Civil and Administrative Tribunal
New South Wales
- Amendment notes
Medium Neutral Citation: Bowman v Curtis [2022] NSWCATCD 125 Hearing dates: 19 May 2022 Date of orders: 3 August 2022 Decision date: 03 August 2022 Jurisdiction: Consumer and Commercial Division Before: D Moujalli, Senior Member Decision: The respondent must pay the applicant the sum of $26,490.89 within 21 days of the date of this order.
Catchwords: BUILDING AND CONSTRUCTION – Home Building Act 1989 (NSW) - defects in building work - whether a work or a money order should be made in respect of defects
Legislation Cited: Home Building Act 1989 (NSW)
Cases Cited: Kurmond Homes Pty Ltd v Marsden [2018] NSWCATAP 23
Category: Principal judgment Parties: Annette Bowman (Applicant)
Jai Curtis t/as Curtis Carpentry & Construction (Respondent)Representation: Applicant: self-represented
Respondent: self-represented
File Number(s): HB 22/10751 Publication restriction: Nil
REASONS FOR DECISION
Introduction
-
On 8 March 2022 the applicant, Annette Bowman, lodged an application with the Tribunal (the Application). The Application seeks an order for payment of money against the respondent in respect of defects in building works carried out by the respondent on the applicant’s residential premises.
-
The hearing was conducted on 19 May 2022.
-
At the hearing on 19 May 2022, each party was self-represented. The hearing proceeded by AVL.
-
At the hearing each party was given an opportunity to present their evidence, ask questions of the other party and make submissions. Both Ms Bowman and Mr Curtis did this in a respectful manner and the Tribunal is grateful for their co-operation in this respect.
Evidence
-
In determining the Application, the Tribunal has had regard to the following:
The material filed by the applicant on 12 April 2022. This was marked Ex A1 at the hearing on 19 May 2022.
The further material filed by the applicant on 11 May 2022. This was marked Ex A2 at the hearing on 19 May 2022.
The material filed by the respondent on 4 May 2022. This was marked Ex R1 at the hearing on 19 May 2022.
An expert’s report of Stephen Webster dated 18 May 2022 relied upon by the respondent. This was marked Ex R2 at the hearing on 19 May 2022.
-
The findings made by the Tribunal on the basis of the above evidence is set out below.
Jurisdiction
-
Section 48K (1) of the Home Building Act 1989 (NSW) (HBA) provides that the Tribunal has jurisdiction to hear and determine a building claim.
-
The Tribunal’s jurisdiction to determine a building claim is subject to whether certain time limits for the making of the claim are complied with.
-
Section 48K (7) of the HBA provides that the Tribunal does not have jurisdiction to determine any building claim for a breach of a statutory warranty if the claim is made after the period provided by section 18E for commencing such a proceeding.
-
The provisions of the section 18E (1) (a)…
Continue reading Bowman v Curtis
Sign in free to access the full text
- AGLC
- Bowman v Curtis [2022] NSWCATCD 125
- Case
- [2022] NSWCATCD 125
- Decision Date
CaseChat Overview and Summary
The tribunal found that the defects identified could not be remedied and that a money order was appropriate. The tribunal noted that the Home Building Act 1989 (NSW) allows for a money order to be made in lieu of a work order if the defects cannot be remedied. The tribunal also noted that the amount of the money order should reflect the cost of remedying the defects. The tribunal ordered Curtis to pay Bowman the sum of $26,490.89 within 21 days of the date of the order.
Orders
Orders of the court
The respondent must pay the applicant the sum of $26,490.89 within 21 days of the date of this order.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.