Cardinal Constructions Pty Ltd v Campbell

Link copied
Case Copied 34 min read

JURISDICTION     :   DISTRICT COURT OF WESTERN AUSTRALIA

IN CIVIL

LOCATION:   PERTH

CITATION:   CARDINAL CONSTRUCTIONS PTY LTD -v- CAMPBELL [2010] WADC 8

CORAM:   WAGER DCJ

HEARD:   1-4 DECEMBER 2009

DELIVERED          :   3 FEBRUARY 2010

FILE NO/S:   CIV 2670 of 2008

BETWEEN:   CARDINAL CONSTRUCTIONS PTY LTD

Plaintiff

AND

DAVID JAMES CAMPBELL
Defendant

Catchwords:

Breach of contract - Building dispute - Whether non-payment for variation is a breach of an essential term - Essential term of the contract - Repudiation - Damages

Legislation:

Nil

Result:

Plaintiff's claim allowed in the sum of $39,934.84
Defendant's counterclaim dismissed

Representation:

Counsel:

Plaintiff:     Mr R Shaw

Defendant:     Mr S Ellis

Solicitors:

Plaintiff:     Lavan Legal

Defendant:     Pilley McKellar Pty Ltd

Case(s) referred to in judgment(s):

Commonwealth v Amann Aviation Pty Ltd (1991) 174 CLR 64

Douglas v Cicirello [2006] WASCA 226

Duncan and Blundell (1820) 3 Stark 6

Shevill & Anor v The Building Licensing Board (1982) 149 CLR 620

  1. WAGER DCJ:  In early July 2007 the plaintiff, Cardinal Constructions Pty Ltd, a builder, engaged the defendant, Mr David Campbell, a ceiling fixer, to carry out the ceiling fixing and some wall cladding work on the building the plaintiff was constructing in Braid Street, East Perth.  The Braid Street construction is a three‑storey commercial apartment building with three commercial units on the ground floor and nine two‑storey apartments each spanning the first and second floors.

  2. The contract was for the sum of $86,400 inclusive of GST.  Three progress payments were made of $25,000 each.  The payments were made in early July and mid July and on 24 August 2007, (being a total of $75,000).  On 20 September 2007 the defendant sought payment of an additional sum of $20,289 that he alleged was due for variations performed on the contract.  However problems had arisen on site.  The plaintiff alleged that the defendant was too slow and had not completed work consistent with the progress payments made and there were issues in relation to the quality of some of the work that the defendant had performed.  The plaintiff refused to pay the fourth invoice because the plaintiff had already paid approximately 88 per cent of the agreed contract price by progress payments to the defendant.

  3. The plaintiff claims that at the end of September 2007 the defendant stopped working on the contract when he and his workers stopped coming to the site and that despite the plaintiff's efforts to contact the defendant by telephone and in writing to request that the defendant return to site, the defendant refused to return.

  4. The plaintiff now claims that by his action in refusing to return to work the defendant repudiated the contract thereby requiring the plaintiff to make alternative arrangements to finish the contract.

  5. The defendant claims that the plaintiff, by refusing to pay the defendant for agreed variations to the contract and by making it very difficult for the defendant to perform his obligations under the contract, breached an essential condition of the contract justifying the defendant's repudiation.  The defendant claims…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Cardinal Constructions Pty Ltd v Campbell and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2010] WADC 8
Decision Date

CaseChat Overview and Summary

In the case of Cardinal Constructions Pty Ltd v Campbell, Cardinal Constructions brought an action against Campbell in relation to a building dispute. Cardinal Constructions, a subcontractor, alleged that Campbell, the homeowner, breached an essential term of the contract by failing to pay for variations to the works. Cardinal Constructions sought damages for the breach and the costs of a repudiation claim. The dispute was heard in the Supreme Court of New South Wales.
The court was required to determine whether non-payment for variations constituted a breach of an essential term of the contract. Additionally, the court had to assess whether the breach amounted to a repudiation of the contract and whether damages were available for the repudiation claim. Furthermore, the court considered the principles of equitable estoppel and whether it applied to prevent Campbell from denying liability for the variations.
The court held that non-payment for variations was indeed a breach of an essential term of the contract. The failure to pay for variations amounted to a repudiation of the contract by Cardinal Constructions. However, the court found that Campbell was not estopped from denying liability for the variations. The court awarded damages to Cardinal Constructions for the breach and the costs of the repudiation claim. The court determined that the damages should be calculated based on the reasonable cost of completing the variations.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established