Castle Constructions Pty Ltd v Napoli Excavations and Civil Pty Ltd

Link copied
Case Copied 13 min read

Supreme Court


New South Wales

Medium Neutral Citation: Castle Constructions Pty Ltd v Napoli Excavations and Civil Pty Ltd [2023] NSWSC 348
Hearing dates: 5 April 2023
Date of orders: 5 April 2023
Decision date: 05 April 2023
Jurisdiction:Equity
Before: Darke J
Decision:

Adjudication determination declared to be void and of no effect.

Catchwords:

BUILDING AND CONSTRUCTION – Building and Construction Industry Security of Payment Act 1999 (NSW) (“the Act”) – adjudication determination – whether adjudication determination is affected by jurisdictional error – whether the adjudicator failed to consider all submissions duly made – held that the adjudicator failed to consider a submission duly made in support of the payment schedule as required by s 22(2)(d) of the Act – held further that the failure was material – jurisdictional error established – declaration made that adjudication determination is void and of no effect

Legislation Cited:

Building and Construction Industry Security of Payment Act 1999 (NSW), ss 13(1C), 20(2B), 22(2)(d)

Uniform Civil Procedure Rules 2005 (NSW), rr 6.1, 10.14

Cases Cited:

BCFK Holdings Pty Ltd v Rork Projects Pty Ltd [2022] NSWSC 1706

Category:Principal judgment
Parties: Castle Constructions Pty Ltd (Plaintiff)
Napoli Excavations and Civil Pty Ltd (First Defendant)
Adjudicate Today Pty Ltd (Second Defendant)
Representation:

Counsel:
Mr D S Weinberger (Plaintiff)

Solicitors:
McLachlan Thorpe Partners (Plaintiff)
Richard Green Construction Lawyers (Second Defendant)
File Number(s): 2022/378535
Publication restriction: None

Judgment – EX TEMPORE (REVISED)

  1. By a Summons filed on 15 December 2022, the plaintiff (Castle Constructions Pty Ltd) seeks a declaration that an adjudication determination purportedly made under the Building and Construction Industry Security of Payment Act 1999 (NSW) (“the Act”) is void and of no effect. The adjudication determination (“the Determination”) was served on 8 December 2022. The adjudicator was Mr Callum Campbell of Adjudicate Today Pty Ltd, which has been named as the second defendant.

  2. The adjudicator determined that the first defendant (Napoli Excavations and Civil Pty Ltd) was entitled to be paid a progress payment by the plaintiff in the sum of $48,362.05 plus interest. The plaintiff has not paid the adjudicated amount to the first defendant.

  3. On 16 December 2022, the plaintiff obtained an order restraining the first defendant until 3 February 2023 from seeking an adjudication certificate in respect of the adjudicated amount. The plaintiff was at the same time ordered to pay the sum of $54,088.31 into Court pending the determination of the proceedings, or earlier order of the Court. The amount of $54,088.31 appears to be the sum of the adjudicated amount, interest up to 15 December 2022, and the adjudicator's fees. On 3 February 2023, the injunction against the first defendant was extended until the determination of the proceedings.

  4. Also on 3 February 2023, the Summons was listed for hearing today, and directions were made for the plaintiff to file a List Statement and brief written submissions. By that time the second defendant had filed a submitting appearance save as to costs, but no appearance had been entered by the first…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Castle Constructions Pty Ltd v Napoli Excavations and Civil... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2023] NSWSC 348
Decision Date

CaseChat Overview and Summary

In the matter of Castle Constructions Pty Ltd versus Napoli Excavations and Civil Pty Ltd, the dispute arose in the context of a payment claim submitted under a construction contract. The case was determined by the New South Wales Supreme Court. The primary focus of the litigation was on an adjudication determination that had been made in favour of Napoli Excavations and Civil Pty Ltd. Castle Constructions challenged the validity of this determination, arguing that it was flawed due to jurisdictional errors committed by the adjudicator.

The central legal issue before the court was whether the adjudication determination was tainted by a jurisdictional error. Specifically, Castle Constructions contended that the adjudicator had failed to consider all submissions that were duly made in the adjudication process. This omission, according to Castle Constructions, was a breach of section 22(2)(d) of the Building and Construction Industry Security of Payment Act 1999 (NSW). The court needed to determine whether this alleged failure constituted a material error that rendered the adjudication determination invalid.

The court found that the adjudicator indeed failed to consider a critical submission made in support of the payment schedule. This oversight was deemed to be a material error as it affected the fairness and correctness of the adjudication process. Given that the failure to consider all relevant submissions amounted to a jurisdictional error, the court concluded that the adjudication determination was void and of no effect. Consequently, the determination was declared invalid, and Castle Constructions’ challenge was successful.

In light of the findings, the court made a declaration that the adjudication determination was void and of no effect. This outcome effectively nullified the adjudicator's decision and left the matter open for further adjudication or resolution under the terms of the construction contract.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established