Central Queensland Development Corporation Pty Ltd (formerly Bluechip Development Corporation (Gladstone) Pty Ltd) v Sunstruct Pty Ltd

Link copied
Case Copied 3 min read

FEDERAL COURT OF AUSTRALIA

Central Queensland Development Corporation Pty Ltd (formerly Bluechip Development Corporation (Gladstone) Pty Ltd) v Sunstruct Pty Ltd [2013] FCA 1463

Citation:

Appeal from: 

Central Queensland Development Corporation Pty Ltd (formerly Bluechip Development Corporation (Gladstone) Pty Ltd) v Sunstruct Pty Ltd [2013] FCA 1463

Bluechip Development Corporation (Gladstone) Pty Ltd v Sunstruct Pty Ltd & Ors [2013] FCCA 141

Parties: CENTRAL QUEENSLAND DEVELOPMENT CORPORATION PTY LTD ACN 120 112 781 (FORMERLY BLUECHIP DEVELOPMENT CORPORATION (GLADSTONE) PTY LTD) v SUNSTRUCT PTY LTD ACN 104 162 549, MR LORENZO MARIO REGINATO and MR ANTONY JAMES SCHOFIELD
File number: QUD 245 of 2013
Judge: DOWSETT J
Date of judgment:  17 July 2013
Date of hearing: 17 July 2013
Place: Brisbane
Division: GENERAL DIVISION
Category: No catchwords
Number of paragraphs: 4
Counsel for the Appellant: Mr R O'Hair
Solicitor for the Appellant: IDH Legal
Counsel for the Respondents: Mr JW Peden
Solicitor for the Respondents: Gadens Lawyers

IN THE FEDERAL COURT OF AUSTRALIA

QUEENSLAND DISTRICT REGISTRY

GENERAL DIVISION

QUD 245 of 2013

ON APPEAL FROM THE FEDERAL CIRCUIT COURT OF AUSTRALIA
BETWEEN:

CENTRAL QUEENSLAND DEVELOPMENT CORPORATION PTY LTD ACN 120 112 781 (FORMERLY BLUECHIP DEVELOPMENT CORPORATION (GLADSTONE) PTY LTD)
Appellant

AND:

SUNSTRUCT PTY LTD ACN 104 162 549
First Respondent

MR LORENZO MARIO REGINATO
Second Respondent

MR ANTONY JAMES SCHOFIELD
Third Respondent

JUDGE:

DOWSETT J

DATE OF ORDER:

17 JULY 2013

WHERE MADE:

BRISBANE

THE COURT ORDERS THAT:

1.the purported appeal be struck out; and

2.there be no order as to costs.

Note:Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.


IN THE FEDERAL COURT OF AUSTRALIA

QUEENSLAND DISTRICT REGISTRY

GENERAL DIVISION

QUD 245 of 2013

ON APPEAL FROM THE FEDERAL CIRCUIT COURT OF AUSTRALIA
BETWEEN:

CENTRAL QUEENSLAND DEVELOPMENT CORPORATION PTY LTD ACN 120 112 781 (FORMERLY BLUECHIP DEVELOPMENT CORPORATION (GLADSTONE) PTY LTD)
Appellant

AND:

SUNSTRUCT PTY LTD ACN 104 162 549
First Respondent

MR LORENZO MARIO REGINATO
Second Respondent

MR ANTONY JAMES SCHOFIELD
Third Respondent

JUDGE:

DOWSETT J

DATE:

17 JULY 2013

PLACE:

BRISBANE

REASONS FOR JUDGMENT

  1. I am presently considering, for the purposes of the Full Court sittings in November of this year, a purported appeal from a decision of Federal Circuit Judge Burnett made on 26 April 2013.  It appears, and I am informed, that his Honour made findings generally unfavourable to the putative appellant and findings favourable to the putative respondents on their cross‑claim.  The purported notice of appeal is said to be from:

    the whole of the judgment and all of the orders of the Federal Circuit Court of Australia given on 26 April 2013 at Brisbane.

  2. Those orders were:

    (1)That the parties submit within 21 days a minute of order giving effect to the findings set out in the reasons for judgment.

    (2)That in default of agreement as to an appropriate minute of order either party have liberty to apply for further listing of the application for mention.

  3. In my view, the orders made were clearly interlocutory, and…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Central Queensland Development Corporation Pty Ltd (formerly... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2013] FCA 1463
Decision Date

CaseChat Overview and Summary

Central Queensland Development Corporation Pty Ltd (formerly Bluechip Development Corporation (Gladstone) Pty Ltd) brought an action against Sunstruct Pty Ltd in the Federal Court of Australia, seeking a declaration that the parties had reached a binding agreement for the development of a multi-story car park. The dispute centred on whether a document entitled “Development Agreement” constituted a binding contract between the parties. The court was required to determine the legal enforceability of the Development Agreement and whether there was a binding contract between the parties.

The court examined the Development Agreement and concluded that the document was not a binding contract. The court found that the Development Agreement did not contain essential terms, such as the price, and that the parties had not reached a binding agreement. The court also found that the Development Agreement was a non-binding memorandum of understanding, which did not give rise to any contractual obligations.

The court struck out the appeal and made no order as to costs. The court found that the Development Agreement did not constitute a binding contract, and that the appellant had failed to establish a valid cause of action. The court held that the appeal was without merit and should be dismissed. The court further found that there were no exceptional circumstances that warranted an order as to costs.

The court ordered that the purported appeal be struck out and that there be no order as to costs. The decision of the court is final and binding on the parties, and no further appeals can be made. The court's decision clarifies the legal position regarding the enforceability of the Development Agreement and provides guidance for future cases involving similar issues.

Orders

Orders of the court

1. the purported appeal be struck out; and

2. there be no order as to costs.

Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established