Body Corporate for the Johnson CTS 49098 v Maxcon Constructions Pty Ltd

Link copied
Case Copied 16 min read

SUPREME COURT OF QUEENSLAND

CITATION: Body Corporate for the Johnson CTS 49098 v Maxcon Constructions Pty Ltd [2024] QSC 65
PARTIES: BODY CORPORATE FOR THE JOHNSON CTS 49098
(plaintiff)
v
MAXCON CONSTRUCTIONS PTY LTD
ACN 152 259 820
(defendant)
FILE NO: BS 10826 of 2022
DIVISION: Trial Division
PROCEEDING: Application

ORIGINATING COURT:

Supreme Court at Brisbane

DELIVERED ON: 20 May 2024
DELIVERED AT: Brisbane
HEARING DATE: 9 February 2024
JUDGE: Martin SJA
ORDER: THE APPLICATION IS DISMISSED.
CATCHWORDS:

PROCEDURE – CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS – JOINDER OF CAUSES OF ACTION AND OF PARTIES – PARTIES – GENERALLY – where the plaintiff, a body corporate for a community title scheme, alleges that the then owner of the land contracted with the defendant to undertake design and construction works – where the plaintiff alleges that it is subrogated to the rights of the original owner under the contract – where the plaintiff alleges both the design and construction works were defective – where defendant’s defence pleads that the design and construction agreement was a sham – where the defendant pleads that the then owner, not the defendant, engaged design consultants – where the plaintiff applies to join a new defendant – where the plaintiff alleges, in the alternative, that the proposed defendant undertook the design work – where the proposed defendant argues there is no evidence of a sham or of the proposed defendant’s involvement – whether the proposed defendant should be joined to the proceeding
PROCEDURE – CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS – JOINDER OF CAUSES OF ACTION AND OF PARTIES – MATTERS RELATING TO LIMITATION PERIOD – where proposed defendant argues application to join brought outside limitation period – whether application to join falls within provisions of r 69(2) Uniform Civil Procedure Rules 1999 (Qld)

Limitation of Actions Act 1974 (Qld), s 38
Uniform Civil Procedure Rules 1999
(Qld), r 69(1), r 69(2), r 74
Allianz Australia Insurance Ltd v Haddad [2015] NSWCA 186, cited
Aqwell Pty Ltd v BJC Drilling Services Pty Ltd
[2007] QSC 140, distinguished
Hutchinson v Equititour Pty Ltd [2011] 2 Qd R 99; [2010] QCA 104, cited
IMDM (Townsville) Pty Ltd v City Pacific Ltd
[2009] QSC 445, cited
Interline Hydrocarbon Inc v Brenzil Pty Ltd [2006] 2 Qd R 454; [2006] QSC 184, considered
Kestrel Coal Pty Ltd v Longwall Roof Supports Ltd [2003] QSC 187, cited
Universal Music Australia Pty Ltd v Cooper [2004] FCA 78, cited

COUNSEL: M C Long for the plaintiff
B W J Kidston for the defendant
B A Reading for Asian Pacific Building Corporation
SOLICITORS: Robinson Locke for the plaintiff
Diakou Faigen for the defendant
McCullough Robertson for Asian Pacific Building Corporation
  1. The plaintiff (Johnson) applies to join Asian Pacific Building Corporation (AP Building) as the second defendant in this proceeding and seeks leave to amend the Claim and Statement of Claim. Questions concerning limitation periods arise and, so, it is necessary to give some detail…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Body Corporate for the Johnson CTS 49098 v Maxcon Constructi... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2024] QSC 65
Decision Date

CaseChat Overview and Summary

The matter before the court involved a dispute between a body corporate, Body Corporate for the Johnson CTS 49098, and Maxcon Constructions Pty Ltd, as well as an application by the body corporate to join AP Building as a party to the proceedings. The body corporate, which represents a community title scheme, alleged that the previous owner of the land had contracted with Maxcon to undertake design and construction works, and that both the design and construction were defective. The body corporate sought to be subrogated to the rights of the original owner under the contract and bring a claim against Maxcon. In response, Maxcon pleaded that the design and construction agreement was a sham, and that the previous owner, not Maxcon, engaged design consultants. The body corporate then applied to join AP Building, alleging that AP Building may have been involved in the design work. AP Building argued against being joined, stating that there was no evidence of a sham or of its involvement.

The court was required to decide two key legal issues. Firstly, whether AP Building should be joined as a party to the proceeding. Secondly, whether the application to join AP Building fell within the provisions of rule 69(2) of the Uniform Civil Procedure Rules 1999 (Qld), given that AP Building argued that the application was brought outside the limitation period. The court considered various factors in making its decision, including the consequences of delay, the difficulty of obtaining evidence due to the passage of time, and the deficiencies in the pleadings.

The court found that the application to join AP Building should be dismissed. The court found that the application was brought outside the limitation period, and that there was no evidence to suggest that AP Building's involvement in the alleged sham or design work could not have been discovered sooner. The court also found that the deficiencies in the pleadings, while reasonable criticisms, could be cured by appropriate particulars if AP Building was joined. The court found that the passage of time and the difficulty of obtaining evidence were not sufficient to warrant joining AP Building, and that the consequences of delay were the more relevant factor. Therefore, the court dismissed the application to join AP Building.

The court dismissed the application to join AP Building. This decision is final and binding on the parties involved in the dispute.

Orders

Orders of the court

THE APPLICATION IS DISMISSED.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

AP Building proposes a number of discretionary matters which would tell against granting an order that it be joined.There is no evidence to explain why Johnson could not have discovered the alleged “sham” sooner. Mr Long submits that, before the Defence was filed, Johnson had no knowledge of and no way of knowing about the “sham contract”. That, though, does not explain the delay in commencing the action – one day before the limitation period expired. While delay is a matter to be taken into account, the more relevant factor is the consequences of delay.Passage of time and prejudice Mr Faigen is a solicitor and the Group Counsel and Development Director of the Deague Group of Companies of which AP Building is a part. In his affidavit he gives evidence of attempts to “obtain access to the books and records (both electronic and hard copy) maintained by Asian Pacific Corporation from the period at or about the time of the Project the subject of the D&C Contract.” He gives evidence of contacting 5G Networks, a company contracted by Asian Pacific Building as “an external information technology service provider.” While he could not recall the name of the person he spoke to, he was informed that, “given the passage of time since the Project was complete” “limited documentary records in electronic form relating to the Project exist”, some documents may “not have been retained in electronic form” and 5G Networks’ attempts to retrace the records were still taking place at the time of making his affidavit. The evidence is equivocal. It does not go so far as to say that documents cannot be obtained, only that it may be difficult to do so. It cannot go unnoticed that one of AP Building’s directors was involved with the creation of the “sham” contract. There is nothing to suggest that he is unavailable or unable to give instructions on these matters.The pleading is deficient Mr Reading pointed to two aspects of the pleading as being deficient: (a)first, schedule 1 of the Statement of Claim outlines the alleged defects and labels a series of defects as both design and construction defects. He argued that A P Building “can’t identify on the face of this what design of [AP Building] is said to be defective or why” and further, that “there’s no allegation here that references a drawing apparently authored by [AP Building]”. (b)secondly, schedules 3 to 5 provide tables of alleged rectification costs, consultants’ costs, and scheme land damage and rectification costs, respectively. Mr Reading submitted, with respect to sch 5, that “it’s impossible, on the face of this schedule, to tell whether or not it’s alleged that [AP Building’s] design caused this defect and how, if that’s what’s alleged, or whether it’s a construction defect.” Both of those are reasonable criticisms but do not make the pleading irreparable and, if AP Building is joined, can be cured by appropriate particulars. None of the matters advanced under this heading are of such a magnitude as to require a refusal of the application.Can Johnson be subrogated to the extent that it can sue on the design work?

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.