Medium Neutral Citation: Centennial Mandalong v Delta Electricity [2013] NSWSC 1505 Hearing dates: 17/09/2013 Decision date: 17 October 2013 Jurisdiction: Equity Division - Commercial List Before: McDougall J Decision: Plaintiff entitled to first declaration sought. Stand over for further consideration of second declaration sought. Reserve costs.
Catchwords: CONTRACTS - interpretation - where coal supply agreement provides for apportionment of charges attributable to coal sold - where government levies charges on carbon emissions associated with coal production - whether charges levied for carbon emissions attributable to coal sold - meaning of words "attributable to"; "attributibility"; "attribute" - whether causal connection between charges levied for carbon emissions during coal production and the subsequent sale of coal. Legislation Cited: Clean Energy Act 2011 (Cth)
Clean Energy (Unit Shortfall Charge - General) Act 2011 (Cth)
National Greenhouse and Energy Reporting Act 2007 (Cth)
Repatriation Act 1920 (Cth)
Veterans' Entitlements Act 1986 (Cth)Cases Cited: AFC Holdings Pty Ltd v Shiprock Holdings Pty Ltd (2010) 15 BPR 28, 199
Central Asbestos Co Ltd v Dodd [1973] AC 5
Dovuro Pty Ltd v Wilkins (2000) 105 FCR 476
Repatriation Commission v Law (1980) 31 ALR 140
Roncevich v Repatriation Commission (2005) 222 CLR 115Category: Principal judgment Parties: Centennial Mandalong Pty Limited (Plaintiff)
Delta Electricity (Defendant)Representation: Counsel:
AC Archibald QC / J Williams
NC Hutley SC / JA Watson
Solicitors:
Herbert Smith Freehills (Plaintiff)
Jones Day (Defendant)
File Number(s): 2012/384031
Judgment
HIS HONOUR: The plaintiff (Centennial) operates the Mandalong coal mine in the Lake Macquarie district of New South Wales. The defendant (Delta) operates the Vales Point power station. Mandalong sells coal from its Mandalong mine to Delta, on the terms of a contract made on 12 April 2002. Centennial's obligations are affected by, and it will have to pay carbon costs under, the Clean Energy Act 2011 (Cth) and related legislation. The question for decision is whether, having regard to the relevant terms of the contract, Centennial can pass some part of those costs onto Delta.
The mining operations at Mandalong
Coal is formed from biomass materials that, over time, have become trapped underground and subjected to high temperatures and pressures. The process of "coalification" (an unpleasant but useful word) produces not only coal but also gaseous materials known generically as "seam gases". Seam gases are trapped in pockets, or pores, within both the coal and the rock strata that surround or enclose the coal.
When coal is mined, one consequence is that the pressure that retains the seam gases in situ may be released. When that happens, the seam gases travel out of the pockets where they are trapped, and may find their way into the atmosphere.
The major seam gas produced by the Mandalong mine is methane. Methane, a hydrocarbon compound, is a "carbon dioxide equivalent greenhouse gas" for the purposes of the Clean Energy Act.
The mining works at the Mandalong mine include the following operations:
(1) a vertical shaft has been sunk from the…
Keep reading for free
Create a free CaseChat account to read Centennial Mandalong v Delta Electricity and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2013] NSWSC 1505
- Decision Date
CaseChat Overview and Summary
The court approached the interpretation of the agreement by considering the ordinary meaning of the terms used, as well as the context in which they appeared. The court held that the key to resolving the dispute lay in understanding whether the carbon emission charges were directly linked to the coal sold. It was necessary to ascertain if the charges were a direct result of the production and sale of the coal, or if they were more broadly related to the overall carbon emissions from the production process. The court ultimately found that the charges were indeed attributable to the coal sold, as they were directly linked to the production process that resulted in the sale of coal. This conclusion was based on the causal connection between the carbon emissions during coal production and the subsequent sale of the coal.
The court's reasoning was grounded in the principle of interpreting contractual terms in their commercial context. By examining the nature of the charges and their direct link to the coal sold, the court was able to determine that the carbon emission charges fell within the scope of the apportionment clause in the agreement. This decision provided clarity for both parties regarding their respective obligations under the coal supply agreement. The outcome ensured that the charges levied for carbon emissions were properly apportioned, reflecting the causal relationship between the production of coal and the subsequent sale of that coal. The final orders of the court required Centennial Mandalong to bear the carbon emission charges attributable to the coal sold, as per the terms of the agreement.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi