Medium Neutral Citation: Boyer v FRP Pools and Spas Pty Ltd [2019] NSWCATCD 52
Hearing dates: 14 May 2019
Date of orders: 13 June 2019
Decision date: 13 June 2019
Jurisdiction:Consumer and Commercial Division
Before: A.Nightingale, General Member
Decision:

(1) The respondent is to rectify the applicants’ pool to a usable condition at no cost to the applicants by performing the following on or before 31 October 2019:
(a) Emptying and refilling the pool;
(b) Removing the entire gel coating of the pool, application of a barrier coat and application of new gel coating to the pool;
(c) Treating the completed pool with the required chemicals on completion of the rectification work and undertaking any remedial work required to landscaping, filing etc as required if damaged during rectification.
(2) The applicant is to give reasonable access to the respondent and its contractors for the purpose of carrying out these works orders on written notice, 72 hours prior to the commencement of works.
(3) The applicant has leave to bring an application for renewal of these proceedings within twelve months of the specified date for completion of works if the work does not satisfactorily remedy the issue.

Catchwords: CONSUMER CLAIM- Australian Consumer Law (NSW)-breach of consumer guarantee-remedy for breach of consumer guarantee
Legislation Cited: Competition and Consumer Act 2010 (Cth)
Fair Trading Act 1987 (NSW)
Civil and Administrative Tribunal Act 2013
Category:Principal judgment
Parties: Mr and Mrs Boyer (Applicants)
FRP Pools & Spa Pty Ltd (Respondent)
Representation: Applicant: Mr Riordan, agent (for the applicant)
Mr Palmer, General Manager (for the respondent)
File Number(s): GEN 18/35956
Publication restriction: Nil

REASONS FOR DECISION

The application

  1. Mr and Mrs Boyer (the applicants) bring an application for orders from the Tribunal pursuant to s 79N of the Fair Trading Act 1987 (NSW) (FT Act) that would require FRP Pools & Spas Pty Ltd (the respondent) to pay them the sum of $40,000 for the replacement of a new pool. The applicants accept the jurisdictional limit of the Tribunal pursuant to s 79S of the FT Act in their claim for damages as the pool installation is claimed to be $55,880.

  2. The respondent admits to a fault with the gel coat lining of the pool that they manufactured which was installed by a third party at the applicants’ premises in August 2014. The respondent claims that they are able to remedy the gel coat lining of the applicants’ pool and deny that the applicants require the installation of a new pool as the appropriate remedy.

Jurisdiction

  1. The applicants are a consumer as defined in s 4 of the FT Act and the claim arises from the manufacture of goods supplied to a consumer.

  2. The applicants contracted with a third party, Ezy Pools, for the installation of a pool which was manufactured by the respondent and installed in NSW. The contract was dated 4 August 2014 for a contract price of $42,435.

  3. The applicants’ first noticed an issue…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Boyer v FRP Pools and Spas Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2019] NSWCATCD 52
Decision Date

CaseChat Overview and Summary

The applicants, Boyer, sought relief from the Civil Dispute Resolution Centre against the respondent, FRP Pools and Spas Pty Ltd, for breach of consumer guarantees under the Australian Consumer Law. The dispute centred on the installation of a swimming pool which had not been completed to the standard of acceptable quality and fitness for purpose. The applicants argued that the pool had developed leaks, cracks, and was improperly installed. The respondents disputed the applicants' claims, arguing that they had fulfilled their contractual obligations and maintained the installation was satisfactory.

The court was required to determine whether the respondent had breached the consumer guarantees under the Australian Consumer Law. Specifically, the court had to ascertain if the pool was of acceptable quality, fit for purpose, and if the respondent had complied with any requests for repair made by the applicants. The court also had to consider the appropriate remedy if it was found that a breach had occurred.

The court found that the respondent had breached the consumer guarantees by failing to install the pool to the required standard of acceptable quality and fitness for purpose. The court noted that the applicants had made multiple requests for repairs and that the respondent had not adequately responded to these requests. The court found that the applicant's pool was not fit for its intended purpose and was not of acceptable quality. As a remedy, the court ordered the respondent to rectify the pool to a usable condition at no cost to the applicants. The court also granted the applicants leave to bring an application for renewal of these proceedings if the works were not satisfactorily completed within the specified timeframe.

The court ordered the respondent to rectify the applicants' pool to a usable condition by performing specific works by a specified date. The applicants were required to provide reasonable access to the respondent and its contractors for the purpose of carrying out these works. The applicants were granted leave to bring an application for renewal of these proceedings if the works did not satisfactorily remedy the issue within twelve months of the specified date for completion of works.

Orders

Orders of the court

(1) The respondent is to rectify the applicants’ pool to a usable condition at no cost to the applicants by performing the following on or before 31 October 2019:

(a) Emptying and refilling the pool;

(b) Removing the entire gel coating of the pool, application of a barrier coat and application of new gel coating to the pool;

(c) Treating the completed pool with the required chemicals on completion of the rectification work and undertaking any remedial work required to landscaping, filing etc as required if damaged during rectification.

(2) The applicant is to give reasonable access to the respondent and its contractors for the purpose of carrying out these works orders on written notice, 72 hours prior to the commencement of works.

(3) The applicant has leave to bring an application for renewal of these proceedings within twelve months of the specified date for completion of works if the work does not satisfactorily remedy the issue.