Canterbury Local Environmental Plan 2012 (Amendment No 23) (2021-200) LW 30 April 2021 (NSW)

Case
No judgment structure available for this case.

New South Wales

Canterbury Local Environmental Plan 2012

(Amendment No 23)

under the

Environmental Planning and Assessment Act 1979

The following local environmental plan is made by the local plan-making authority under the

Environmental Planning and Assessment Act 1979.

BRETT WHITWORTH

As delegate for the Minister for Planning and Public Spaces

Canterbury Local Environmental Plan 2012 (Amendment No 23) [NSW]

Canterbury Local Environmental Plan 2012 (Amendment No 23)

under the

Environmental Planning and Assessment Act 1979

1      Name of Plan

This Plan is Canterbury Local Environmental Plan 2012 (Amendment No 23).

2      Commencement

This Plan commences on the day on which it is published on the NSW legislation website.

3      Land to which Plan applies

This Plan applies to Lot 25, DP 13586 and Lot X, DP 377169, 20 and 21 Boorea

Avenue, Lakemba.

4      Maps

The maps adopted by Canterbury Local Environmental Plan 2012 are amended or replaced, as the case requires, by the maps approved by the local plan-making authority on the making of this Plan.

5      Amendment of Canterbury Local Environmental Plan 2012

Schedule 1 Additional permitted uses

Insert at the end of the Schedule, with appropriate clause numbering—

Use of certain land at 20 and 21 Boorea Avenue, Lakemba

(1)

This clause applies to Lot 25, DP 13586 and Lot X, DP 377169, 20 and

21 Boorea Avenue, Lakemba.

(2)

Development for the purposes of residential care facilities is permitted

with development consent if the consent authority is satisfied that—

(a)

a comprehensive assessment of the flood risk has been carried out in relation to the development, and

(b)

the development will incorporate appropriate measures to—

(i)      manage flood risk on the land to which this clause applies and surrounding land, and

(ii)      ensure the residential care facility will be able to continue to operate during flooding, and

(c)

an emergency response management plan has been developed in consultation with the State Emergency Service and the Council.

Actions