Bundaberg Regional Council v Lammi & Anor

Link copied
Case Copied 24 min read

PLANNING & ENVIRONMENT COURT
OF QUEENSLAND

CITATION:

Bundaberg Regional Council v Lammi & Anor [2014] QPEC 52

PARTIES:

BUNDABERG REGIONAL COUNCIL

(applicant)

v

KENNETH AARRE LAMMI

(first respondent)

and

SUE-ELLEN LAMMI

(second respondent)

FILE NO/S:

2350/14

DIVISION:

Planning & Environment

PROCEEDING:

Application

ORIGINATING COURT:

Planning & Environment Court at Brisbane

DELIVERED ON:

5 September 2014

DELIVERED AT:

Brisbane

HEARING DATE:

26 August 2014

JUDGE:

Horneman-Wren SC DCJ

ORDER:

1.   The respondents are jointly fined $5,000 for contempt of the Order of his Honour Judge Andrews SC made 27 November 2013 in Planning and Environment Court proceedings No. 2879 of 2013.

2.   The fine is to be paid within three (3) months of this order being made.

3.   Paragraphs 2, 3, 4, 5 and 6 of the Order of his Honour Judge Andrews SC made 27 November 2013 in Planning and Environment Court proceedings No. 2879 of 2013 are vacated.

4.   In lieu of the vacated paragraphs;

The first respondent by himself, his servants or agents must:

undertake the relevant steps to refer the building development application to the applicant by 17 September 2014;a.   

use his best endeavours to:b.   

pursue the building development application expeditiously; andi.   

obtain an effective building development approval by 17 October 2014 (“development permit for building works”);ii.   

within three months of obtaining the development permit for building works, and by no later than 17 January 2015, complete the building works for the exterior of the relocated buildings approved by the development permit for building works; and c.   

within six months of obtaining the development permit for building works, and by no later than 30 April 2015 complete the balance of the building works for the relocated buildings and obtain the final certificate of completion.d.   

The respondents are to pay the applicant’s costs of the application on the standard basis.5.   

CATCHWORDS:

PROCEDURE – CONTEMPT, ATTACHMENT AND SEQUESTRATION – CONTEMPT - WHAT CONSTITUTES – DISOBEDIENCE OF ORDERS OF COURT – OTHER CASES – where an enforcement order was made by the his Honour Judge Andrews SC in the Planning & Environment Court on 17 November 2013 – where the order was made by consent – where the enforcement order required the respondents to take action regrading their property – where the action was not taken – whether the respondents are in contempt of the enforcement order

PROCEDURE – CONTEMPT, ATTACHMENT AND SEQUESTRATION – POWER OF COURT TO PUNISH FOR CONTEMPT – OTHER COURTS – OTHER CASES – where the respondents admit they are in contempt of a court order – where the respondents have taken steps in attempting to follow the enforcement order – where the applicant submits that a sentence ought be imposed – whether imprisonment is the appropriate remedy for the respondents’ contempt

PROCEDURE – JUDGMENTS AND ORDERS – AMENDING, VARYING AND SETTING ASIDE – OTHER CASES – where the applicant seeks a further enforcement order be made – where the applicant does not seek to vary or set aside the…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Bundaberg Regional Council v Lammi & Anor and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2014] QPEC 52
Decision Date

CaseChat Overview and Summary

The Bundaberg Regional Council brought an application against the Lammi respondents in relation to an enforcement order made in the Planning and Environment Court. The Council sought to have the respondents held in contempt of the enforcement order, as they had failed to take the requisite action regarding their property. The respondents admitted that they were in contempt of the court order, but argued that imprisonment was not the appropriate remedy. The Council also sought a further enforcement order to be made against the respondents. The Court had to determine whether the respondents were in contempt of the original order, and if imprisonment was an appropriate remedy for their contempt. The Court also needed to decide whether the original order should be varied or set aside, and whether a further enforcement order could be made against the second respondent who was no longer an owner of the property.

The Court found that the respondents were in contempt of the enforcement order, as they had not taken the requisite action regarding their property. The Court rejected the argument that imprisonment was not an appropriate remedy for their contempt, and found that a fine was a more suitable punishment. The Court also found that the original order should be varied, as the second respondent was no longer an owner of the property, and a further enforcement order could be made against the first respondent. The Court set out new steps that the respondents needed to take in relation to their property, and ordered that the respondents pay the Council's costs of the application.

In summary, the Bundaberg Regional Council successfully brought an application against the Lammi respondents in relation to an enforcement order made in the Planning and Environment Court. The Court found that the respondents were in contempt of the order, and imposed a fine as a punishment. The Court varied the original order, and made a new enforcement order against the first respondent. The respondents were ordered to pay the Council's costs of the application. The Court's decision highlights the importance of complying with court orders, and the consequences of failing to do so.

Orders

Orders of the court

1. The respondents are jointly fined $5,000 for contempt of the Order of his Honour Judge Andrews SC made 27 November 2013 in Planning and Environment Court proceedings No. 2879 of 2013.

2. The fine is to be paid within three (3) months of this order being made.

3. Paragraphs 2, 3, 4, 5 and 6 of the Order of his Honour Judge Andrews SC made 27 November 2013 in Planning and Environment Court proceedings No. 2879 of 2013 are vacated.

4. In lieu of the vacated paragraphs;

The first respondent by himself, his servants or agents must:

undertake the relevant steps to refer the building development application to the applicant by 17 September 2014;a.

use his best endeavours to:b.

pursue the building development application expeditiously; andi.

obtain an effective building development approval by 17 October 2014 (“development permit for building works”);ii.

within three months of obtaining the development permit for building works, and by no later than 17 January 2015, complete the building works for the exterior of the relocated buildings approved by the development permit for building works; and c.

within six months of obtaining the development permit for building works, and by no later than 30 April 2015 complete the balance of the building works for the relocated buildings and obtain the final certificate of completion.d.

The respondents are to pay the applicant’s costs of the application on the standard basis.5.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.