Boral Resources (Qld) Pty Ltd v Gold Coast City Council

Link copied
Case Copied 61 min read

PLANNING & ENVIRONMENT COURT
OF QUEENSLAND

CITATION:

Boral Resources (Qld) Pty Ltd v Gold Coast City Council & Ors [2012] QPEC 53

PARTIES:

BORAL RESOURCES (QLD) PTY LIMITED
ABN 46 009 671 809

(appellant)

v

GOLD COAST CITY COUNCIL
(respondent)

and

CHIEF EXECUTIVE, DEPARTMENT OF TRANSPORT AND MAIN ROADS
(co-respondent by election)

and

ROBERT BLUCHER
(co-respondent by election)

and

ROBYN BLUCHER
(co-respondent by election)

and

WILLIAM BLUCHER
(co-respondent by election)

and

PETER LEHMANN
(co-respondent by election)

and

TIM GREGG
(co-respondent by election)

FILE NO:

4699/11

DIVISION:

PROCEEDING:

Preliminary Hearing

ORIGINATING COURT:

Brisbane

DELIVERED ON:

21 September 2012

DELIVERED AT:

Brisbane

HEARING DATE:

20-21 August 2012

JUDGE:

Robin QC, DCJ

ORDER:

Preliminary points determined favourably to the appellant, so that its conditions appeal might proceed to a hearing on the merits

CATCHWORDS:

Integrated Planning Act 1997 s3.2.1(5)

Integrated Planning Regulation 1998 Schedule 10 Items 14, 15

Sustainable Planning Act 2009 s820

Water Act 2000 definitions of “water” and “watercourse”

Conditions appeal by developer quarry operator – co-respondents raise allegations ordered to be determined as preliminary issues as to whether development application “properly made” – Pimpama Creek, a water course, constituted a boundary of the site – course of creek changed (apparently imperceptibly) since boundaries surveyed – “ambulatory boundary” situation that may have existed in early years did not persist – water course diverted by works by appellant (or a predecessor) about 1983 – this controlled the location of the water course as a matter of fact – co-respondents contended proposal involved State resources, by taking water and/or quarry material, either under the proposal or under Council’s imposed conditions requiring rehabilitation of Pimpama Creek and surrounds by removal of large quantities of fill – issues whether certain gullies were water courses on the site – “lapsing” issue whether failure to start quarrying on one of two lots pursuant to entitlements dating from 2004 was fatal to the current development application for expansion – issues whether existing licences under the Water Act were appropriate and whether this is relevant in any event

COUNSEL:

Mr D. R. Gore QC and Mr J. G. Lyons for the appellant

Mr T. Law for the respondent

Mr P. Lehmann for the first, second, third and forth co-respondents by election

Mr T. Gregg for the fifth co-respondent by election

SOLICITORS:

Ashurst for the appellant

King & Company for the respondent

Mr Lehmann representing himself and the first, second and third co-respondents by election

Mr Gregg representing himself

  1. The appellant wishes to expand its established quarry at Upper Ormeau Road, Kingsholme.  Its development application made in March 2008 resulted in the desired development permit for material change of use for extractive industry and environmentally relevant activities (negotiated decision notice dated 20  October 2011), but the Council imposed conditions which the appeal seeks to have changed.  The development application was impact assessable.  Adverse submitters included the five co-respondents by election.  Mr Gregg has been self represented.  Mr Lehmann has represented himself and the others.  He raised issues in an affidavit…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Boral Resources (Qld) Pty Ltd v Gold Coast City Council and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2012] QPEC 53
Decision Date

CaseChat Overview and Summary

In the case of Boral Resources (Qld) Pty Ltd v Gold Coast City Council, the developer, Boral Resources, appealed against the conditions imposed on its development application by the Gold Coast City Council. The development application was for the expansion of a quarry located adjacent to Pimpama Creek. The dispute centred around the interpretation of the site's boundaries and the appropriateness of the conditions set by the Council, particularly those related to the environmental rehabilitation of the area, including the creek. The Council argued that the development involved state resources and questioned whether certain gullies on the site were watercourses, thereby subject to stricter environmental regulations.

The legal issues before the court were multifaceted, involving the determination of the site's boundaries, the validity of the development application, the relevance of existing licenses under the Water Act, and the implications of the Council's conditions on the project's feasibility. A key point of contention was whether the course of Pimpama Creek, which had apparently changed since the initial survey, constituted a boundary of the site. The Council also raised concerns about the environmental impact of the proposed development on the creek and surrounding areas.

The court addressed the preliminary issues in favour of Boral Resources, allowing the conditions appeal to proceed to a hearing on the merits. The court determined that the development application was properly made and that the Council's allegations regarding the boundaries and the nature of the site did not preclude the appeal from proceeding. The court found that the changes to the creek's course, as well as the historical works by Boral Resources or its predecessor, were factual matters that did not invalidate the development application. Additionally, the court ruled that the existing licenses under the Water Act were not determinative of the current appeal, and the alleged failure to commence quarrying on one of the lots did not render the development application invalid.

Orders

Orders of the court

Preliminary points determined favourably to the appellant, so that its conditions appeal might proceed to a hearing on the merits

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established