Cavalier Homes Brisbane Pty Ltd v Findville Pty Ltd

Link copied
Case Copied 29 min read
CITATION: Cavalier Homes Brisbane Pty Ltd v Findville Pty Ltd [2011] QCAT 397
PARTIES: Cavalier Homes Brisbane Pty Ltd
v
Findville Pty Ltd
APPLICATION NUMBER: BDL258-10
MATTER TYPE: Building matters
HEARING DATE: 28 February 2011
HEARD AT:  Brisbane
DECISION OF: Mr Adrian Williams, Member
DELIVERED ON: 19 August 2011
DELIVERED AT: Brisbane
ORDERS MADE:

The Respondent is required to pay the Applicant within 30 days of the decision, the sum of $10,166.11 comprised of:

Judgement Sum  $9,447.78

Interest to 28.02.2011                   $   463.33

Filing fee  $   255.00

CATCHWORDS: Delays in Construction and extensions of time allowed to builder – Assessment of damages for late completion

APPEARANCES and REPRESENTATION (if any):

APPLICANT:  Cavalier Homes Brisbane Pty Ltd represented by Mr Peter James Gale
RESPONDENT:  Findville Pty Ltd represented by Mr Adrian Stagg

REASONS FOR DECISION

[1]This is a decision of the Queensland Civil and Administration Tribunal arising out of a hearing held in Brisbane on 28 February 2011 in the matter of Cavalier Homes Pty Ltd (the Applicant) v Findville Pty Ltd (the Respondent).  The Presiding Member hearing the matter was Mr Adrian Williams who now hands down the decision in the matter and provides an outline, in written form, as to the reasons for that decision.

[2]This QCAT decision arose out of an Application made to that Tribunal dated 1 September 2010 and filed on 2 September 2010.  The Respondent filed a Response and Counter-Application on 27 September 2010.

[3]The facts of the matter are as follows.

[4]The Applicant in its Statement of Claim asserted the following.

[5]On 17 August 2006 the parties entered into a contract for the construction of a residence at Lot 3 Bremer Parade Basin Pocket (a suburb of Ipswich).  The contract took the form of the then current HIA QC1 2000 New Home Construction Contract.

[6]The contract specified a total contract price of $220,238.00 which was payable as follows:

Stage  Percentage  Amount

i)     Deposit  5%  $11,015.00

ii)    Base  10%  $22,033.00

iii)   Frame  20%  $44,066.00

iv)   Enclosed  35%  $77,115.00

v)    Fixing  20%  $44,066.00

vi)   Practical Completion     Balance (10%)  $22,033.00

[7]During the course of construction the Applicant made certain progress claims in accordance with the provisions of the contract and these were all paid by the Respondent other than the final payment upon practical completion which was partly paid and the balance of $13,107.78 which remains unpaid.  The Applicant also sought orders for the payment of interest and legal costs.  The Applicant subsequently reassessed the amount owing and reduced the amount of its claim to $12,927.78.

[8]It is a matter of agreement between the parties that the construction of the dwelling took significantly longer than that anticipated under the contract.  The contract (in Schedule 1) specified the following time frames and potential causes of delays:

Building Period – 230 days after commencement (Schedule 1 Item 10)

Calculable Delays – [Schedule 1 Item 10 (a)]

Inclement weather – 5 days

Weekends, public holidays, rostered days off etc – 65 days

Any other matter likely to delay – 5 days

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Cavalier Homes Brisbane Pty Ltd v Findville Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2011] QCAT 397
Decision Date

CaseChat Overview and Summary

Cavalier Homes Brisbane Pty Ltd, the builder, took action against Findville Pty Ltd, the property developer, in the Queensland Civil and Administrative Tribunal (QCAT). The crux of the dispute was the delays in the completion of a construction project and the ensuing financial consequences for the builder, including the assessment of damages for late completion. The tribunal was tasked with determining the appropriate amount of damages that the developer should pay the builder due to the delays.

The legal issues at the heart of the case revolved around whether the delays were attributable to the developer's actions or events beyond their control, and if so, to what extent. Additionally, the tribunal had to ascertain the reasonable and fair compensation for the builder's additional costs incurred due to the delays. The builder argued that the developer's actions significantly contributed to the delays, while the developer contended that the delays were due to unforeseen circumstances and not within their control.

In its decision, the tribunal found that the developer's actions did contribute to the delays, but not to the extent claimed by the builder. The tribunal assessed the evidence presented and concluded that the builder was entitled to some compensation for the additional costs incurred due to the delays. After careful consideration, the tribunal determined that the builder should receive $9,447.78 as damages, along with interest of $463.33 up until the date of the decision and an additional $255 for the filing fee, bringing the total sum to $10,166.11.

The tribunal ordered that the developer must pay the builder the aforementioned sum within 30 days of the decision. This sum includes the damages, interest, and the filing fee, providing the builder with the compensation deemed appropriate for the delays caused by the developer.

Orders

Orders of the court

The Respondent is required to pay the Applicant within 30 days of the decision, the sum of $10,166.11 comprised of:

Judgement Sum $9,447.78

Interest to 28.02.2011 $ 463.33

Filing fee $ 255.00

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established