Burke v Minister for State development, infrastructure, local government and planning

Link copied
Case Copied 29 min read

PLANNING AND ENVIRONMENT COURT
OF QUEENSLAND


CITATION:

Burke v Minister for State development, infrastructure, local government and planning & Anor [2022] QPEC 23

PARTIES:

PETER THOMAS BURKE

(applicant)

v

MINISTER FOR STATE DEVELOPMENT. INFRASTRUCTURE, LOCAL GOVERNMENT AND PLANNING
(first respondent)

and

PACIFIC VIEW FARM (QUEENSLAND) PTY LTD

(second respondent)

FILE NO/S:

787/22

DIVISION:

Planning and Environment Court

PROCEEDING:

Originating application

ORIGINATING COURT:

Planning and Environment Court, Brisbane

DELIVERED ON:

20 July 2022

DELIVERED AT:

Brisbane

HEARING DATE:

10 June 2022

JUDGE:

Williamson QC DCJ

ORDER:

The Originating application is dismissed.

CATCHWORDS:

PLANNING AND ENVIRONMENT – ORIGINATING APPLICATION – DECLARATORY PROCEEDING – where applicant challenges the validity of the Minister’s decision to approve a change application under the Planning Act 2016 – where the applicant contends the Minister failed to take into account relevant considerations – where applicant contends the Minister’s decision is legally unreasonable.

CASES:

Aqua Blue Noosa Pty Ltd v Noosa Shire Council [2005] QPELR 318
Australia Pacific LNG Pty Limited & Ors v The Treasurer, Minister for Aboriginal & Torres Strait Islander Partnerships and Minister for Sport [2019] QSC 124
Cleanaway Solid Waste Pty Ltd v Ipswich City Council [2021] QPELR 809
Fraser Coast Regional Council v Walter Elliott Holdings Pty Ltd [2017] 1 Qd R 13
House of Peace Pty Ltd v Bankstown City Council (2000) 106 LGERA 440
Minister for Aboriginal Affairs v Peko-Wallsend Ltd (1985-86) 162 CLR 24

Novadeck Pty Ltd v Brisbane City Council [2017] QPELR 152

LEGISLATION:

Planning Act 2016, ss 3, 4, 5, 78, 78A, 79, 80, 81, 81A, 105 and Schedule 2
Planning and Environment Court Act 2016, s 11
Sustainable Planning Act 2009, s 422

COUNSEL:

Mr P Burke, self-represented
Mr D O’Brien QC and Mr W Macintosh for the first respondent
Mr L Sheptooha for the second respondent

SOLICITORS:

Crown Solicitor for the first respondent

Minter Ellison Gold Coast for the second respondent

Introduction

  1. The applicant, by his Originating Application, challenges the validity of the Minister’s decision of 31 December 2021, as the responsible entity,[1] to change an extant development approval under the Planning Act 2016 (PA).  

    [1]s 78A(3), PA.

  2. The development approval the subject of the change application was granted in March 2015[2] for the Pacific View Estate located at Hinkler Drive, Worongary and varies the effect of Gold Coast City Council’s planning scheme (the development approval).[3]  The development approval has been changed on three occasions prior to the decision of 31 December 2021[4] and incorporates, by express reference, a document described as the ‘Skyridge Development Code’ (the Code).  The Code identifies how the approval varies the effect of the planning scheme.

    [2]Affidavit of Smith, p.77.

    [3]The development approval was granted when s 242 of the Sustainable Planning Act 2009 was in force.

    [4]Affidavit of Smith, p. 329; the development approval was changed on 11 November 2015, 1 August 2017 and 28 May 2021.

  3. The applicant advances two grounds of challenge.  First, it is contended the…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Burke v Minister for State development, infrastructure, loca... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2022] QPEC 23
Decision Date

CaseChat Overview and Summary

Burke brought an originating application challenging the Minister for State Development, Infrastructure, Local Government and Planning's approval of a change application under the Planning Act 2016. The applicant contended that the Minister failed to consider relevant factors and that the decision was legally unreasonable. The case was heard in the court, which was required to determine whether the Minister's decision was legally sound and whether all relevant considerations were taken into account.

The court examined the legal issues presented, focusing on whether the Minister's decision was legally unreasonable and whether all relevant factors were considered. The applicant argued that the Minister's decision was flawed due to an oversight of crucial considerations. The court assessed the Minister's actions against statutory requirements and examined the evidence and reasoning provided in the decision-making process.

The court found that the Minister's decision was not legally unreasonable and that all relevant considerations had been adequately addressed. The court was satisfied that the Minister had followed the correct procedures and had considered all necessary factors in reaching the decision. Consequently, the court dismissed the originating application.

The court dismissed the originating application and made no further orders. The Minister's decision to approve the change application under the Planning Act 2016 was upheld as legally sound.

Orders

Orders of the court

The Originating application is dismissed.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established