MAGISTRATES COURT OF THE AUSTRALIAN CAPITAL TERRITORY
Case Title: | Bost Civil Pty Ltd v Cornerstone Building Developments Australia Pty Ltd |
Citation: | [2022] ACTMC 27 |
Hearing Date: | 21 December 2022 |
Decision Date: | 21 December 2022 |
Before: | Magistrate Theakston |
Decision: | See [23] |
Catchwords: | BUILDING AND CONSTRUCTION – Application for summary judgment for defendant – contractual bar to make final payment claim – estoppel |
Legislation Cited: | Court Procedures Rules 2006 (ACT), r 1147 |
Cases Cited: | AGC Industries Pty Ltd v Karara Mining Ltd [2019] WASC 140 Bartier v Kounza Investments Pty Ltd [2003] QSC 390 Carlisle v Filara Pty Ltd [2002] ACTSC 33 John Goss Projects Pty Ltd v Leighton Contractors & Anor [2006] NSWSC 798 Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd [2015] HCA 37 Spencer v Commonwealth [2010] HCA 28 |
Parties: | Bost Civil Pty Ltd (Plaintiff) Cornerstone Building Developments Australia Pty Ltd (Defendant) |
Representation: | Counsel B Buckland (Plaintiff) J Hastie (Defendant) |
| Solicitors Mills Oakley (Plaintiff) Shand Taylor Lawyers (Defendant) | |
File Number: | CS 150 of 2022 |
MAGISTRATE THEAKSTON:
Introduction
The plaintiff claims a debt of approximately $240,000 from the defendant for civil works done in accordance with a construction contract. The defendant subsequently applied for summary judgment or, in the alternative, to have the pleadings in the statement of claim struck out.
Yesterday I refused the application, other than striking out paragraph [10] of the statement of claim – as the plaintiff abandoned its alternative claim of quantum meruit. These are my reasons.
Background
The defendant was the head contractor for the construction of a commercial building in Canberra. The plaintiff was contracted by the defendant to conduct civil earth works as part of that build. The defendant says the claim is doomed to fail because the contract requires any claim for payment to be made within a certain time, and the plaintiff made that claim two years after the relevant date.
The plaintiff says the contract is not clear about any such deadline and, in any event, the defendant should be estopped from relying on that provision due to an arrangement agreed between the parties and relied upon by the plaintiff.
Deadline to make final payment claim
Practical completion of the works was certified on 25 February 2019. The plaintiff pleads the final payment claim was subsequently provided to the defendant on 31 May 2022.
Clause 37.4 of the contract provided the mechanism for making payment of a final claim. It is informed by Item 31. Both provisions are reproduced below, with my emphasis added. The plaintiff is the Subcontractor, and the defendant is both the Main Contractor and the Subcontract Superintendent.
37.4 Final payment claim and certificate
In accordance with Item 31 the Subcontractor shall give the Subcontract Superintendent:
(a) a written final payment claim endorsed ‘Final Payment Claim’ being a progress claim together with all other claims whatsoever in connection with the subject matter of the Subcontract: and
(b) an executed…
Keep reading for free
Create a free CaseChat account to read Bost Civil Pty Ltd v Cornerstone Building Developments Austr... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2022] ACTMC 27
- Decision Date
CaseChat Overview and Summary
The court held that the plaintiff's claim was not absolutely hopeless and there was a prospect of its success. The court noted that there appeared to be factual issues that needed to be resolved before the case could proceed. The court also held that the plaintiff's pleadings needed to address the estoppel issue, which could be done within a reply. The court held that the defendant's application for summary judgment was not appropriate in the circumstances. The court noted that the authorities required a high degree of certainty before a plaintiff was summarily deprived of the opportunity to have its case properly tried. The court also held that the focus was on substance and not form, and that questions of fact were not to be decided in these applications.
The court made several orders in relation to the defendant's application. Paragraph 10 of the plaintiff's statement of claim was struck out, and the defendant's application for summary judgment was dismissed. The plaintiff was ordered to pay the defendant's costs of the application, and to file and serve any reply by the end of January 2023. The matter was listed on 21 February 2023 in the Registrar's List, and the defendant was given leave to appear by audio-visual link.
Orders
Orders of the court
See [23]
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.