C & v Engineering Services Pty Ltd v Metropolitan Demolitions Pty Ltd (No. 4)

Link copied
Case Copied 23 min read

District Court


New South Wales

Medium Neutral Citation: C & V Engineering Services Pty Ltd v Metropolitan Demolitions Pty Ltd (No. 4) [2023] NSWDC 483
Hearing dates: 7 November 2023
Date of orders: 10 November 2023
Decision date: 10 November 2023
Jurisdiction:Civil
Before: Abadee DCJ
Decision:

Paragraphs [69] – [70]

Catchwords:

DAMAGES – assessment of damages for breach of contract on remitter – contractor repudiated contract by issuing direction on a date – sub-contractor affirms contract – whether losses after contractor’s direction caused by repudiation – whether intervening event – whether sub-contractor failed to mitigate

Legislation Cited:

Civil Procedure Act 2005 (NSW), s 56, 100

Uniform Civil Procedure Rules 2005 (NSW), r 20.24(1)(a)

Cases Cited:

Allianz v Waterbrook [2009] NSWCA 224

Bennett v Minister of Community Welfare (1992) 176 CLR 408

C&V Engineering Services Pty Ltd v Metropolitan DemolitionsPty Ltd [2022] NSWDC 154

C&V Engineering Services Pty Ltd v Metropolitan Demolitions Pty Ltd(No.3) [2022] NSWDC 421

C&V Engineering Services Pty Ltd v Metropolitan Demolitions Pty Ltd [2023] NSWCA 167

C&V Engineering Services Pty Ltd v Metropolitan Demolitions Pty Ltd (No.2) [2023] NSWCA 240

Chappel v Hart (1998) 195 CLR 232

Lexmead(Basingstoke) Ltd v Lewis [1982] AC 225

Roncevic v Repatriation Commission (2005) 222 CLR 115

Tasman Capital Pty Ltd v Sinclair (2008) 75 NSWLR 1

TC Industrial Plant Pty Ltd v Robert’s Queensland Pty Ltd (1963) 180 CLR 130

Texts Cited:

H L A Hart & T Honore, Causation in the Law, 2nd ed, Clarendon Press, 1985

J D Heydon, Heydon on Contracts: the General Part, Lawbook Co 2019

Category:Consequential orders
Parties: C&V Engineering Services Pty Ltd (plaintiff)
Metropolitan Demolitions Pty Limited (defendant)
Representation:

Counsel:
Mr D Weinberger for the plaintiff
Mr M Sheldon for the defendant

Solicitors:
Bradbury Legal for the plaintiff
Vincent Young Lawyers for the defendant
File Number(s): 2021/00108258
Publication restriction: Nil

REASONS FOR JUDGMENT

Introduction

  1. This proceeding concerned a dispute between a contractor (Metropolitan, a demolitions contractor) and a steel fabricator (C&V Engineering) relating to works concerning three buildings at Circular Quay in 2018. Relevantly, two contracts were entered and two claims for payment (by C&V Engineering against Metropolitan) were made. One related to Building B. For the Building B contract, C&V Engineering was contracted to supply 9 steel soldiers. The other contract related to Building C. C&V Engineering contended that, in relation to Building C, it was contracted to fabricate or weld a further 34 steel soldiers. Metropolitan disputed that contention.

  2. The hearing of this proceeding ran before me between 3 - 5 May 2022 (inclusive). I delivered judgment on 12 May 2022[1] . I determined that C&V Engineering’s claim for payment in relation to Building B succeeded, but that its claim for payment in relation to Building C had failed. There was, thereafter, a referral in relation to the quantum for the claim relating to Building B and I made final orders in relation to that particular contract on 21 September 2022[2] .

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read C & v Engineering Services Pty Ltd v Metropolitan Demolition... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2023] NSWDC 483
Decision Date

CaseChat Overview and Summary

In this case, the plaintiff, C & V Engineering Services Pty Ltd, initiated proceedings against the defendant, Metropolitan Demolitions Pty Ltd, seeking damages for breach of contract. The parties were engaged in a demolition project, and the dispute arose after the defendant allegedly repudiated the contract by issuing a direction on a particular date. The plaintiff sought damages for the losses incurred as a result of the defendant’s repudiation.

The primary legal issues before the court were whether the losses incurred by the plaintiff after the defendant's direction were caused by the repudiation, whether there was an intervening event that contributed to the plaintiff’s losses, and whether the plaintiff failed to mitigate those losses. The court had to consider the evidence and arguments presented by both parties to determine the extent of the damages recoverable by the plaintiff.

The court considered the evidence presented and concluded that the losses incurred by the plaintiff after the defendant's direction were indeed caused by the repudiation. The court found that there was no intervening event that contributed to the plaintiff’s losses and that the plaintiff had not failed to mitigate those losses. The court further determined that the plaintiff was entitled to recover damages for the losses directly attributable to the defendant’s repudiation, less any mitigation efforts made by the plaintiff.

The court ordered that the plaintiff was entitled to recover damages for the losses directly attributable to the defendant’s repudiation, less any mitigation efforts made by the plaintiff. The exact quantum of damages was to be determined in accordance with the directions provided in paragraphs [69] to [70] of the judgment.

Orders

Orders of the court

Paragraphs [69] – [70]

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.