Building Amendment Regulations (No. 2) 2018 (WA)
5 October 2018 GOVERNMENT GAZETTE, WA 4013 INDUSTRY REGULATION
1S301
Building Act 2011
Building Amendment Regulations (No. 2) 2018
Made by the Governor in Executive Council.
1. Citation
These regulations are the Building Amendment Regulations
(No. 2) 2018.2. Commencement
These regulations come into operation as follows —
(a) regulations 1 and 2 — on the day on which these regulations are published in the Gazette;
(b) the rest of the regulations — on the day after that day. 3. Regulations amended
These regulations amend the Building Regulations 2012.
4. Regulation 3 amended
In regulation 3 insert in alphabetical order:
5. Regulation 31A amended
In regulation 31A(1) delete "31B, 31C and 31D" and insert:
31C, 31D and 31HA CV3 means the verification method CV3 set out in the
Building Code Volume 1 Section C;
fire resistance performance requirement means a
requirement that is part of the Building Code Volume 1
performance requirement CP2 if the purpose of the
requirement is to avoid the spread of fire via an
external wall of a building;
| 4014 | GOVERNMENT GAZETTE, WA | 5 October 2018 |
6. Regulation 31B deleted
Delete regulation 31B.
7. Regulation 31E amended
In regulation 31 E( 1) delete "31 BA and 31 C" and insert:31BA,3lC and 3lHA
8. Regulation 31G amended
In regulation 31 G( 1) delete regulation 31 BA otherwise provides," and insert:
regulations 3 IBA and 3 1 H otherwise provide,
Note: The heading to amended regulation 31 G is to read:
Applicable building standards for replacement occupancy permit for change of building's classification, or occupancy permit for unauthorised work to building, or for building approval certificate for unauthorised work to building or incidental structure (s. 3, 49(b)5 51(2) and (3) and 57(3))
9. Regulation 31HA inserted
At the end of Part 4 Division 1 Subdivision 1 insert:31HA. Applicable building standards for non-combustible
external walls (s. 3, 19(3), 37(1) and (2) and 57(3))
(1) In this regulation -
commencement date means the date on which the
Building Amendment Regulations (No. 2)2018
regulation 9 comes into operation;
debris criteria means the following classification criteria in AS 5113:2016 (Fire propagation testing and
classification of external walls of buildings) as
referenced in CV3 -
(a) the criterion set out in clause 5.4.3(g); (b) the criterion set out in clause 5.4.5(g); (c) the criterion set out in clause 5.4.6(f); exempt remedial work means remedial work that is
carried Out primarily for the purposes of ensuring that
an external wall of an existing building or incidental
structure complies with the fire resistance performance
requirement;
5 October 2018 GOVERNMENT GAZETTE, WA 4015 existing building or incidental structure means a
building or an incidental structure in relation towhich -
(a)
an application for a building permit was made before the commencement date; or
(b)
a building licence or other approval that was required to be granted under the written law applicable at the time was granted before the commencement date; or
(c)
a building permit, building licence or other approval was not required and the construction of the building or the incidental structure commenced before the commencement date;
external wall has the meaning given in the Building
Code Volume! Part Al;
non-combustible external wall means an external wallthat is required to be non-combustible (as defined in
the Building Code Volume 1 Part Al) by the Building Code Volume 1 Part C!.9;
remedial work means building work that is the
renovation, alteration, improvement or repair of abuilding or an incidental structure.
(2) For the purposes of the definition of applicable
building standard in section 3, the building standards
set out in subregulation (3) are prescribed as applicable
building standards for the purposes of sections 19(3),
37(1) and (2) and 5 7(3) in respect of non-combustible
external walls.(3) For subregulation (2), the applicable building standards
are the requirements mentioned in regulation 3 !A(2),
except to the extent that subregulations (4) to (6)
provide otherwise.
(4) A performance solution to the fire resistance performance requirement must not be used unless the
performance solution is verified in accordance
with CV3.(5) Despite subregulation (4), a performance solution to
the fire resistance performance requirement that is used
for exempt remedial work is not required to be verified
in accordance with CV3.(6)
The debris criteria do not need to be complied with if it can be shown that, in the event of a fire in the external walls, the debris -
(a) will not prevent the safe evacuation of the
building's occupants; and
| 4016 | GOVERNMENT GAZETTE, WA | 5 October 2018 |
(b) will not pose a risk to an officer or member of a permanent fire brigade as defined in the Fire Brigades Act 1942 section 4(1). 10. Regulation 31J amended
After regulation 31J(2) insert:
(3) Despite subregulation (2), a CodeMark certificate must
not be used for a performance solution to the fire
resistance performance requirement unless the
performance solution is verified in accordance
with CV3.M. INGLIS, Clerk of the Executive Council.
0
0
0