Reported Decision: 124 LGERA 90
Land and Environment Court
of New South Wales
CITATION: Boral Resources (NSW) Pty Limited v Wingecarribee Shire Council [2003] NSWLEC 39 PARTIES: APPLICANT:
RESPONDENT:
Boral Resources (NSW) Pty Limited
ACN 000 756 507
Wingecarribee Shire CouncilFILE NUMBER(S): 40570 of 2002 CORAM: Lloyd J KEY ISSUES: Development Consent :- lapse - commencement - preparatory works - works carried out pursuant to conditions of development consent
LEGISLATION CITED: Environmental Planning and Assessment Act 1979 s 95 CASES CITED: Auburn Municipal Council v F.N.Eckold Pty Ltd (1974) 34 LGRA 101;
Bell v Minister for Urban Affairs and Planning & Anor (1997) 95 LGERA 86;
Captain Cook Cruises v North Sydney Council [2002] NSWLEC 243;
Drummoyne Municipal Council v Lebnan & Ors (1974) 131 CLR 350;
Iron Gates Developments Pty Ltd v Richmond-Evans Environmental Society Inc (1992) 81 LGERA 132;
Liverpool City Council v Home Units Australia Pty Ltd (1973) 28 LGRA 28;
North Sydney Council v Ligon 302 Pty Ltd (1996) 185 CLR 470, 91 LGERA 352;
Smith v Wyong Shire Council [No. 3] (1984) 53 LGRA 170DATES OF HEARING: 20/12/2002 DATE OF JUDGMENT:
02/21/2003LEGAL REPRESENTATIVES: RESPONDENT:
APPLICANT:
Mr M G Craig QC with him Mr I J Hemmings (barrister)
SOLICITORS:
Hunt & Hunt
Mr M H Tobias QC with him Ms J M Jagot (barrister)
SOLICITORS:
B Bilinsky & Co
JUDGMENT:
IN THE LAND AND
ENVIRONMENT COURT
OF NEW SOUTH WALES
40570 of 2002
21 February 2003Lloyd J
Boral Resources (NSW) Pty Limited
ACN 000 756 507
- Applicant
- Respondent
- Introduction
1. The applicant claims a declaration that a development consent granted by the Court on 11 February 1991 has not lapsed. A development consent lapses five years after the date from which it operates: s 99(1), Environmental Planning and Assessment Act 1979, as in force in February 1996 – since re-enacted as s 95(1) in the Act as presently in force. The parties agree that the question of whether the consent has lapsed must be answered as at 11 February 1996, being five years after the consent was granted by the Court.
2. Section 99(4) of the Environmental Planning and Assessment Act 1979 (“the EP&A Act”) as in force in February 1996 relevantly provides as follows:
- Development consent for:
- (a) the erection of a building, or
(b) the subdivision of land, or
(c) the carrying out of a work,
The Relevant Facts
3. On 11 February 1991 the Land and Environment Court granted development consent as follows:
- Development consent be granted for the application to establish a hard rock quarry, processing area and the transportation of…
Keep reading for free
Create a free CaseChat account to read Boral Resources (NSW) Pty Limited v Wingecarribee Shire Coun... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2003] NSWLEC 39
- Decision Date
CaseChat Overview and Summary
The court had to determine if the preparatory works were indeed "engineering or construction work relating to" the development and if they were carried out on the land to which the consent applied. Boral Resources argued that the preparatory works were integral to the development and were carried out on the land specified in the consent. Conversely, the Wingecarribee Shire Council contended that the preparatory works were merely preliminary and not part of the approved development, and thus could not prevent the consent from lapsing.
The court found that the preparatory works were indeed "engineering or construction work relating to" the development, as they were expressly required by the conditions of the consent and integral to the construction of the quarry. The court rejected the council's argument that these works were merely preparatory and not part of the approved development. Furthermore, the court held that the preparatory works were carried out on the land to which the consent applied, as they were necessary for the construction of the quarry and specified in the conditions of the consent. Therefore, the court concluded that the development consent had not lapsed as the preparatory works were commenced prior to the expiration date. The court made a declaration that the development consent had not lapsed and reserved the question of costs.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi