JURISDICTION : STATE ADMINISTRATIVE TRIBUNAL
ACT: BUILDING SERVICES (COMPLAINT RESOLUTION AND ADMINISTRATION) ACT 2011 (WA)
CITATION: CHELLEM and KULOWALL CONSTRUCTION PTY LTD [2022] WASAT 95
MEMBER: MS KY LOH, MEMBER
MR P MARSHALL, SESSIONAL MEMBER
HEARD: 15 AUGUST 2022
DELIVERED : 2 NOVEMBER 2022
FILE NO/S: CC 199 of 2022
BETWEEN: OBED CHELLEM
First Applicant
SHAZIA ALI
Second Applicant
AND
KULOWALL CONSTRUCTION PTY LTD
Respondent
Catchwords:
Building services complaint - Home Building Contract complaint - Whether builder entitled to increase contract price after laying slab - Whether contract was validly terminated - Whether owners entitled to compensation
Legislation:
Building Services (Complaint Resolution and Administration) Act 2011 (WA), s 5(2), s 41(2), s 41(2)(a)(ii), s 41(2)(d)(i), s 43
Home Building Contracts Act 1991 (WA), s 3, s 9, s 9(1), s 9(1)(a), s 9(2), s 9(2)(a)(i), s 9(2)(b)(i), s 17, s 25C, s 25C(2), Pt 2, Pt 3A, Sch 1, cl 2, cl 4, cl 5(1)
Result:
Application allowed
Category: B
Representation:
Counsel:
| First Applicant | : | In Person |
| Second Applicant | : | In Person |
| Respondent | : | Mr M Salman (as representative) |
Solicitors:
| First Applicant | : | N/A |
| Second Applicant | : | N/A |
| Respondent | : | N/A |
Case(s) referred to in decision(s):
Nil
REASONS FOR DECISION OF THE TRIBUNAL:
Introduction
The owners of a block of land in Girarawheen, Mr Obed Chellem and Ms Shazia Shehnaz Ali, entered into a contract with Kulowall Construction Pty Ltd to build a double storey house on their land.
After the ground floor slab was poured, no further works were undertaken as the parties disagreed about an increase in contract price.
The builder relies on a provision in the contract which allows it to increase the contract price if a delay to the commencement of works of more than 45 days into the contract was caused by the owners, that being their failure to obtain finance in time.
The owners dispute that the builder raised this failure with them as the reason for the price increase, which was instead motivated by an increase in bricklaying costs.
The builder lodged a notice of cessation with the City of Wanneroo as a result of termination of the contract 'by mutual agreement', which the owners also dispute was their intention.
For reasons set out below, we are not satisfied that the contract was terminated, nor was any price increase valid under the contract.
The contract remains on foot, and the owners will be compensated for the loss of rental income and consequential losses due to the unlawful suspension of work by the builder.
Issue for determination
The primary issue for determination is whether a Home Building Work Contract (HBWC) remedy order is justified in the circumstances.
In considering the primary issue, the following secondary issues arise:
1)whether the builder was entitled to increase the contract price as a matter of contract law and whether the builder has complied with the provisions of the Home Building Contracts Act 1991 (WA) (the ContractsAct)?
2)whether the contract between the parties was…
Keep reading for free
Create a free CaseChat account to read CHELLEM and KULOWALL CONSTRUCTION PTY LTD and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2022] WASAT 95
- Decision Date
CaseChat Overview and Summary
The primary legal issues were whether the builder was entitled to increase the contract price post-slab laying, whether the contract was validly terminated by the owners, and whether the owners were entitled to compensation. The court had to interpret the contract terms to determine the validity of the price increase and termination, and assess whether the owners were entitled to compensation under the statutory framework governing home building contracts.
The court found that the contract did not permit a price increase after the slab was laid, as the terms were clear and unambiguous. The builders' claim for an increased price was rejected. Regarding the termination, the court held that the owners validly terminated the contract due to the builders' failure to meet critical deadlines. Finally, the court determined that the owners were entitled to compensation for the builders' breaches, as per the statutory provisions. The builders were ordered to compensate the owners for the losses incurred due to the contract termination.
The court's final orders required the builders to compensate the owners for the losses incurred due to the contract termination. The builders were also directed to pay the owners' costs of the proceedings.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.