Bowen Basin Coal Pty Ltd v Namrog Investments Pty Ltd

Case

[2020] QLC 23

17 June 2020

No judgment structure available for this case.

LAND COURT OF QUEENSLAND

CITATION:  Bowen Basin Coal Pty Ltd v Namrog Investments Pty Ltd
[2020] QLC 23
PARTIES:  Bowen Basin Coal Pty Ltd
(applicant)
v
Namrog Investments Pty Ltd
(respondent)
FILE NO:  CPA202-18
DIVISION:  General Division
PROCEEDING:  Application to decide a dispute under the Mineral and Energy
Resources (Common Provisions) Act 2014
DELIVERED ON:  17 June 2020
DELIVERED AT:  Brisbane
HEARD ON:  20 April 2020
HEARD AT:  Brisbane
MEMBER:  JR McNamara

ORDERS: 

1. 

I determine compensation in respect of MDL429 and MDL3001 in the sum of One Hundred and Seven Thousand, Three Hundred Dollars ($107,300).

2. 

The parties will be heard in relation to any application for determination of outstanding issues pursuant to section 96 of the Mineral and Energy Resources (Common Provisions) Act 2014. A request for such a hearing must be made no later than 15 business days after the delivery of these reasons.

CATCHWORDS: 

STATUTES – ACTS OF PARLIAMENT – INTERPRETATION – GENERAL APPROACHES TO INTERPRETATION – whether the pre-amended Mineral

and Energy Resources (Common Provisions) Act 2014
applies – whether, if the pre-amended Act does apply, the
Land Court has jurisdiction to decide issues in dispute other
than compensation – where the parties referred the whole
dispute to the Court

PROCEDURE – CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS – SEPARATE DECISION OR DETERMINATION OF QUESTIONS – where the Court was asked to determine compensation – where the parties

would bring outstanding issues before the court at a later date

ENERGY AND RESOURCES – MINERALS – MINING FOR MINERALS – COMPENSATION – available mapping

datasets - where agronomy experts disagreed on accuracy of

available land type mapping data – where agronomy experts disagreed on land type composition of affected paddock –

where available mapping data was accepted
Mineral and Energy Resources (Common Provisions) Act
2014 s 15A, s 81, s 83, s 96(2)
Acts Interpretation Act 1954 s 20
MRV Metals Pty Ltd v Chief Executive, Department of
Environment and Science [2020] QLC 9

APPEARANCES: 

EJ Morzone (instructed by Emanate Legal) for the applicant N Loos (instructed by Colin Biggers and Paisley Lawyers)

for the respondent

The legislative scheme

[1]      Under the Mineral and Energy Resources (Common Provisions) Act 2014

(MERCPA), before a resource company can enter private land to carry out advanced

activities[1] pursuant to a mineral development licence, they generally must have a legally binding agreement with the landholder. This can be either a conduct and

compensation agreement (CCA),[2] a deferral agreement, or an opt-out agreement.[3]

[1]            Advanced activity is defined at s 15A of the MERCPA as activities that have more than a minor impact on the landholder's land use activities or business activities. They can include:

[2]            Conduct and compensation agreement is defined at s 83 of the MERCPA.

[3]            Landholders can agree to delay making a conduct and compensation agreement until after the land has been accessed under MERCPA s 44 (deferral agreement) or opt-out of negotiating a conduct and compensation agreement under MERCPA s 45(2) (opt-out agreement).

[2]      A CCA sets out the activities or conduct proposed to be undertaken as well as

compensation arrangements for any impacts.[4]

[4] Mineral and Energy Resources (Common Provisions) Regulation 2016 pt 5.

[3]      A resource authority holder may give an eligible claimant a notice that they wish to

negotiate a CCA.[5]

[5]            MERCPA s 84.

[4]      In those circumstances the parties must use reasonable endeavours to negotiate a CCA

during the prescribed period, but if no agreement is reached either party may give an

ADR election notice.[6]

[6]            MERCPA s 88.

This case

[5]      The applicant, Bowen Basin Coal Pty Ltd (Bowen Basin Coal) holds MDL429 and

MDL3001 (the MDLs), which affect a cattle property known as Vermont Park at

Dysart owned by the respondent, Namrog Investments Pty Ltd (Namrog).

[6]      The proposed activity comprises 35 exploration core drill holes, three seismic drill

holes, about 12 kilometres of seismic line, seven point of access tracks, 15 kilometres

of access along existing roads and two kilometres of access along the seismic lines.[7]

[7]            T 1-4, lines 35 to 38.

[7]      In this case an ADR election notice was given on 8 March 2018 and mediation

occurred on 13 April 2018, however a CCA was not agreed, and the applicant filed

an application in the Land Court on 24 May 2018 pursuant to MERCPA s 96(2).

Neither a deferral agreement nor an opt-out agreement was pursued in this matter.

Jurisdiction

[8]      Since the filing of the application, the provisions of the MERCPA which concern the

jurisdiction of the Land Court were amended, including s 96(2).

[9]      The scheme of the MERCPA as amended now requires the parties to engage in non-

binding ADR prior to the making of an application to the Court. That occurred in any

case. The pre-amended s 96(2) allowed an application to be brought in the alternative,

that is, for the Court to decide compensation, or future compensation, or matters

concerning entry and conduct. The amended s 96(2) simply provides that either party

may apply to the Land Court to decide the dispute.[8]

[8]            A dispute might relate to all or any of the s 83 matters – entry conditions, conduct and/or

[10]      Consistent with the findings of Kingham P in MRV Metals Pty Ltd v Chief Executive,

Department of Environment and Science,[9] generally, the amendment of an Act does

not affect anything begun under the Act or a right acquired under the Act. The remedy

can be started, continued, or completed, as if the amendment had not happened.[10]

There is no contrary intention expressed in the amending Act.[11]

[9] [2020] QLC 9 at [20].

[10] Section 20(2) of the Acts Interpretation Act 1954 provides that the repeal or amendment of an Act

[11] Natural Resources and Other Legislation Amendment Act 2019.

[11]      The originating application asks the Court to decide the applicant’s compensation

liability or future compensation liability only. The alternative versions of the draft

CCA found in the hearing materials disclose there are more matters in dispute than

compensation.[12]

[12]           Ex 1, tab 7; Ex 1, tab 8.

[12]      Had the application been brought after the Act was amended it would seem that the

task for the court would be to ‘decide the dispute’ – presumably outstanding issues

between the parties relevant to the CCA. However, the pre-amended Act gave the

applicant the option to seek a decision regarding any (or all) of the issues in dispute

being compensation, future compensation and access/conduct arrangements.

[13]      While the originating application was specific to compensation, as discussed below,

the subject matter broadened.

Issues unresolved

[14]      Orders made 13 March 2020 required the parties to provide, amongst other things, a

list of issues and a list of matters not in dispute. The document filed by the parties is

headed ‘List of Issues in Dispute/List of Matters not in Dispute’.[13]

[13]           List of Issues in Dispute/List of Matters not in Dispute, provided 17 April 2020.

[15]      The matters in dispute are identified under sub-headings ‘issues of fact in dispute’

and ‘issues of law in dispute’. The issues of fact relate to the bases and assessment of

compensation. The issues of law are expressed as follows:

6.     The terms of the conduct and compensation agreement to be entered into by the parties; and

7. The compensation payable by the Applicant to the Respondent as required under section 81(1)(a)(i) (sic) of the Mineral and Energy Resources (Common Provisions) Act 2014 (Qld).

[16]      In opening submissions, Mr Loos noted that the hearing materials included an original

version and a marked up version of the CCA, and said that whether the differences in

those two documents are resolved in this decision is a matter for the court, but also

noted that it may be that the determination of the compensatable effect of the

deprivation of possession of the land surface might adjust the parties’ approaches to

how the CCA might be drafted.[14] The substance of the CCA, other than compensation,

was not significantly discussed in the hearing. In closing submissions it was

acknowledged that a number of the issues were conceded or resolved and a process

for determining issues regarding the CCA dispute could be included in orders made

at the time of delivering judgment on compensation. That is the way I intend to

proceed.

[14]           T 1-15, lines 6 to 11.

Compensation

[17]      The parties were unable to agree on compensation for the advanced activities on

MDL429 and MDL3001.

[18]      As noted, attempts had been made to resolve the compensation issue in mediation

prior to the application to the Court.

[19]      The parties sought to rely on expert evidence of valuers and agronomists. The

respondent engaged agronomist Mr William Thompson and valuer Mr William

McLay, while the applicant engaged agronomist Mr Jim Brennan and valuer Mr Chris

Caleo.

[20]      After the application was made, the Court Managed Expert Evidence (CMEE)

process was used to develop joint expert reports (JERs) by the expert agronomists

and valuers.[15] Mr Thompson and Mr Brennan produced an agronomists’ JER dated

31 May 2019 (Initial Agronomists’ JER)[16] and an agronomists’ supplementary JER

dated 20 December 2019 (Supplementary Agronomists’ JER).[17] Mr Caleo and Mr

McLay produced a valuation JER dated 5 July 2019 (Initial Valuation JER)[18] and a

supplementary valuation JER dated 20 March 2020 (Supplementary Valuation

JER).[19]

[15]           The CMEE process is a method where the Court supervises the briefing and meeting of expert witnesses and production of their joint expert report. See Practice Direction No 3 of 2018 - Procedure for Court Managed Expert Evidence, 30 April 2018.

[16]           Ex 1, tab 3.

[17]           Ex 1, tab 5.

[18]           Ex 1, tab 4.

[19]           Ex 1, tab 6.

[21]      The qualifications and experience of Mr Thompson and Mr Brennan is outlined in

their respective curricula vitae.[20] Their expertise was not challenged. In my view both

are suitably experienced to provide expert evidence in this matter. At the hearing

conducted on 20 April 2020 they gave evidence in concurrent session.

[20]           Ex 1, tab 9; Ex 1, tab 10.

[22]      Facts concerning the work program were not in dispute. Where and when advanced

activities are to occur was agreed.

Components of compensation

[23]      The assessment of compensation in this case is a mathematical exercise. It is the

values ascribed to certain variables that are in dispute. Those variables are the

stocking rate or carrying capacity, the average daily weight gain, and the average

annual operating cost. This results in a difference of opinion concerning the gross

value of production loss and opportunity cost – which are agreed components of

compensation in this matter. The quantum of the other components (fencing,

labour/stock management, managers time, and cost, damage or loss), were agreed.

[24]      The valuers reached agreed values of compensation for the alternative assessments of

production loss by each agronomist. At the commencement of the hearing there were

three scenarios referred to in the hearing material and presented for consideration.[21]

At the hearing in closing submissions the third scenario was abandoned.[22] The two

remaining scenarios reflect the values ascribed to the variables by the expert

agronomists as seen in the following table titled “Table 6 – Summary of Impacts”

found in the Agronomists’ Supplementary JER:[23]

[21]           Ex 1.

[22]           T 1-81, line 43 to line 46; T 1-82 line 1 to line 2.

[23]           Ex 1, tab 5, page 255 (first three columns shown only).

JB Assessment BT Assessment
Productivity $29,536 $49,469
Fencing $15,000 $15,000
Labour/Stock Management $1,250 $1,250
Managers Time $8,250 $8,250
Opportunity Cost $20,138 $45,625
Total $74,174 $119,594

[25]      It was also agreed at the hearing that the assessment of cost, damage and loss,

regardless of scenario, of $15,750 in the Supplementary Valuation JER was accepted

by both parties.[24]

[24]           T 1-14, line 24 to line 28; T 1-14 line 40; Ex 1, tab 6.

Variables affecting productivity and opportunity cost

Stocking rate or carrying capacity

[26]      The advanced activities are located across five paddocks,[25] however they will be

carried out principally in the two paddocks known respectively as Tree Pine and Paper

Gum. The following figure was included in the hearing materials as “Figure 1 –

Vermont Park Property Plan".[26]

[25]           Vermont Park consists of 24 paddocks in total.

[26]           Ex 1, tab 5, page 257.

[27]      Stocking rate or carrying capacity is determined in relation to land type. The

following table appeared as “Table 1 - Assessment of Carrying Capacity for all of

Vermont Park” in the Supplementary Agronomists’ JER.[27] The table provides a

[27]           Ex 1, tab 5, page 242.

breakdown of Vermont Park by land type in order of dominance, and the estimated

area occupied by each land type both as a number of hectares and as a percentage of

the total area. The information relates to the whole property rather than individual

paddocks.

Table 1 Assessment of Carrying Capacity for all of Vermont Park

Ha Acres Ha/AE CC

Land

Type Total Area 16,669 41,189 AE Rate Breeder
7 Poplar box with ironbark 6,866 41.2% 16,966 16.19 424
2 Box flats 4,970 29.8% 12,281 8.09 614
6 Brigalow with melonholes 3,889 23.3% 9,610 3.24 1,201
4 Coolibah floodplains 439 2.6% 1,085 4.05 108
1 Alluvial brigalow 238 1.4% 588 3.24 74
3 Blue gum/river red gum flats 121 0.7% 299 3.64 33
Brigalow with blackbutt
5 (Dawson gum) 105 0.6% 259 3.64 29
16,628 41,088 6.71 2,483 1.35 1,840
Variance -41 -0.25% -101
Notes:- 1. Land type & areas as per DNR Forage Report: Indicate Land Type
2. As aerial maps inconclusive, CC rates assumes most of the land suitable for development (pulling & pasture establishment) has been
developed
3. Rate is the conversion rate from AE (Adult Equivalent) to a Breeder Equivalent
Breeders AE Conversion AE

Paddock data set[28] and the DNR Queensland Globe, which shows paddocks affected

by the activities.[29]

[28]           Ex 1, tab 5, page 259.

[29]           Ex 1, tab 5, page 260.

[32]      A site inspection was also conducted by the expert agronomists who traversed the

track abutting the fence line between the two most affected paddocks and observed

the landscape from that position in either direction. Mr Thompson in evidence said

that he and Mr Brennan were able to inspect approximately 15% of the impacted

area.[30] In the course of the inspection the agronomists also spoke with the property

manager.

[30]           T 1-23, line 15 to line 16; T 1-27 line 11.

[33]      The agronomists’ conclusions differed and both accept the data is not perfect. Mr

Thompson said that it is useful at a whole of property level, but not necessarily at the

paddock level.[31]

[31]           T 1-23, lines 10 to 20.

Affected paddocks

[34]      Advanced activities will have a small impact on three paddocks which can be

managed and rehabilitated with exclusion fencing, but the majority of the area

affected lies in just two paddocks – Tree Pine and Paper Gum. According to the

Supplementary Agronomists’ JER these two paddocks have 28 of the 35 drill sites

and are transected by seismic lines.[32] While the cattle could remain in these paddocks

during drilling (provided the work sites are properly fenced off), grazing and

management of the paddocks during rehabilitation periods is impractical. At

completion of the drilling program the paddocks will be destocked, drill sites and

other disturbed areas reseeded, so that the areas can be returned to pre-disturbance

condition within three years.

[32]           Ex 1, tab 5, page 240.

[35]      The task for the expert agronomists was to determine the carrying capacity loss on

each of the affected paddocks expressed in AE. Each expert agronomist completed a

table setting out productivity losses on each affected paddock – Table 2JB[33] and Table

[33]           Ex 1, tab 5, page 246.

2BT.[34] The tables are reproduced below:

[34]           Ex 1, tab 5, page 248.

Table 2JB Productivity Losses JB

Productivity Losses with Updated Mapping

Paddock CC Loss - % of Year Not Grazed

Tree Pine (100% affected)

Land Affected AE CC Drill Total AE Total Kg
Type Ha Ha/AE Loss Sites Yr 1 Yr 2 Yr 3 CC Loss ADWG Loss $/Kg Total Loss
7 560.92 16.19 35 50% 50% 35 0.3 3,794
2 34.87 8.09 4 50% 50% 4 0.3 472
Undeveloped 6 166.33 16.19 10 50% 50% 10 0.3 1,125
762.12 15.48 49 18 49.2 5,391 $ 2.70 $ 14,555

Paper Gum (100% affected)

Land Affected AE CC Drill Total AE Total Kg
Type Ha Ha/AE Loss Sites Yr 1 Yr 2 Yr 3 CC Loss ADWG Loss $/Kg Total Loss
7 626.42 16.19 39 50% 50% 39 0.3 4,237
2 0 8.09 - 50% 50% - -
Undeveloped 6 0 16.19 - 50% 50% - 0.3 -
626.42 16.19 39 10 38.7 4,237 $ 2.70 $ 11,439

Bottom Cherwell (affected area only)

Land Affected AE CC Drill Total AE Total Kg
Type Ha Ha/AE Loss Sites Yr 1 Yr 2 Yr 3 CC Loss ADWG Loss $/Kg Total Loss
7 122 16.19 8 50% 50% 8 0.3 825
2 0 8.09 - 50% 50% - -
Undeveloped 6 0 16.19 - 50% 50% - -
122 16.19 8 6 7.5 825 $ 2.70 $ 2,228

Zarbs Paddock (affected area only)

Land Affected AE CC Drill Total AE Total Kg
Type Ha Ha/AE Loss Sites Yr 1 Yr 2 Yr 3 CC Loss ADWG Loss $/Kg Total Loss
7 0 16.19 - 50% 50% - -
2 0 8.09 - 50% 50% - -
Developed 6 4.5 3.24 1 50% 50% 1.4 0.6 304
Undeveloped 6 1 16.19 0 50% 50% 0 0.3 152
4.5 3.10 1 0 1.5 456 $ 2.70 $ 1,232

Middle Cherwell (Affected area only)

Land Affected AE CC Drill Total AE Total Kg
Type Ha Ha/AE Loss Sites Yr 1 Yr 2 Yr 3 CC Loss ADWG Loss $/Kg Total Loss
7 16.19 - 50% 50% - -
Developed 2 2.25 8.09 0.3 50% 50% 0 0.3 30
6 0 16.19 - 50% 50% - -
2.25 8.09 0 1 0.3 30 $ 2.70 $ 82

Summary

Affected AE CC Drill Total AE Total Kg
Ha Ha/AE Loss Sites Yr 1 Yr 2 Yr 3 CC Loss ADWG Loss $/Kg Total Loss
1517 15.6 97 50% 50%
1517 15.6 35 97 0.31 10,939 $ 2.70 $ 29,536

Table 2BT Productivity Losses BT

Productivity Losses with Updated Mapping

Paddock CC Loss - % of Year Not Grazed

Tree Pine (100% affected)

Land Affected AE CC Drill Total AE Total Kg
Type Ha Ha/AE Loss Sites Yr 1 Yr 2 Yr 3 CC Loss ADWG Loss $/Kg Total Loss
7 560.92 12.14 46 50% 50% 46 0.4 6,746
2 34.87 8.09 4 50% 50% 4 0.4 629
Undeveloped 6 166.33 16.19 10 50% 50% 10 0.4 1,500
762.12 12.54 61 18 60.8 8,875 $ 2.70 $ 23,963

Paper Gum (100% affected)

Land Affected AE CC Drill Total AE Total Kg
Type Ha Ha/AE Loss Sites Yr 1 Yr 2 Yr 3 CC Loss ADWG Loss $/Kg Total Loss
7 626.42 12.14 52 50% 50% 52 0.4 7,534
2 0 8.09 - 50% 50% - -
Undeveloped 6 0 16.19 - 50% 50% - 0.3 -
626.42 12.14 52 10 51.6 7,534 $ 2.70 $ 20,341

Bottom Cherwell (affected area only)

Land Affected AE CC Drill Total AE Total Kg
Type Ha Ha/AE Loss Sites Yr 1 Yr 2 Yr 3 CC Loss ADWG Loss $/Kg Total Loss
7 122 12.14 10 50% 50% 10 0.4 1,467
2 0 8.09 - 50% 50% - -
Undeveloped 6 0 16.19 - 50% 50% - -
122 12.14 10 6 10.0 1,467 $ 2.70 $ 3,961

Zarbs Paddock (affected area only)

Land Affected AE CC Drill Total AE Total Kg
Type Ha Ha/AE Loss Sites Yr 1 Yr 2 Yr 3 CC Loss ADWG Loss $/Kg Total Loss
7 0 12.14 - 50% 50% - -
2 0 8.09 - 50% 50% - -
Developed 6 4.5 3.24 1 50% 50% 1.4 0.4 203
Undeveloped 6 1 16.19 0 50% 50% 0 0.4 203
4.5 3.10 1 0 1.5 406 $ 2.70 $ 1,095

Middle Cherwell (Affected area only)

Land Affected AE CC Drill Total AE Total Kg
Type Ha Ha/AE Loss Sites Yr 1 Yr 2 Yr 3 CC Loss ADWG Loss $/Kg Total Loss
7 16.19 - 50% 50% - -
2 2.25 8.09 0.3 50% 50% 0 0.4 41
Developed 6 0 16.19 - 50% 50% - -
2.25 8.09 0 1 0.3 41 $ 2.70 $ 110

Summary

Affected AE CC Drill Total AE Total Kg
Ha Ha/AE Loss Sites Yr 1 Yr 2 Yr 3 CC Loss ADWG Loss $/Kg Total Loss
1517 12.2 124 50% 50%
1517 12.2 35 124 0.40 18,322 $ 2.70 $ 49,469

[36]      In both tables, for each of the five paddocks, the land type per hectare information is

identical. Only three land types, 7, 2 and 6, are identified for the five paddocks.

[37]      In both tables, for land types 2 and 6, the Ha/AE figure and the AE (carrying capacity)

loss is identical. For land type 2 the Ha/AE figure is 8.09, which is the figure

contained in Table 1.[35] For land type 6 both tables record the Ha/AE figure as 16.19

(whereas Table 1 indicates for land type 6 a Ha/AE of 3.24). A note beside land type

6 in the agronomists’ tables says ‘Undeveloped’. This is explained in the JER that the

land type 6 on Vermont Park is “undeveloped Brigalow” and has a very low carrying

capacity, “similar or less than land type 7 … i.e. 16.19 Ha/AE”.[36]

[35]           Ex 1, tab 5, page 242.

[36]           I would observe that the agreed adjustment by the agronomists to the DNR Forage Report assessment of Ha/AE for land type 6 on Vermont Park based on other mapping and on a site inspection would suggest that the figures are not necessarily fixed.

[38]      However, for land type 7, in relation to the affected paddocks, as between the experts

the Ha/AE figures differ.[37]

[37]           I note that in Table 2BT in relation to Middle Cherwell the figure of 16.19 Ha/AE is recorded. In evidence Mr Thompson confirmed that the figure should be 12.14. Regardless it made no difference

[39]      Mr Brennan adopted the Ha/AE figure of 16.19 which appears in Table 1 above. Mr

Thompson adopted a figure of 12.14. The reasons for Mr Thompson’s difference are

explained below. The cumulative loss in carrying capacity based on Mr Brennan’s

calculation is 97 AE, and on Mr Thompson’s calculation 124 AE.

The difference in Ha/AE

[40]      Mr Thompson expressed his view that broadscale data cannot be relied on at paddock

level. In his view the Long Paddock mapping actually suggested ratios on the affected

paddocks as broadly similar to that of the overall property (6.71 Ha/AE). However,

based on the field inspection of the affected paddocks he considered this an

overestimate and thought a more appropriate figure for the land type 7 area, given the

range in soils and land units would be mid-way between the carrying capacity of land

type 7 and land type 2, which he averaged as 12.14 ha/AE. He confirmed in evidence

and based on the site inspection (what appears in his observations in the

Supplementary Agronomists’ JER) that land type 2 soils were “were observed

throughout the area and intermixed with land type 7”. He noted in the Supplementary

Agronomists’ JER that land type 6 “is also mapped in the paddocks”.

[41]      Mr Brennan took a more clinical approach. He overlaid the activities on the

Queensland Globe Land Type Map, which was considered more accurate than the

mapping used in the Initial Agronomists’ JER. In the Supplementary Agronomists’

JER and in evidence he expressed the view that the land types depicted on the Long

Paddock mapping confirmed noted observations regarding the extent of impact on the

five paddocks and the approximate breakdown (percentage and area) by land type.[38]

[38]           T 1-28, lines 32 to 39.

[42]      Mr Brennan maintained that he did not agree that averaging should be applied.

[43]      The Land Type Mapping was accepted at face value in constructing Tables 2JB and

2BT. Both Mr Thompson and Mr Brennan agreed, for example, that Tree Pine

included 560.92 hectares of land type 7, 34.87 hectares of land type 2, and 166.33

hectares of (undeveloped) land type 6.

[44]      In evidence Mr Thompson said that:

“The reality of this land type mapping is that it’s pretty crude. It’s useful at

arguably the whole of a very large property, but it’s not necessarily an

accurate indicator or predictor of what you will get in an individual

paddock.”[39]

[39]           T 1-23, lines 18 to 20.

[45]      Mr Thompson continued:

“There are a number of other resources that you can assess to determine

whether the mapping as used to compile table 1 was a reasonable predictor of what you could find on the ground. One of those is what you visually see when you drive through those paddocks. The other ones are looking in detail at some of the satellite imagery. And the other one is looking at the other

independent data sets … which is the CSIRO soils and land resource

mapping …”[40]

[40]           T 1-23, lines 45 to 47; T 1-24 lines 1 to 3.

[46]      Mr Thompson said that these other datasets indicate a significant percentage “of what

could loosely be called land type 2, which is the box flats, scattered throughout – or

soil similar to that scattered throughout that nominal land type 7 area”.[41]

[41]           T 1-24, lines 3 to 6.

[47]      Accordingly, it is asserted by Mr Thompson that the agreed area of land type 7 on the

affected paddocks was in fact not purely land type 7 (although still described as such),

but was collocated or intermixed with land type 2, which would require its own

Ha/AE score - although the agreed area of land type 2 remains.

[48]      I accept that the experts did not accept at face value the Ha/AE score for land type 6

because it was undeveloped – but not because it was not land type 6.

[49]      Both experts took away different conclusions from the site inspection. Mr Thompson

observations are noted above. Mr Brennan however said he came away from the

inspection feeling the mapping was “quite a good indicator”; that he felt “at ease with

Table 1”; and that he “thought it aligned very well”.[42] Mr Brennan says he questioned

the manager “about the country and the land and how they ran the place, and I

questioned him extensively”.[43] Mr Brennan said in evidence:

“… basically, there are two paddocks that comprise 92 per cent of the area

that is being affected by the mining activity so tree pine and paper gum, those two paddocks cover 92 per cent of the affected area, and of that 86 per cent is land type 7, which has the lowest carrying capacity on our assessment, and undeveloped land type 6 is 12 per cent, and it is undeveloped land type 6

which is regulated scrub. When it’s undeveloped … it has a similar carrying

capacity to land type 7. And my point was that there is 98 per cent of the 92

per cent, that is the lowest carrying capacity land type.”[44]

[42]           T 1-28, lines 1 to 29.

[43]           T 1-29, lines 28 to 29.

[44]           T 1-29, lines 12 to 22.

[50]      In closing submissions Mr Morzone accepted that any land type category is going to

contain a mix of land types but said it is the dominant land type which is agreed for

the purpose of determining carrying capacity. He said that if the land type information

is used for determining affected areas but not for determining carrying capacity,

adjustments to carrying capacity would need to be balanced over other land types –

which potentially make adjustments arbitrary.

[51]      I accept the position advocated by Mr Morzone in this regard. In my view had Mr

Thompson re-classified land type 7 on the affected paddocks as a hybrid, or had the

ratio of land type 7 and land type 2 been adjusted to reflect his observations, his table

would in my view have greater strength. I accept that broadscale data is indicative

and is only as good as the quality of the inputs – but if it is accepted for some purposes

and not others the conclusions become little more than a ‘guesstimate’. Averaging

seems convenient – but perhaps simplistic. The intermixing of land types (as opposed

to more discrete areas) could have other consequences which have a bearing on the

carrying capacity – although there is no evidence regarding this. If there was in fact

a greater area of type 2 land, then it should have been quantified.

[52]      In my view the stocking rate or carrying capacity outlined in Mr Brennan’s table 2JB

is to be preferred. This results in acceptance of the figure of 15.6 Ha/AE over the

affected area of 1,517 hectares and an AE loss of 97.

Average daily weight gain

[53]      The monetary figure of total loss in productivity is reached by multiplying the AE

loss by the daily weight gain (ADWG), by the number of days in a year, by the per

kilogram value, which is agreed to be $2.70. This is set out below:

Total productivity loss = total CC loss × (average daily weight gain × 365 days) × cost per kilogram

[54]      Mr Thompson contends the ADWG to be 0.4, Mr Brennan contends it to be 0.31.

[55]      In the Initial Agronomists’ JER it says: “The estimated liveweight gain (LWG) from

this class of grazing land assuming minimal supplementation is 0.4 kg/AE/year (sic)

or 146 kg/AE/year …”.[45]

[45]           Ex 1, tab 3, page 226, line 211.

[56]      A 2017 report authored by M. K. Bowen and F. Chudleigh (the Bowen and Chudleigh

report)[46] was tendered during the hearing although the only parts of the report referred

[46]           Ex 2.

to specifically were Table 17[47] and Table 23.[48] In the Supplementary Agronomists’

JER, in response to the use by Mr Brennan of the “liveweight gain figure of 0.31

kg/day” in table 2JB, Mr Thompson notes that it is less than the figure adopted in the

Initial Agronomists’ JER. He says: “Recent research modelling of herd performance

in the Central Queensland and Bowen districts indicates that the figure of 0.4 is of

itself at the lower end of what could be anticipated for weaner cattle.”[49] He notes that

Table 17 in the Bowen and Chudleigh report shows an overall annual daily gain of

0.49 kg per day. In evidence Mr Thompson said the data is “based on real herd,

commercial scale herd … monitoring”[50] – that is, real reference data from commercial

herds as opposed to modelling.[51]

[47]           Ex 2, page 79.

[48]           Ex 2, page 83.

[49]           Ex 1, tab 3, page 226, line 211.

[50]           T 1-42, lines 22 to 24.

[51]           T 1-42, line 35.

[57]      Mr Brennan, in response to Mr Thompson’s assessment in the Supplementary

Agronomists’ JER, says that he accepted the figure of 0.4 in the Initial Agronomists’

JER as a compromise, but no accommodation had then been made for opportunity

cost. In the Supplementary Agronomists’ JER, opportunity cost is included. Mr

Brennan considered that the Bowen and Chudleigh report concerned two enterprises

on “brigalow softwood scrub country near Rolleston”, which he says is regarded as

some of the best country in central Queensland. He says that based on his professional

experience he is firmly of the view that 0.3 for land type 7 is a realistic ADWG for

the affected area.

[58]      It is not clear how comparable Vermont Park is to the two enterprises the subject of

the report, however, the report says: “The modelled enterprises were situated centrally

in the Fitzroy Natural Resource Management region in central Queensland, near

Rolleston, with the predominant land type used for growing and finishing cattle

considered to be Brigalow softwood scrub.” The report states further that the land

type constitutes the largest land type area within the Fitzroy NRM area, being 1.5

million hectares and 9.7% of the entire area,[52] and that the majority of this land type

has been cleared and developed to sown pasture with buffel the predominant

species.[53] Mr Brennan in evidence said that the two properties are “premium

country”.[54]

[52]           Ex 2, page 10, para 2.2.1.

[53]           Ex 2, page 10.

[54]           T 1-44, line 43.

[59]      The land types in the affected paddocks are as described in Tables 2BT and 2JB. I

note that in Table 1, “Brigalow with melonholes” is defined as land type 6, and

“Brigalow with blackbutt (Dawson gum)” is defined as land type 5. According to

Tables 2BT and 2JB some undeveloped land type 6 (166.33 hectares) is agreed to

exist in Tree Pine.

[60]      In evidence, Mr Thompson explained that live weight gain comes from weaners – the

weight of cows does not change year on year. He calculated that a figure of 0.31

would translate to about 131 kilograms live weight which he considered a “very, very,

very low weight weaner”.[55] He said that his figure of 0.4 means a live weight of about

195 kg, which is at the bottom end of what would be an acceptable sale.[56] He said his

figure of 0.4 matches what you would expect from a good sustainable operation. Mr Thompson said that he believed the relevant paddocks could support a 0.4 average

daily weight gain.

[55]           T 1-44, lines 2 to 8.

[56]           T 1-44, lines 11 to 13.

[61]      Mr Brennan said that the basis of calculations had been AE such that “it was not

consistent to use weaner weight”,[57] which introduces a range of other variables.

[57]           T 1-44, line 35.

[62]      Both experts were forceful in their arguments to support their assessment of ADWG.

In the circumstances I accept the conclusion of Mr Thompson. As noted in closing

submissions from Mr Loos, Mr Thompson drew his conclusion from the Bowen and

Chudleigh report, aware of factors which would cause him to moderate the factor to

be applied, and adjusting to what he described as the lower end of the scale what is

in fact a figure beneath the scale referred to in that report. I accept the data in that

report is drawn from monitoring rather than modelling which lends it more credence.

I accept there is some lack of precision, but I have also take into account the lower

carrying capacity I have accepted which in theory would render a higher ADWG more

likely.

[63]      I accept the ADWG of 0.4 kg/day. Accordingly, productivity loss for the whole of

Vermont Park is calculated as below:

productivity loss = 97 × (0.4 × 365) × 2.70

[64]      The total productivity loss is $38,237.

[65]      My calculation is on the basis that total loss is the $/kg figure multiplied by the total

kilogram loss figure. Total kilogram loss is calculated by multiplying the AE loss by

ADWG by the number of days in a year.

[66]      In relation to calculating the total kilogram loss, I note that the summary tables 2BT

and 2JB, in a straight calculation, do not deliver their respective calculated total losses

precisely. Those tables contain a variance which is not explained. In both cases the

figure in 2JB and 2BT is slightly below the straight calculation. My conclusion is

based on a straight calculation based on the AE loss and ADWG as determined in this

decision.

Average Annual Operating Costs

[67]      The opportunity cost is the value of the productive loss less the cost of production.

Opportunity cost is calculated by subtracting expenses and freight and selling costs

from the productivity loss, which is the potential income. Expenses are calculated by

multiplying the number of AE by the number of years by the average annual operating

cost. This is set out below:

opportunity cost = productivity loss − freight and selling costs − expenses

[68]      The main variable in dispute however is the average annual operating cost. Mr

Brennan adopted a figure of $60/AE/year. Mr Thompson adopted a figure of

$15.50/AE/year.

[69]      In closing submissions Mr Loos said that, understanding that Mr Brennan did not

contend for a figure higher than $60 per AE/year, it was accepted by Mr Thompson.

[70]      I accept the figure of $60/AE/year. Over two years, productivity loss is 97 AE which

is 49 AE per year when rounded. I accept the figure of $3,544 as freight and selling

cost. The opportunity cost is therefore $28,813, as set out in the table below:

Potential Income $38,237
Less freight & selling Costs $3,544
Expenses
Potential Additional AE 49
No of years 2
Average annual operating costs $60
Total additional costs $5,880
Potential Opportunity Cost $28,813

Determination

[71]      Based on my findings I determine the compensation payable by the applicant Bowen

Basin Coal Pty Ltd to the respondent Namrog Investments Pty Ltd as follows:

Productivity $38,237
Fencing $15,000
Labour/stock management $1,250
Manager’s time $8,250
Opportunity cost $28,813
Cost, damage, loss $15,750
Total $107,300

Orders:

1.        I determine compensation in respect of MDL429 and MDL3001 in the sum of One Hundred and Seven Thousand, Three Hundred Dollars ($107,300).

2. The parties will be heard in relation to any application for determination of outstanding issues pursuant to section 96 of the Mineral and Energy Resources (Common Provisions) Act 2014. A request for such a hearing must be made no later than 15 business days after the delivery of these reasons.

levelling of drilling pads and digging sumps
earthworks associated with pipeline installation
bulk sampling
open trenching or costeaning with an excavator
vegetation clear-felling

constructing an exploration camp, concrete pad, sewage or water treatment facility or fuel dump

geophysical surveying with physical clearing
carrying out a seismic survey using explosives
constructing a track or access road
changing a fence line.
compensation. However, under s 96(3), the Land Court may decide the liability or future liability
(compensation) only to the extent it is not subject to a CCA.

does not—(c) affect a right, privilege or liability acquired, accrued or incurred under the Act; or …

(e) affect an investigation, proceeding or remedy in relation to a right, privilege, liability or penalty
mentioned in paragraph (c) or (d). Section 20(3) provides that the investigation, proceeding or
remedy may be started, continued or completed, and the right, privilege or liability may be enforced
and the penalty imposed, as if the repeal or amendment had not happened.

Breeders Currently Run (as

advised by manager) 1,700 1.35 2,295

[28]      There are seven land types identified on Vermont Park. The land type and areas are

“as per DNR Forage Report”. Forage is an online system that generates and distributes

information for rural lots on plan. The information in the table is not based on a site

inspection but is rather drawn from a range of physical, geographical and spatial

datasets.

[29]      The stocking rate, by land type, is expressed numerically as hectares per adult

equivalent (Ha/AE). By taking the area of a particular land type (in hectares) and

dividing it by the Ha/AE, the figure produced is the expected number of adult

equivalents that that pasturage can sustain.

[30]      If a paddock is all one land type, then the actual carrying capacity of that paddock is

easily calculated (x hectares divided by the Ha/AE figure). If however a paddock is

made up of a combination of land types, then the same calculation is done per land

type area and the total aggregated.

[31]      To more accurately determine land type in the affected paddocks, additional datasets

were overlaid. These datasets were the Land Type Mapping from the DNR Long

to Mr Thompson’s assessment of cumulative AE loss.