SUPREME COURT OF QUEENSLAND
CITATION: Body Corporate for the Johnson CTS 49098 v Maxcon Constructions Pty Ltd [2024] QSC 65 PARTIES: BODY CORPORATE FOR THE JOHNSON CTS 49098
(plaintiff)
v
MAXCON CONSTRUCTIONS PTY LTD
ACN 152 259 820
(defendant)FILE NO: BS 10826 of 2022 DIVISION: Trial Division PROCEEDING: Application ORIGINATING COURT:
Supreme Court at Brisbane
DELIVERED ON: 20 May 2024 DELIVERED AT: Brisbane HEARING DATE: 9 February 2024 JUDGE: Martin SJA ORDER: THE APPLICATION IS DISMISSED. CATCHWORDS: PROCEDURE – CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS – JOINDER OF CAUSES OF ACTION AND OF PARTIES – PARTIES – GENERALLY – where the plaintiff, a body corporate for a community title scheme, alleges that the then owner of the land contracted with the defendant to undertake design and construction works – where the plaintiff alleges that it is subrogated to the rights of the original owner under the contract – where the plaintiff alleges both the design and construction works were defective – where defendant’s defence pleads that the design and construction agreement was a sham – where the defendant pleads that the then owner, not the defendant, engaged design consultants – where the plaintiff applies to join a new defendant – where the plaintiff alleges, in the alternative, that the proposed defendant undertook the design work – where the proposed defendant argues there is no evidence of a sham or of the proposed defendant’s involvement – whether the proposed defendant should be joined to the proceeding
PROCEDURE – CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS – JOINDER OF CAUSES OF ACTION AND OF PARTIES – MATTERS RELATING TO LIMITATION PERIOD – where proposed defendant argues application to join brought outside limitation period – whether application to join falls within provisions of r 69(2) Uniform Civil Procedure Rules 1999 (Qld)Limitation of Actions Act 1974 (Qld), s 38
Uniform Civil Procedure Rules 1999 (Qld), r 69(1), r 69(2), r 74
Allianz Australia Insurance Ltd v Haddad [2015] NSWCA 186, cited
Aqwell Pty Ltd v BJC Drilling Services Pty Ltd [2007] QSC 140, distinguished
Hutchinson v Equititour Pty Ltd [2011] 2 Qd R 99; [2010] QCA 104, cited
IMDM (Townsville) Pty Ltd v City Pacific Ltd [2009] QSC 445, cited
Interline Hydrocarbon Inc v Brenzil Pty Ltd [2006] 2 Qd R 454; [2006] QSC 184, considered
Kestrel Coal Pty Ltd v Longwall Roof Supports Ltd [2003] QSC 187, cited
Universal Music Australia Pty Ltd v Cooper [2004] FCA 78, citedCOUNSEL: M C Long for the plaintiff
B W J Kidston for the defendant
B A Reading for Asian Pacific Building CorporationSOLICITORS: Robinson Locke for the plaintiff
Diakou Faigen for the defendant
McCullough Robertson for Asian Pacific Building Corporation
The plaintiff (Johnson) applies to join Asian Pacific Building Corporation (AP Building) as the second defendant in this proceeding and seeks leave to amend the Claim and Statement of Claim. Questions concerning limitation periods arise and, so, it is necessary to give some detail…
Keep reading for free
Create a free CaseChat account to read Body Corporate for the Johnson CTS 49098 v Maxcon Constructi... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2024] QSC 65
- Decision Date
CaseChat Overview and Summary
The court was required to decide two key legal issues. Firstly, whether AP Building should be joined as a party to the proceeding. Secondly, whether the application to join AP Building fell within the provisions of rule 69(2) of the Uniform Civil Procedure Rules 1999 (Qld), given that AP Building argued that the application was brought outside the limitation period. The court considered various factors in making its decision, including the consequences of delay, the difficulty of obtaining evidence due to the passage of time, and the deficiencies in the pleadings.
The court found that the application to join AP Building should be dismissed. The court found that the application was brought outside the limitation period, and that there was no evidence to suggest that AP Building's involvement in the alleged sham or design work could not have been discovered sooner. The court also found that the deficiencies in the pleadings, while reasonable criticisms, could be cured by appropriate particulars if AP Building was joined. The court found that the passage of time and the difficulty of obtaining evidence were not sufficient to warrant joining AP Building, and that the consequences of delay were the more relevant factor. Therefore, the court dismissed the application to join AP Building.
The court dismissed the application to join AP Building. This decision is final and binding on the parties involved in the dispute.
Orders
Orders of the court
THE APPLICATION IS DISMISSED.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.