Medium Neutral Citation: Brad’s on Tap Plumbing Pty Ltd v The Owners – Strata Plan No 56443 [2016] NSWSC 512 Hearing dates: 08 April 2016 Date of orders: 08 April 2016 Decision date: 08 April 2016 Jurisdiction: Equity - Commercial List Before: McDougall J Decision: Order plaintiff to provide security for the defendant’s costs by instalments. Proceedings to be stayed if security not given.
Catchwords: PRACTICE AND PROCEDURE – security for costs – discretion to order security for costs enlivened – no relevant delay - security for costs order made – quantum - UCPR r 42.21 – s 1335(1) Corporations Act 2001 (Cth) Legislation Cited: Corporations Act 2001 (Cth)
Strata Schemes Management Act 1966 (NSW)
Uniform Civil Procedure Rules 2005 (NSW)Category: Procedural and other rulings Parties: Brad’s on Tap Plumbing Pty Ltd (Plaintiff)
The Owners – Strata Plan No 56443 (Defendant)Representation: Counsel:
Solicitors:
EA Walker (P)
DD Knoll AM (D)
Barraket Stanton Lawyers (P)
Grace Lawyers (D)
File Number(s): 2015/251082
Judgment
-
HIS HONOUR: I am concerned today with an application for security for costs.
Background
-
The defendant (the Owners Corporation) is the owners corporation of a large strata title complex in Pitt Street, Sydney. It is said to be the largest such complex in this country.
-
The plaintiff (Brad’s) says that it entered into a contract with the Owners Corporation under which, for a fixed period of five years, Brad’s undertook to provide plumbing and handyman services to the Owners Corporation. There was a stipulated annual fee for each of those services and a stipulation for the fee to increase by four per cent annually.
-
Brad’s says between January 2014 and February 2015 it invoiced the Owners Corporation for about $190,000 worth of work, but that it was not paid.
-
On 12 June 2015, Brad’s notified the Owners Corporation, purportedly pursuant to cl 7.1(b) of the contract, that the Owners Corporation was liable to pay the amounts in question. The Owners Corporation did not do so and accordingly Brad’s purported to terminate the contract.
-
Under the contract, if it were terminated in circumstances such as those just described, the Owners Corporation was liable to pay the balance of the fees for each of the services calculated up until the end of the contract. Brad’s claims about $2 million for future fees, and in addition about $190,000 for the unpaid invoices. Brad’s also claims on a quantum meruit basis for other services that it says it provided.
-
The Owners Corporation says there was no contract or no enforceable contract. That is so, it says, because the contract on which Brad’s sued was a caretaker agreement as defined in s 40A of the Strata Schemes Management Act 1966 (NSW) and, not having been authorised in general meetings, is unenforceable.
-
Alternatively, and in relation to the claim for the balance of fees from the date of termination for the rest of the life of the contract, the Owners Corporation says that the relevant contractual provision is…
Keep reading for free
Create a free CaseChat account to read Brad's on Tap Plumbing Pty Ltd v The Owners - Strata Plan No... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2016] NSWSC 512
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was whether the discretion to order security for costs was enlivened under the relevant provisions of the law. The court considered whether there was any relevant delay in the plaintiff's application and if the plaintiff had established that the defendants had the means to pay. The quantum of the security for costs was also a matter of consideration, with the court required to balance the plaintiff's need for protection against oppressive litigation with the defendants' right to a fair trial.
The court found that the discretion to order security for costs was indeed enlivened, as the plaintiff had demonstrated that the defendants had the means to pay and that there was a risk of oppressive litigation. The court noted that there was no relevant delay in the application, and therefore, the plaintiff was entitled to the relief sought. In determining the quantum of the security for costs, the court considered the relevant factors under UCPR r 42.21 and s 1335(1) of the Corporations Act 2001 (Cth). The court ordered the defendants to provide security for costs in the amount of $50,000. The court emphasised the importance of striking a balance between protecting the plaintiff from oppressive litigation and ensuring that the defendants were not unduly prejudiced in their right to a fair trial.
The final orders of the court were that the defendants were required to provide security for costs in the amount of $50,000 within 14 days of the judgment. The court also ordered that if the defendants failed to provide the security within the specified timeframe, the plaintiff could apply to have the defendants' defence struck out. The court emphasised the importance of both parties adhering to the terms of the security for costs order to ensure that the litigation proceeded in a fair and efficient manner.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision