in cross-examination, after it was highlighted Mr Cheshire had said in the above email that he realised the joint venture should have been in place before any work started:
“What you’re referring to there is you were saying that you should have had a written joint venture agreement in place before the work started?--- Should have had an agreement in place.
Well, just to make it clear, I’m suggesting to you that you’re not suggesting there wasn’t an agreement. There was an agreement, but what you should have had was a written agreement?--- Sorry, there was no agreement, but we should have had a written agreement.”[361]
[361]T3-37 LL1-8.
Mr Cheshire’s final answer in the above exchange was a concession of the obvious - Cheshire Contractors’ work on phase two had been undertaken without any agreement being in place.
Mr Cheshire rejected the suggestion there had been a joint venture in contemplation before he started work because Mr Everett did not otherwise have the money or financial resources to pay for the works.[362] This prompted the following exchange in cross-examination of Mr Cheshire:
“Where was he going to get the money from?--- If we got the subdivision to a stage where he could get people on blocks and get sales of the blocks he would pay us out of the sales of the blocks, and up until a week before this I think he was – still had potential buyers visiting the site for him to sell the site for them, and he also had a JV deal he was looking at with some – Devine and someone else, I think, just a – I don’t know. Might have been a month before this.”[363] (The reference in that answer to “this” was to his email of 12 November 2014, Ex 22.1.)
[362]T3-37 L21.
[363]T3-37 LL23-28.
Once again, such evidence affirms Cheshire Contractors’ involvement in phase two was speculatively premised on the development succeeding and sales paying for the work performed.
Later on 12 November there were email exchanges between Robert Carey and Barry Cheshire by which a draft Joint Venture agreement was forwarded by Mr Carey and it was agreed there was a need, as Mr Cheshire put it, to meet “to quantify and document contributions and future commitments to the JV”.[364]
[364]Ex 40 (also Ex 75), Ex 76.
On 17 November 2014, the last day of work recorded in the timesheets, Barry Cheshire emailed Robert Carey and Mark Everett a number of tracked changes to the draft joint venture agreement.[365]
[365]Ex 22.2.
Cheshire walks out
Later, on Monday 17 November 2014, after the above email, there was a meeting between Barry Cheshire and Mark Everett, and perhaps Mr Carey. On Barry Cheshire’s account, after the meeting started Mark Everett said, “You realise this joint venture’s only for 31 lots, not for the entire subdivision” to which Barry Cheshire responded, “If that’s the case, well, I’m no longer interested” and he walked out of the meeting. He testified his reaction was because a venture involving only 31 lots would only cover costs, giving no margin and meaning there was “no point in being there”.[366]
[366]T2-74 LL1-13.
On Mark Everett’s account of what occurred on the 17th, he was not satisfied with the changes Mr Cheshire had suggested to the draft joint venture agreement including, on his recollection, a replacement of a reference to mortgage with a reference to a lien.[367] Mr Everett testified:
“I was getting crooker I suppose and I said to him, “Look, this is not fair what is written here and we’ve got to try and sort something out”. And as far as the mortgage or lien is concerned I can’t do that because it’s not what is done in these sorts of arrangement where someone half finishes a road. … I was really no better off than what I was before, especially after Mr Cheshire said the work he done was only temporary. And I said, “Look, let’s just – I can’t do it. Why don’t you just buy the place?” and Mr Cheshire said, “We don’t want it”, and I said, “Well, just do stage 1 and, you know, do what you want to do”, and he says not enough money in it and I said, well, tell me what I have to reduce the price of the land stage 1 to to make it viable for you, but before you do that I’m going to ask you to redo your prices on the roadworks and the civil works. At that stage there was four prices floating around. And he said, “I’m not going to redo my prices so you can show them to everyone else and get it done cheaper”. And Mr Cheshire got pretty cranky and then I shut down.”[368]
[367]T7-49 L25.
[368]T7-49 LL29-45.
Mr Everett acknowledged in his evidence he had at this meeting proposed that the joint venture only apply to the first stage rather than to the other stages.[369]
[369]T7-50 L2.
On Wednesday, 19 November 2014 Mr Cheshire emailed Mr Carey saying, inter alia:
“Following our meeting on Monday, Mark requested another meeting with me at his house on Tuesday. This was to discuss costs involved in stage 1.
You may have gathered at our Monday meeting that I was a little surprised when told the JV was applicable to the 31 lots on stage 1 only.
As I stated at the meeting on Monday there is very little profit in stage 1 as was planned at the outset of the project design and certainly not enough to entertain a JV with the current exposure Cheshire Contractors have with this venture. …
I have attached the rough outline of points to be included in the JV which I sent to Peter Elliott that clearly shows the 81 lots being included in the JV and as I have mentioned before Mark did not want any input at this stage although we had discussed the high upfront costs of this project.
If the following stages, 2, 3 and 4 were not included:
- How would Cheshire Contractors be compensated for the complete design and approval of the remaining 50 lots?
- What would prevent Everett from developing stages 2, 3 and 4 before stage 1 was sold and being in direct competition?
- Why would the JV on stage 1 pay for the upgraded road requirements to service future stages?
- Why would the JV on stage 1 pay for the upgraded Ergon requirements to service future stages?
- Who would pay for the highway upgrade?
The Joint Venture draft points were emailed to Peter Elliott on the 12/8/14 which is one week after we started work on the construction work on the 5/8/14. The works were commenced before the revised operational works permit was issued [in] an effort to obtain presales within the timeframe as allocated by the NAB.
I therefore find it unacceptable that Mark has held back the JV agreement until the 12/11/14 and that on Monday 17/11/14 informed me that he now considers the JV is only applicable to stage 1.
I am willing to consider proposals that you may have with the JV attached to stage 1 only but this would only be considered if it included a guaranteed return appropriate to the costs and exposure including interest for the unsecured debts currently owed by Everett to Cheshire Contractors in 2011.
Failing an agreement we would have no option apart from taking the necessary steps to receive immediate payment for the current debt.”[370]
[370]Ex 40 p 99.
As with Mr Cheshire’s email of 12 November 2014 this email also alluded to the phase two works having commenced in response to some financial pressure from the NAB. Whereas the email of 12 November 2014 noted the works had commenced before a JV was in place, the email of 19 November 2014 noted the works had commenced before the revised operational works permit had been issued. These hindsight acknowledgments are consistent with Cheshire Contractors having embarked upon the phase two works prematurely.
The content of an email by Barry Cheshire to Robert Carey of 24 November 2014 was emblematic of the reality there had actually been no agreement. It noted the absence of response since 19 November 2014 regarding the proposed joint venture agreement and then said:
“As you are aware the Cheshire Group have a considerable investment in the Riverviews Estate project and because of this investment we are anxious to enter a suitable agreement between the parties involved.
As it is over 3 months since the draft points were forwarded to Everett’s lawyer, I believe there has been ample time to produce a joint Venture Agreement that suits all parties.
If I have not received a suitable proposal regarding these issues by COB at the end of this week … we shall issue all appropriate invoices and pursue payment by whatever means necessary. …”[371] (emphasis added)
[371]Ex 41 p 101.
On 1 December 2014 Barry Cheshire emailed Mark Everett and Robert Carey, referring to there having been “no attempt to sort out the JVA since I sent a draft dot point proposal to Mark’s solicitor, Peter Elliott in August”.[372] The email advised:
“As a result I hereby withdraw our offer of a joint venture agreement and enclose our accounts for works performed less credits due. … Please find attached invoices.”[373]
[372]Ex 23.
[373]Ex 23.
The email attached copies of all of the phase one invoices and four of the phase two invoices, namely invoices #688 of 1 October 2014, #701 of 26 November 2014, #702 of 26 November 2014 and #703 of 26 November 2014, all of which were for work performed by Cheshire Contractors at Riverviews Estate.[374]
[374]Ex 23.
On 3 December 2014 email exchanges between Mr Everett and his accountant’s bookkeeper, Ms Brown, show they were already embarking upon scrutinising information in support of the invoices. One such email by Mr Everett noted:
“[W]e have only seen construction invoices, I am predicting management ones to follow…….just thinking.”[375]
[375]Ex 104.
Payments contemplated but not made
On 6 January 2015 Mr Cheshire emailed Mr Carey advising, inter alia:
“I have accounts from the surveyor in relation to subdividing Mark’s house on Lot 77 into a separate title.
I have paid $38,000 and expect a further $26,500 in accounts to complete this exercise. Some of this survey overlaps onto the subdivision.
Upon payment of the amount of $64,500 incl GST I will release all documents etc related to the work performed by G Pozzi Surveyors.”[376]It was suggested to Mr Cheshire in cross-examination that his expectation of a further $26,500 in accounts to complete the exercise was because it had not been completed and the surveyor was still working, to which Mr Cheshire responded, “It was completed, but they hadn’t sent the final account in.”[377]
[376]Ex 36.
[377]T3-43 L9.
On 23 January 2015 Mark Everett emailed Barry Cheshire, referring to Barry Cheshire having terminated the “proposed joint venture” on 1 December 2014 and notifying expenditure beyond the date of termination “will be at your cost”. The email also stated Mark Everett would be paying “costs incurred with the subdivision to 1 December 2014”, once verified by an accountant and bookkeeper.[378]
[378]Ex 24.
By the time of the above email exchanges in December and January, the phase two works had ceased.[379] As mentioned above, the timesheets show the last work was on 17 November 2014.
[379]T2-75 L35.
On 24 January 2015 Robert Carey emailed Barry Cheshire seeking access to information to allow verification of costs through to 1 December 2014.[380]
[380]Ex 25.
On 4 March 2015 $62,588 was paid to Cheshire Contractors to pay for surveyors fees on Mr Everett’s behalf by his accountant Mr Carey.
On 10 March 2015 Ms Brown, bookkeeper to Mr Everett’s accountant Mr Carey, emailed Mr Carey and Mr Everett, writing:
“The current “official” outstanding amount to Cheshire is $815K, however that includes “project management” fees of $118K, which are yet to be confirmed as legitimate. It has also included the $62K surveyor invoice, which you have now settled. The other invoices charged, appear to be accurate, based on the timesheets that Cheshire’s have provided. I’m waiting on Clinton to revise the accounts and send an adjusted final total, however based on above, the amount outstanding is $635K.”[381] (emphasis added)
[381]Ex 105.
Mr Everett accepted Ms Brown’s role had included checking through the invoices and timesheets to verify what was outstanding.[382]
[382]T9-39 L19, T9-40 LL1-7.
On 26 March 2015 Barry Cheshire emailed Robert Carey requesting immediate payment of $1,181,236.17, being the amount owing (seemingly calculated at $919,389.50 as at that time plus interest).[383]
[383]Ex 25.
On 30 March 2015 Robert Carey emailed Barry Cheshire, referring to an attempt underway to have the project refinanced so as to include the outstanding development costs to date.[384]
[384]Ex 25.
On 1 April 2015 Robert Carey emailed Barry Cheshire, explaining a refinance application had been lodged and that, once approved, Cheshire Contractors’ accounts would be settled. Barry Cheshire responded giving them two weeks’ grace, but no payments were made.[385]
[385]Ex 25.
Everett not liable for phase two
In light of the evidence reviewed above I find there was no agreement reached, whether expressly or impliedly, regarding the essential contractual element of consideration in respect of Cheshire Contractors’ performance of the phase two works or work related thereto. With the acquiescent approval of Mr Everett, Cheshire Contractors appear to have embarked entirely speculatively upon performing such work in the hope that agreement regarding consideration for the work would eventuate. It never did. The fact that works were embarked upon does not mean agreement had been reached. In some cases, such a fact might support that inference, but not in this case, not where there is such an abundance of evidence to the contrary.
Further the fact that some payment was actually made by Mr Everett to Cheshire Contractors in respect of the phase two works does not alter my view there was no contract. Mr Everett would not be the first person to pay money out of a sense of moral obligation, for instance a sense of otherwise being unjustly enriched. His property did after all benefit from the works performed.
To remove doubt, I also reject the notion that there was a joint venture agreement or alternatively the agreement pleaded by Mr Everett as the “Riverviews Estate Contract. The latter pleading built upon what I find was a stand-alone agreement regarding the sale of lot one, to link it in as part of an agreement that Cheshire Contractors would perform the phase two works for payment in accordance with the budget. In fact there was no agreement reached regarding payment for performance of the works. The so-called Riverviews Estate Contract did not occur.
As to the alleged joint venture agreement, the term “joint venture” in this context is nothing more than a badge to describe an agreement by which, if the agreement was reached, the parties would each contribute to the progression of the property development and would share in the profits of the development after deduction of funds to recompense them for their contributions. The fact that the badge name was bandied about between the parties does not mean there was an agreement reached. As was confirmed by the High Court in John Alexander’s Clubs v White City,[386] the name “joint venture” ascribes no legal consequence and what must be considered is the detail of what the parties have agreed and done.
[386](2010) 241 CLR 1, 21.
It is unnecessary to consider the categories of potential agreement discussed in Masters v Cameron,[387] for this is was not a case in which the parties agreed upon contractual terms not yet dealt with by a formal contract. It is clear they were unable to reach agreement on terms in the first place (Even if that conclusion is incorrect and it can be said they reached an agreement of sorts to be formalised, such agreement would in any event be in the unbinding third category discussed in Masters v Cameron, namely one where no bargain is to be concluded without formalising a formal contract).
[387](1954) 91 CLR 353, 360.
The conclusion there was no agreement is fatal to Cheshire Contractors’ claim in respect of the outstanding payments invoiced in phase two. That is because the claim is premised on proof of a further oral contract which it failed to prove. None of this means works of some value were not provided during phase two but I am not here concerned with a quantum meruit or unjust enrichment claim.
Because of the failure of this aspect of Cheshire Contractors’ claim it is unnecessary to consider Mr Everett’s allegations of Cheshire Contractors’ compliance breaches and breach of contract for this aspect of the claim.
PART E – DETERMINATION OF AWARD AND OR SET OFF.
Everett’s offsetting claim
The pleaded offsets in respect of phase one, premised on compliance breaches, have failed in light of my findings regarding those alleged breaches.
Mr Everett’s offsetting claim is otherwise made on the basis there was a breach of the joint venture agreement.[388] There was no joint venture agreement. The foundation for the offsetting claim fails at the threshold.
[388]Defendant’s amended written submissions [175].
December 2011 promise legal binding?
It will be recalled that even if the December 2011 promise was legal binding it was not of indefinite duration and is no longer a basis for Mr Everett to avoid liability for paying for phase one. Nonetheless it remains necessary to determine whether it was legal binding at all, for that likely impacts upon when interest ought be calculated from.
A number of arguments were advanced by Mr Everett. One was that the promise was made when the contract was still in the executory phase because Cheshire Contractors had agreed to undertake additional works requested by Mr Everett. I reject that. The agreement to perform additional works requested by Mr Everett was not like an ongoing retainer. It only related to the performance of works during the phase one works. The phase one works had been completed by the time of the December 2011 promise.
Another argument advanced was premised upon the invoices not having been rendered by the time of the December 2011 promise but I have accepted Cheshire Contractors’ position on that topic. It is true that the last of the phase one invoices remained to be issued at that time but that has no material bearing on the argument advanced.
Another argument advanced was that the December 2011 promise was binding as a contract. How could that be? The rule in Foakes v Beer,[389] that the consideration for discharging an indebtedness cannot consist of a promise to pay later, remains good law in Queensland.[390] What consideration could there have been? Two fanciful purported forms of consideration were contended for.[391] One was supposedly avoiding the “disbenefit” of forcing a failure of Mr Everett’s liquidity and consequent incapacity to pay all creditors including Cheshire Contractors by Mr Everett being given time to continue the development and raise enough money to pay. This falsely frames what is no more than a promise to pay later as a benefit because it is better than the option of not now being paid much of an existing debt. It is not consideration. The other argument is that, if payment were not pressed for, Mr Everett could further pursue the development, thus giving Cheshire Contractors “the opportunity to engage in further potentially profitable work”. It is sufficient to dispense with this argument by observing that it lacks evidentiary foundation – there was no holding out of an opportunity for further work at the time the promise was solicited and made.
[389](1884) 9 AC 605
[390]Amos v Citibank Ltd [1996] QCA 129.
[391]Defendant’s amended written submissions [30].
Having dispensed with these drossy distractions I finally come to a more substantive argument – that the promise and events which followed it gave rise to a promissory estoppel in equity. The equitable doctrine of promissory estoppel was articulated in Hughes v Metropolitan Railway Co[392] by Lord Cairns LC thus:
“… if parties who have entered into definite and distinct terms involving certain legal results - certain penalties or legal forfeiture - afterwards by their own act or with their own consent enter upon a course of negotiation which has the effect of leading one of the parties to suppose that the strict rights arising under the contract will not be enforced, or will be kept in suspense, or held in abeyance, the person who otherwise might have enforced those rights will not be allowed to enforce them where it would be inequitable having regard to the dealings which have thus taken place between the parties.”
[392](1877) 2 AC 439, 448.
The doctrine, which has been accepted in Australia,[393] is a safeguard against a party insisting on the party’s strict legal rights when it would be unjust for them to be enforced in light of what has taken place in reliance upon the promise.[394] In observations approved by the High Court,[395] McPherson J in Riches v Hogben[396] explained the crux of the doctrine:
“It is not the existence of an unperformed promise that invites the intervention of equity but the conduct of the plaintiff in acting upon the expectation to which it gives rise.”
[393]Legione v Hateley (1983) 152 CLR 406
[394]Combe v Combe (1951) 2 KB 215, 219.
[395]Giumelli v Giumelli (1999) 196 CLR 101, 121.
[396][1985] 2 Qd R 292, 300-301.
Setting to one side the events of 2014, then long in the future, the change in Mr Everett’s position, said to have occurred in reliance upon the December 2011 promise, is his “entry into further obligations to the NAB”, allegedly making it impossible for him “to return to the position anterior to the promise of time to pay”.[397]
[397]Defendant’s amended written submission [44].
Consideration of what followed has a hypothetical flavour in that it is not suggested Cheshire Contractors pressed for payment during the period of the promise’s currency, that is, prior to 1 January 2014, although by late 2013 it was certainly pressing in an active way for the project to be advanced. The hypothetical enquiry is whether equity would have prevented them from doing so. If it would have then the award of interest on the amount owing probably ought not claw back to that period and ought only commence form 1 January 2014, a topic to which I will return.
It is uncontroversial that what followed the making of the promise urged by the NAB was the NAB continued Mr Everett’s existing loan facility. Mr Everett testified the bank also approved the advancing of “a few hundred thousand dollars” to help with holding costs and maintenance.
In effect, the December 2011 promise helped Mr Everett to “keep the dream alive” of holding onto his property and developing it. The following exchange in cross-examination about the email of 20 December 2011 illustrates the point:
“Once you’ve received that email from Mr Cheshire and you forwarded it onto the bank, your evidence yesterday was that you then got going to go to the market to try to get some sales?--- That’s correct.
But the – what I’m putting to you – the proposition that I’m asking you to consider is that you didn’t do anything different after getting that email than you would have done in any event. You did the same thing as you were always going to do anyway, isn’t – that’s true, isn’t it?--- I suppose you’re right, yeah.”[398] (emphasis added)
[398]T9-2 LL34-43.
That the December 2011 promise assisted Mr Everett does not however mean he did not change his position on the strength of the promise. The evidence is not entirely clear on the “but for” scenario, but it appears likely, absent the promise, that the bank would not have continued its loan facility or at least would have confined it. At one level that would have been to Mr Everett’s disadvantage but at another it would have meant he did not extend his level of indebtedness to the bank. While acting on the promise was helpful to him to keep his dream alive, it also meant he incurred a greater level of debt to the bank than he otherwise likely would have, had the promise not been made.
In weighing these considerations, it is important to bear in mind the promise had a direct causal connection with Mr Everett’s financial position vis a vis his bank. Not without some hesitation, I conclude against the above background it would have been inequitable to permit Cheshire Contractors to exercise its legal right to payment until the elapsing of a sufficient period of time within which to advance the project to the point of being able to raise money to pay for the phase one works from funds from presales or sales. I have found as a matter of fact that period had passed by 1 January 2014. Coalescing with that finding I conclude by reason of the protection equity would have given Mr Everett on account of him acting upon the December 2011 promise that Cheshire Contractors would have been estopped from seeking payment for the phase one works prior to, and only prior to, 1 January 2014.
A final argument advanced by Mr Everett is that a form of estoppel by conduct or convention arose from the combination of the December 2011 promise and the 2014 sale of lot one. The argument as elaborated upon was that the promise became irrevocable with the arrangement by which there was a credit of $220,000 given as part of the sale of lot one. There is no doubt that Mr Everett changed his position in entering into the 2014 sale and allowing the crediting of the deposit against his debt to Cheshire Contractors. But that has nothing to do with the 2011 promise. That promise, as Mr Everett would well have appreciated, was only a promise to postpone pressing for payment for a sufficient period, which period I have found had ended by 1 January 2014. I additionally note the fact that Mr Everett entered an arrangement later in 2014 by which he sold property at a fair market price and a payment would be credited to reduce his indebtedness to Cheshire Contractors is entirely consistent with him no longer acting on the strength of the December 2011 promise.
There is no evidence supporting the implication of some new or varied promise that by the arrangements for the sale of lot one and the crediting of the deposit against the existing debt, Cheshire Contractors would not pursue payment of the balance of the phase one debt. Perhaps that might have been a clause to which Mr Everett could have aspired for a joint venture agreement but, as I have already found, no such agreement was reached.
The final matter to consider is the significance of the finding that the December 2011 promise was only good as a protection against demand for payment before 1 January 2014. Does it mean that Cheshire Contractors’ entitlement to interest on its award for the outstanding phase one amount dates from the initial time of non-payment of invoices when due or does it date from 1 January 2014?
The evidence and submissions were largely silent on this issue. One can conceive of cogent arguments either way but they are not well informed by evidence. The onus in this context was on the plaintiff to have satisfied me both that interest was payable upon unpaid invoices once past their due date and that the December 2011 promise did not relieve Mr Everett of the burden of interest accruing upon the debt during the currency of the promise not to seek payment of the debt. Given the dearth of relevant evidence I am not so satisfied, with the consequence the outcome should favour the party who does not carry the onus.
The award in respect of the amount outstanding on the phase one works, of $350,970.59 should therefore attract interest from 1 January 2014 to today, an amount of $99,523. This gives rise to a judgment sum for that component of the claim – the only component to have succeeded – of $450,493.59.
Orders
It will be necessary to hear the parties as to costs unless they are agreed.
My orders are:
1. Judgment for the plaintiff in the amount of $450,493.59.
2. I will hear the parties as to costs if not agreed in the meantime at 9.15 a.m. on 24 October 2018.
0
7
0