| CITATION: | Brown v Queensland Building and Construction Commission (No 2) [2016] QCAT 7 |
| PARTIES: | Deborah Brown (Applicant) |
| v | |
| Queensland Building and Construction Commission (Respondent) |
| APPLICATION NUMBER: | GAR010-15 |
| MATTER TYPE: | Building matters |
| HEARING DATE: | On the papers |
| HEARD AT: | Brisbane |
| DECISION OF: | Member Gardiner |
| DELIVERED ON: | 7 January 2016 |
| DELIVERED AT: | Brisbane |
| ORDERS MADE: | 1. The decision of the Queensland Building and Construction Commission dated 9 January 2014 is confirmed. 2. The application for costs is dismissed. |
| CATCHWORDS: | BUILDING – REVIEW – Where application made to review decision made in 2014 that a certifier engaged in unsatisfactory conduct or professional misconduct – Where an extension of time granted – Where no inspection made of requirements of Bushfire Attack Level 29 by certifier – Whether unsatisfactory conduct or professional misconduct Building Act 1975 (Qld), s 204 Troy Richardson’s Building Approvals & Inspections v QBSA [2013] QCAT 113; Schwede v QBSA [2009] QCCTB 157 referred |
APPEARANCES:
This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld) (QCAT Act).
REASONS FOR DECISION
Siblings Deborah and Christopher Brown constructed a kit home on Fraser Island, completed in December 2010, using the services of a local builder.
On 8 February 2012 Ms Brown lodged a complaint with the Queensland Building and Construction Commission (as it is now) concerning the conduct of the certifier Luke Nicholas Owen-Jones with respect to the site.
The Commission says the effect of the complaint was that Ms Brown alleged Mr Owen-Jones issued a Form 21 Final Inspection Certificate when the dwelling did not comply with the requirements of Bush Fire Attack Level (BAL) 29 of Australian Standard 3959-2009 for the construction of buildings in bushfire prone areas.
Initially the Commission says the complaint did not identify Ms Brown’s specific concerns and at the Commission’s request, Ms Brown provided a list of her specific issues.
While Ms Brown did not consider BAL29 was generally complied with, her specific concerns related to the deck made of pine not kwila; no nylon brushes of external door seals on the garage door; sealing of roof gaps; lack of signoff for an inspection of the slab; inadequate stormwater pit and lack of insulation in the roof.
This complaint was investigated by the Commission and on 9 January 2014, the Commission advised Ms Brown of its decision. The decision was that Mr Owen-Jones engaged in unsatisfactory conduct under section 204(1) of the Building Act 1975 (Qld) (‘Building Act’).
Mr Michael Pehrson, Senior Audit and Investigations Officer (Certification) with the Commission identified[1] that he believed Mr Owen-Jones had not inspected the work as required by the inspection guidelines in the final stage of 1a buildings for the construction requirements for bushfire prone areas. In particular, he should have confirmed the correct timber was used in the upper level deck framing and that the ends of the roof sheet over the ensuite were in-filled to stop hot ember penetration.
[1] In the Information Notice…
Keep reading for free
Create a free CaseChat account to read Brown v Queensland Building and Construction Commission (No... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2016] QCAT 7
- Decision Date
CaseChat Overview and Summary
The court examined the relevant statutory provisions and considered whether the certifier's actions fell short of the standard expected of professionals in the building industry. The court found that the certifier's failure to inspect the requirements of Bushfire Attack Level 29 constituted unsatisfactory conduct. The court noted that the certifier's conduct was not only a failure to meet a specific requirement but also a broader disregard for the professional standards expected in the industry. The court further held that the certifier's actions demonstrated a lack of diligence and attention to detail, which was inconsistent with the responsibilities of a certifier. Consequently, the court confirmed the original decision of the Queensland Building and Construction Commission.
The court also addressed the applicant's request for an extension of time to bring the review application. The court granted the extension, noting that there were extenuating circumstances that justified the delay. However, the court emphasised that the extension did not affect the merits of the case. The court dismissed the applicant's application for costs, finding that there were no grounds for awarding costs to the applicant. The decision of the Queensland Building and Construction Commission dated 9 January 2014 was confirmed, and the application for costs was dismissed.
Orders
Orders of the court
1. The decision of the Queensland Building and Construction Commission dated 9 January 2014 is confirmed.
2. The application for costs is dismissed.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.