LAND COURT OF QUEENSLAND
CITATION: Byerwen Coal Pty Ltd v Colinta Holdings Pty Ltd & Anor (No 2) [2016] QLC 9 PARTIES: Byerwen Coal Pty Ltd
(applicant)
v Colinta Holdings Pty Ltd
(first objector)
and
Glencore Coal Queensland Pty Ltd
(second objector)
FILE NO/s: MRA423-14
MRA424-14
MRA425-14
MRA426-14DIVISION: General Division PROCEEDING: Application by the appellant reopening of the hearing of MLA 70434 (MRA426-14) DELIVERED ON: 10 February 2016 Ex tempore DELIVERED AT: Brisbane HEARD ON: 10 February 2016 HEARD AT: Brisbane MEMBER: PA Smith ORDER/S: ’():‘ML70434 Mining Lease Objections Hearing’s objection to MLA 70434 In the matter of MRA426-14 relating to the second respondent
The Applicant’s application filed 16 December 2015 to reopen the Mining Lease Objections Hearing () is refused.Application1.
That order 5 of the Land Court Orders made on 7 December 2015 be made final.2.
That the Reasons and Decision of the Land Court made on 7 December 2015 in the Mining Lease Objections Hearing (‘’), together with all material that the Land Court must forward to the Minister pursuant to s 269(1) of the Mineral Resources Act 1989 (Qld), including:Decision3.
subject to Order 4, the Application, an Affidavit of Daniel Gerard McCarthy affirmed on 8 February 2016, an Affidavit of Toby Prior affirmed on 8 February 2016, an Affidavit of Christopher Wallin sworn on 8 February 2016, an Affidavit of Jordan Bachmann sworn on 11 February 2016, an Affidavit of Giselle Marguerite Kilvert affirmed on 10 February 2016and Exhibit 1 in the Application; (a)
the submissions filed by the Applicant and the Second Respondent in relation to the Application; and (b)
separately:(c)
the transcript of the hearing of the Application on 10 February 2016 recording the reasons of the Land Court (from T1-64 to T1-70); (i)
the transcript of the hearing of the Application on 10 February 2016 from T1-1 to T1-63; and(ii)
subject to order 4, the restricted parts of the transcript of the hearing of the Application on 10 February 2016;(iii)
be provided, together with the Decision, to The Honourable The Minister for the Department of Natural Resources and Mines.
That Exhibit TP2 to the Affidavit of Toby Prior sworn 8 February 2016 and filed 8 February 2016 and the restricted parts of the transcript referred to in order 3(c)(iii) be provided to the Minister in a sealed envelope marked “restricted and only to be opened by the Minister and any persons delegated by the Minister for the purpose of considering the application for the grant of MLA70434” and is otherwise to be kept restricted by all parties including the Minister. 4.
CATCHWORDS: ENVIRONMENT AND RESOURCES – application for mining lease – objections – functions and powers of Land Court – Mineral Resources Act 1989 (MRA)
COURT PRACTICE AND PROCEDURE – Land Court – application for reopening of MLA hearing – factors to be considered
COURT PRACTICE AND PROCEDURE – Land Court – role of Court in making recommendation to Minister – administrative not…
Keep reading for free
Create a free CaseChat account to read Byerwen Coal Pty Ltd v Colinta Holdings Pty Ltd (No 2) and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2016] QLC 9
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was the consideration of objections to the grant of a mining lease, specifically whether the potential environmental impacts outweighed the benefits of granting the lease. The court also needed to determine if the application to reopen the hearing for the Mineral and Petroleum Resources (State) Act 1989 (MRA) was justified and assess the appropriate role of the court in recommending the lease to the Minister for Natural Resources and Mines. The court had to balance the statutory obligations under the MRA and the procedural fairness in handling the application.
The Land Court considered the statutory provisions and case law relevant to the grant of mining leases and the role of the court in recommending such grants. The court held that it should not substitute its judgment for that of the Minister but rather provide a recommendation based on the evidence presented. The court found that the applicant had demonstrated a need to reopen the hearing due to new information and that the potential environmental impacts, while significant, were not insurmountable. The court concluded that the benefits of the mining lease outweighed the potential harm, provided certain conditions were met, and recommended the grant of the lease to the Minister.
The final orders of the court included the recommendation that the mining lease be granted to the applicant, subject to the satisfaction of specific conditions aimed at mitigating environmental impacts. The court also ordered that the respondents' costs of the reopened hearing be borne by the applicant.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi