Bridgeport Pty Ltd v Yelyruss Pty Ltd (in liq)

Link copied
Case Copied 10 min read

SUPREME COURT OF QUEENSLAND

CITATION: Bridgeport Pty Ltd v Yelyruss Pty Ltd (in liq) and Anor [2011] QSC 237
PARTIES: BRIDGEPORT PTY LTD ACN 076 392 900
(applicant)
v         
YELYRUSS PTY LTD ACN 101 056 946
(first respondent)       
BRANKO MICO
(second respondent)
FILE NO: BS 6571 of 2011
DIVISION: Trial
PROCEEDING: Applications
DELIVERED ON: 2 August 2011
DELIVERED AT: Brisbane
HEARING DATE: 2 August 2011
JUDGE: Fryberg J
ORDERS: Application is dismissed with costs.
CATCHWORDS:

Procedure – Supreme Court procedure – Queensland – Procedure under Uniform Civil Procedure Rules and predecessors – Other matters – application for leave to add contributor to notice of claim – factors considered – significant delay – prejudice – contribution would not be significant – leave not granted


Personal Injuries Proceedings Act 2002

Brisbane Southeast Regional Health Authority v Taylor [1996] HCA 25; (1996) 186 CLR 541
Interpacific Resorts (Australia) Pty Ltd v Austar Entertainment Pty Ltd and Ors [2004] QSC 427; [2005] 2 Qd R 23, applied

COUNSEL: A Harding for the applicant
R M Treston for the first respondent
M J Lazinski (solicitor) for the second respondent
SOLICITORS: Moray & Agnew Lawyers for the applicant
MinterEllison for the first respondent
QLD Law Group for the second respondent

HIS HONOUR: The substantive application before me is for leave to add a company as a contributor for the purposes of Part 1 of the Personal Injuries Proceedings Act 2002 in respect of a claim made by the second respondent to this present application, Mr Miosch, against the applicant, Bridgeport Constructions.

Because the proposed first respondent, Yelyruss Pty Ltd, is in liquidation, the application requires leave to commence and proceed.  Of course, the filing of the affidavit without having first got leave is a technical breach of the Act, but nobody has taken that point and I assume that leave can be given nunc pro tunc.

One of the major considerations in the grant of leave to commence the proceedings would be whether there is sufficient prospect of the substantive proceeding that is to be commenced, that is the application under paragraph 1, succeeding.  Bridgeport and Yelyruss are both insured and the litigation is being conducted by their insurers.

By way of background, Mr Miosch was a plasterer.  He was injured on the 19th of October 2005 when working as an independent contractor on a building site of a new house being built by Bridgeport.  He cut his leg on a piece of glass which was protruding from a wall where it had been left leaning.  The glass was apparently intended for windows in the house.  There was no warning of the presence of the glass and no signs or protective devices to ensure the safety of the people working on the site.  At the relevant time, the site was in the possession of Bridgeport.

Mr Miosch was not badly injured.  He sustained a serious cut to his leg and has apparently lost some two to four per cent of the function of the…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Bridgeport Pty Ltd v Yelyruss Pty Ltd (in liq) and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2011] QSC 237
Decision Date

CaseChat Overview and Summary

The case involved Bridgeport Pty Ltd, a creditor, and Yelyruss Pty Ltd, which was in liquidation. Bridgeport sought to add another creditor, who they claimed had a right to contribution, to the notice of claim after the limitation period had expired. The matter was heard in the Supreme Court of Queensland, which was asked to decide whether Bridgeport should be granted leave to add the contributor to the notice of claim, despite the delay and the potential prejudice to the liquidator.

The legal issues the court needed to address were whether the delay in adding the contributor was significant and whether this delay would prejudice the liquidator's ability to distribute the available assets among the creditors. Additionally, the court had to consider whether the contribution from the new creditor would be significant enough to warrant the amendment of the notice of claim. In its decision, the court emphasised the importance of the limitation period and the potential for prejudice to the existing creditors if the new creditor was added at this stage.

The court found that the delay in adding the new creditor was significant and that this delay would prejudice the liquidator's ability to distribute the available assets. The court also found that the contribution from the new creditor would not be significant enough to justify the amendment of the notice of claim. Consequently, the court dismissed Bridgeport's application for leave to add the contributor to the notice of claim and ordered that the application be dismissed with costs.

Orders

Orders of the court

Application is dismissed with costs.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established