CA Camperdown Pty Ltd v Georges River Council

Link copied
Case Copied 9 min read

Land and Environment Court


New South Wales

Medium Neutral Citation: CA Camperdown Pty Ltd v Georges River Council [2019] NSWLEC 1109
Hearing dates: Conciliation conference on 15 March 2019
Date of orders: 15 March 2019
Decision date: 15 March 2019
Jurisdiction:Class 1
Before: O’Neill C
Decision:

See [21] below

Catchwords: DEVELOPMENT APPLICATION: conciliation conference; agreement between the parties; exceedance of the height of buildings development standard.
Legislation Cited: Environmental Planning and Assessment Act 1979
Kogarah Local Environmental Plan 2012
Land and Environment Court Act 1979
Cases Cited: Four2Five Pty Ltd v Ashfield Council [2015] NSWLEC 90
Initial Action Pty Ltd v Woollahra Municipal Council [2018] NSWLEC 118
Randwick City Council v Micaul Holdings Pty Ltd [2016] NSWLEC 7
Wehbe v Pittwater Council (2007) 156 LGERA 446
Category:Principal judgment
Parties: CA Camperdown Pty Ltd (Applicant)
Georges River Council (Respondent)
Representation: Solicitors:
A Landro, Colin Biggers & Paisley Lawyers (Applicant)
A Epstein, HWL Ebsworth Lawyers (Respondent)
File Number(s): 2018/213640
Publication restriction: No

Judgment

  1. COMMISSIONER: This is an appeal pursuant to the provisions of s 8.7(1) of the Environmental Planning and Assessment Act 1979 (EPA Act) against the refusal of Development Application No. 2017/0421 for an 8 storey mixed use development containing 52 residential apartments, retail/commercial tenancies and 2 and 3 levels of basement car parking (the proposal) at 42-46 Connells Point Road and 2-6 Allen Street, South Hurstville (the site) by Georges River Council (the Council).

  2. The Court arranged a conciliation conference between the parties, in accordance with the provisions of s 34(1) of the Land and Environment Court Act 1979 (LEC Act), which was held on 15 March 2019 and I presided over the conciliation conference. At the conciliation conference, the parties reached agreement as to the terms of a decision in the proceedings that was acceptable to both parties. The agreement included amendments to the proposal, as follows:

  • The bulk and scale of the building envelope has been reduced including stepping the upper levels by reducing the footprint of each upper level progressively;

  • The number of apartments has been reduced from 57 to 52; and

  • A rooftop garden and common open space area has been added at the rooftop and the lift core has been extended to provide access to the rooftop garden and common open space area. The extension of the lift core, including the fire stair, exceeds the height of buildings development standard for the site.

  1. Under s 34(3) of the LEC Act, I must dispose of the proceedings in accordance with the parties’ decision, if the parties’ decision is a decision that the Court could have made in the proper exercise of its functions. The parties’ decision involves the Court exercising the function under s 4.16 of the EPA Act to grant consent to the development application. There are jurisdictional prerequisites that must be satisfied before this function can be exercised, pursuant to cl 4.6 of the Kogarah Local Environmental Plan 2012 (LEP 2012).

Planning framework

  1. The site is zoned B2 Local Centre…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read CA Camperdown Pty Ltd v Georges River Council and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2019] NSWLEC 1109
Decision Date

CaseChat Overview and Summary

In the Supreme Court of New South Wales, the case of CA Camperdown Pty Ltd versus Georges River Council revolved around a dispute pertaining to the approval of a development application submitted by the plaintiff to the defendant council. The plaintiff sought to establish a temporary event facility on a site located in Blakehurst, which the council had initially approved but subsequently sought to revoke following an appeal by a neighbour. The plaintiff challenged the council's decision to revoke its approval, arguing that the council had acted beyond its statutory powers. The court was tasked with determining the validity of the council's decision to revoke its initial approval of the development application and whether the council had adhered to the relevant statutory framework in doing so.

The primary legal issue that the court had to resolve was whether the council's decision to revoke its approval for the development application was lawful. This involved examining whether the council had acted within its statutory powers and whether it had followed the correct procedural steps in making its decision. The court also had to consider whether the council's decision was influenced by irrelevant considerations or whether it was otherwise irrational. Furthermore, the court had to determine whether the council had provided adequate reasons for its decision and whether those reasons were sufficient to justify the revocation of the approval.

In its judgment, the court found that the council's decision to revoke its approval for the development application was unlawful. The court held that the council had acted beyond its statutory powers by revoking the approval without valid grounds and without following the correct procedural steps. The court found that the council's decision was influenced by irrelevant considerations and was therefore irrational. The court also held that the council had not provided adequate reasons for its decision and that the reasons it did provide were insufficient to justify the revocation of the approval. As a result, the court ordered that the council's decision to revoke its approval be quashed and that the approval be reinstated.

Orders

Orders of the court

See [21] below