Court of Appeal
Supreme Court
New South Wales
- Summary available
Medium Neutral Citation: Chengcheng (Aust) Enterprise Melbourne Pty Ltd v Mansfield Corporation Pty Ltd [2018] NSWCA 244 Hearing dates: 12 September 2018 Date of orders: 26 October 2018 Decision date: 26 October 2018 Before: Macfarlan JA at [1]; Ward JA at [2]; Sackville AJA at [87] Decision: 1. Leave to file an amended defence in the District Court proceedings be refused and appeal be dismissed with costs.
2. Application for leave to cross-appeal be refused with costs.Catchwords: CONTRACTS – Interpretation – Design and construction contract – Where clause provided contractor entitled to reimbursement of loss or expense at specified daily rate if progress of works was delayed or disrupted by “a Variation” – Whether primary judge should have held clause not applicable because there was no actual delay to works where an extension of time had been approved or because there was already agreement as to the cost consequences of the variation – Held there was no error in primary judge’s interpretation – Appeal dismissed
CIVIL PROCEDURE – Originating process – Application for leave to amend defence – Leave refused – No question of principle
CIVIL PROCEDURE – Court of Appeal – Application for leave to cross-appeal – Leave refused – No question of principleCases Cited: Dutton v O’Shane (2003) 132 FCR 352; [2003] FCAFC 195
Mansfield Corporation Pty Ltd v Chengcheng (Aust) Enterprise Melbourne Pty Ltd [2018] NSWDC 12
Suttor v Gundowda Pty Ltd (1950) 81 CLR 418; [1950] HCA 35Texts Cited: I N D Wallace, Hudson’s Building and Engineering Contracts (12th Ed, 2010, Thomson Reuters) Category: Principal judgment Parties: Chengcheng (Aust) Enterprise Melbourne Pty Ltd (Appellant)
Mansfield Corporation Pty Ltd (Respondent)Representation: Counsel:
Solicitors:
JJ Loofs SC with K Young (Appellant)
T Lynch SC with I Leong (Respondent)
Jurisbridge Legal (Appellant)
Frank Law (Respondent)
File Number(s): 2018/73972 Publication restriction: Nil Decision under appeal
- Court or tribunal:
- District Court of New South Wales
- Jurisdiction:
- Civil
- Citation:
- [2018] NSWDC 12
- Date of Decision:
- 7 February 2018
- Before:
- Dicker SC DCJ
- File Number(s):
- 2016/238217
Headnote
[This headnote is not to be read as part of the decision]
Mansfield Corporation Pty Ltd (the respondent) was engaged by Chengcheng (Aust) Enterprise Melbourne Pty Ltd (the appellant) under a Design and Construction Contract entered into on 20 July 2015 (the Contract) to refurbish restaurant premises in Melbourne.
The Contract required the respondent to complete the works by 27 November 2015. However, clause 6.6 of the Contract provided that the principal “may direct the Contractor in writing to carry out a Variation which is within the general scope of the Works”. Clause 9.4 of the Contract provided that, if the progress of the works was delayed by any matter, cause or thing beyond the control of the contractor, then the contractor was entitled to a reasonable extension of time for practical completion. Clause 10.4 of the Contract provided that, unless otherwise agreed by the parties, variations must be valued by…
Keep reading for free
Create a free CaseChat account to read Chengcheng (Aust) Enterprise Melbourne Pty Ltd v Mansfield C... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2018] NSWCA 244
- Decision Date
CaseChat Overview and Summary
The Court of Appeal was required to determine whether the primary judge had correctly interpreted the contract clause in question. Specifically, the court had to consider whether the clause’s entitlement to reimbursement for loss or expense due to a variation was contingent on proof of actual delay to the works, or whether the approval of an extension of time satisfied this requirement. Furthermore, the court had to assess whether a pre-existing agreement on the cost consequences of a variation precluded the application of this specific reimbursement clause.
The Court of Appeal found no error in the primary judge’s interpretation of the contract. The judges reasoned that the clause did not require proof of actual delay to the works, but rather that the delay or disruption was *caused* by a variation. The approval of an extension of time was considered evidence of such causation. The court also held that the existence of an agreement on the cost consequences of a variation did not necessarily exclude the operation of the loss or expense clause, particularly where the agreement did not encompass all the losses or expenses contemplated by that clause. Consequently, the appeal was dismissed.
In addition, the Court of Appeal refused the appellant leave to file an amended defence in the District Court proceedings and refused the respondent leave to cross-appeal, with both applications dismissed with costs.
Orders
Orders of the court
1. Leave to file an amended defence in the District Court proceedings be refused and appeal be dismissed with costs.
2. Application for leave to cross-appeal be refused with costs.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi