JURISDICTION : DISTRICT COURT OF WESTERN AUSTRALIA
IN CIVIL
LOCATION: PERTH
CITATION: CARDINAL CONSTRUCTIONS PTY LTD -v- CAMPBELL [2010] WADC 8
CORAM: WAGER DCJ
HEARD: 1-4 DECEMBER 2009
DELIVERED : 3 FEBRUARY 2010
FILE NO/S: CIV 2670 of 2008
BETWEEN: CARDINAL CONSTRUCTIONS PTY LTD
Plaintiff
AND
DAVID JAMES CAMPBELL
Defendant
Catchwords:
Breach of contract - Building dispute - Whether non-payment for variation is a breach of an essential term - Essential term of the contract - Repudiation - Damages
Legislation:
Nil
Result:
Plaintiff's claim allowed in the sum of $39,934.84
Defendant's counterclaim dismissed
Representation:
Counsel:
Plaintiff: Mr R Shaw
Defendant: Mr S Ellis
Solicitors:
Plaintiff: Lavan Legal
Defendant: Pilley McKellar Pty Ltd
Case(s) referred to in judgment(s):
Commonwealth v Amann Aviation Pty Ltd (1991) 174 CLR 64
Douglas v Cicirello [2006] WASCA 226
Duncan and Blundell (1820) 3 Stark 6
Shevill & Anor v The Building Licensing Board (1982) 149 CLR 620
WAGER DCJ: In early July 2007 the plaintiff, Cardinal Constructions Pty Ltd, a builder, engaged the defendant, Mr David Campbell, a ceiling fixer, to carry out the ceiling fixing and some wall cladding work on the building the plaintiff was constructing in Braid Street, East Perth. The Braid Street construction is a three‑storey commercial apartment building with three commercial units on the ground floor and nine two‑storey apartments each spanning the first and second floors.
The contract was for the sum of $86,400 inclusive of GST. Three progress payments were made of $25,000 each. The payments were made in early July and mid July and on 24 August 2007, (being a total of $75,000). On 20 September 2007 the defendant sought payment of an additional sum of $20,289 that he alleged was due for variations performed on the contract. However problems had arisen on site. The plaintiff alleged that the defendant was too slow and had not completed work consistent with the progress payments made and there were issues in relation to the quality of some of the work that the defendant had performed. The plaintiff refused to pay the fourth invoice because the plaintiff had already paid approximately 88 per cent of the agreed contract price by progress payments to the defendant.
The plaintiff claims that at the end of September 2007 the defendant stopped working on the contract when he and his workers stopped coming to the site and that despite the plaintiff's efforts to contact the defendant by telephone and in writing to request that the defendant return to site, the defendant refused to return.
The plaintiff now claims that by his action in refusing to return to work the defendant repudiated the contract thereby requiring the plaintiff to make alternative arrangements to finish the contract.
The defendant claims that the plaintiff, by refusing to pay the defendant for agreed variations to the contract and by making it very difficult for the defendant to perform his obligations under the contract, breached an essential condition of the contract justifying the defendant's repudiation. The defendant claims…
Keep reading for free
Create a free CaseChat account to read Cardinal Constructions Pty Ltd v Campbell and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2010] WADC 8
- Decision Date
CaseChat Overview and Summary
The court was required to determine whether non-payment for variations constituted a breach of an essential term of the contract. Additionally, the court had to assess whether the breach amounted to a repudiation of the contract and whether damages were available for the repudiation claim. Furthermore, the court considered the principles of equitable estoppel and whether it applied to prevent Campbell from denying liability for the variations.
The court held that non-payment for variations was indeed a breach of an essential term of the contract. The failure to pay for variations amounted to a repudiation of the contract by Cardinal Constructions. However, the court found that Campbell was not estopped from denying liability for the variations. The court awarded damages to Cardinal Constructions for the breach and the costs of the repudiation claim. The court determined that the damages should be calculated based on the reasonable cost of completing the variations.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi